Fulton Electropack 100 kW User manual

Type
User manual
This manual must be available to the boiler operator at all times. EP100-IOMM-2017-11
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Electropack 100 kW
Electric Steam Boiler
(Step Controlled)
EP100-IOMM-2017-11
Fulton Ltd
Page II
EP100-IOMM-2017-11
Fulton Ltd
Page III
TABLE OF CONTENTS
SECTION 1 - INTRODUCTION
1.1 General 1
1.2 Technical Data 1
1.3 Product Overview 1
SECTION 2 - INSTALLATION
2.1 General 5
2.2 Pre-Installation 5
2.2.1 Siting 6
2.3 Boiler Connections 6
2.3.1 Steam Safety Valves 7
2.4 Water Supply 8
2.5 Electrical Requirements 8
2.6 Commissioning the Boiler 10
2.7 Cleaning Steam Lines and Pressure Vessels 13
SECTION 3 - OPERATION
3.1 General 15
3.2 Controls 15
3.2.1 Boiler Control Panel 16
3.2.2 Steam Pressure Controls 18
3.2.2.1 Setting Steam Pressure Controls 19
3.2.2.2 Step Controller 20
3.2.2.3 Step Controller Indicator Lights 21
3.3 Filling The Boiler 22
3.4 Draining the Boiler 23
3.5 Boiler Start-Up (from cold)-all models 24
3.6.1 Boiler Start-Up Following short term Shut-Down 24
3.6 Boiler Shut-Down 25
3.6.1 Short Term Shut-Down (hours) 25
3.6.2 Long Term Shut-Down (weeks) 25
Electrical diagrams supplied separately
SECTION 4 - MAINTENANCE
4.1 Visual Checks 27
4.2 Water Level and Low Water Safety Controls 28
4.2.1 Feedwater Pump Test 28
4.2.2 Low Water Level Checks 29
4.2.3 Evaporation Check 29
4.3 Blowdown Procedures 30
4.3.1 Main Boiler Blowdown 30
4.3.2 Water Level Gauge (Sight Glass) Blowdown 30
4.4 Boiler Internal Inspection 31
4.5 Fitting New Gaskets To Boiler Inspection Holes 32
4.5.1 Important Information 32
4.5.2 Fitting Procedure 33
4.6 Element Care and Protection 34
4.6.1 Element Removal 35
4.7 Cleaning Water Level Probes 36
4.8 Schedule of Operator Tests and Checks 37
4.8.1 Daily 38
4.8.2 Weekly-in addition 38
4.8.3 Monthly-in addition 38
4.8.4 Three Monthly-in addition 39
4.9 Maintenance Record Keeping 40
4.10.1 Troubleshooting-boiler 41
4.10.2 Troubleshooting-feedwater pump 42
4.10.2 Troubleshooting-feedwater pump 43
APPENDIX A - TI SHEETS
 EP100Dimensions&Specication 46
EP Probe Lengths 48
Recommended Water Conditions 50
High Integrity Water Level Controls 51
Water Level Probes 52
Auto TDS Blowdown Systems 54
Auto TDS Blowdown System Install Guide 56
Auto Timed Blowdown System 58
EP100-IOMM-2017-11
Fulton Ltd
Page IV
WARNINGS
The Pressure System Safety Regulations 2000
Fulton boilers fall within the scope of the Pressure Systems Examination Scheme.
Regular inspections are therefore required by a competent person.
The scope of the examination and the actual intervals between examinations is at the discretion of the competent
person.
It is the responsibility of the user to provide a written scheme of examination for those parts of the system in which
a defect may give rise to danger.
Instructions in this manual are provided for the safe operation and maintenance of the boiler and do not cover
periodic statutory inspections.
For further information contact:
(a) SAFed
SAFETY ASSESSMENT FEDERATION Limited.
Nutmeg House,
60 Gainsford Street,
Butlers Wharf,
London, SE1 2NY.
(b) HealthandSafetyExecutivelocalofce.
(c) Your Competent Person.
For your safety!
The following WARNINGS, CAUTIONS and NOTES appear in various sections of this manual.
 WARNINGS must be observed to prevent serious
injury or death to personnel.
 CAUTIONS must be observed to prevent damage
or destruction of equipment or loss of operating
effectiveness.
 Notes: must be observed for essential and
effective operating procedures, conditions and as
a statement to be highlighted.
It is the responsibility and duty of all personnel involved
in the operation and maintenance of this equipment
to fully understand the WARNINGS, CAUTIONS and
NOTES by which hazards are to be eliminated or
reduced.
Personnel must become familiar with all aspects of
safety and equipment prior to operation or
maintenance of the equipment.
CAUTION
In case of emergency
This boiler has been designed and constructed to meet all of the essential requirements of the applicable
European Directives and subject to proper maintenance should not give occasion to any hazardous conditions.
If such a condition should occur during commissioning or during subsequent operation of this product,
regardless of the cause, then the electrical supply to the boiler should be isolated immediately, until the fault
hasbeeninvestigatedbyacompetentpersonandrectied.
!
WARNING
Steam boilers are a potential hazard, possibly fatal if not properly maintained.
CAUTION
It is vitally important that the instructions given in this manual are strictly adhered to. Failure to carry
out the routine maintenance checks could result in a drastic reduction in the life expectancy of the

!
!
EP100-IOMM-2017-11
Fulton Ltd
Page V
WARNINGS
SAFETY
The instructions provided for the operation and maintenance of the boiler MUST be observed. Failure to do so could result in
damage to the heater and serious personal injury.
WARNING
Do not try to do repairs or any other maintenance work
you do not understand. Obtain a service manual from
Fulton Ltd or call a Fulton service engineer.
It is the responsibility of the installer to ensure all parts
suppliedwiththeboilerarettedinacorrectandsafe
manner.
Understand the electrical circuit before connecting
or disconnecting an electrical component. A wrong
connection can cause injury and or damage.
A defective boiler can injure you or others. Do not
operate a boiler which is defective or has missing
parts. Make sure that all maintenance procedures are
completed before using the boiler.
LIFTING EQUIPMENT
Make sure that lifting equipment complies with all local
regulations and is suitable for the job. You can be injured
if you use faulty lifting equipment. Make sure the lifting
equipment is in good condition.
Operating the boiler beyond its design limits can damage
the boiler, it can also be dangerous. Do not operate the
boiler outside its limits. Do not try to upgrade the boiler
performancebyunapprovedmodications.
Non-approvedmodicationscancauseinjuryand
damage. Contact your Fulton dealer before modifying
the boiler.

operate and maintain the boiler and its equipment.
Boilers should always be drained through an approved
blowdown vessel.
Prior to the commencement of any work requiring the
removal of cover plates and the opening of control panel
box, the electrical supply to the boiler must be isolated.
Steam boilers have high temperature surfaces, that if
touched may cause serious burns. Only competent and
qualiedpersonnelshouldworkonorinthelocalityof
a steam boiler and ancillary equipment. Always ensure
theworkingareaandoorareclearofpotentialhazards,
work slowly and methodically.
DoNOTstoreinammablematerialsneartheboiler.
The importance of correct boiler water and feedwater
cannot be over emphasised, see the relevant section in
this manual.
!
CAUTION
Obey all laws and local regulations which affect you and
your boiler.
LOW FEEDWATER TEMPERATURE
Low feedwater temperature can result in thermal shock
to the boiler pressure vessel. Return the maximum
amount of condensate and if necessary preheat the
feedwater. If in doubt consult Fulton Ltd.
WATER SOFTENER and CHEMICAL TREATMENT
The chemicals required to operate the water softeners
and chemical treatment plants CAN BE SUPPLIED by
Fulton Ltd.
It is the responsibility of the operator to ensure adequate
supplies of chemical are available at all times
(including commissioning). Costly repairs could be
required should the plant operate without chemicals or
the wrong dosage of chemicals.
HYDRAULIC TEST - RISK OF BRITTLE FRACTURE
Hydraulic testing requires specialist equipment and
is normally only required by engineering surveyors /
inspectors. In order to ensure the material/ pressure
vessel does not suffer from brittle fracture, hydraulic
testing should not be carried out below 7 °C.
!
EP100-IOMM-2017-11
Fulton Ltd
Page VI
EP100-IOMM-2017-11
Fulton Ltd
Page 1
INTRODUCTION - 1
SECTION 1 - INTRODUCTION
1.1 GENERAL
1.2 TECHNICAL DATA
Forafullspecicationreferto
The Fulton Electropack electric steam boiler service manual is a generic publication, providing
information on standard boiler operation and maintenance.
Every care has been taken in the manufacture of the boiler to ensure that quality and reliability
standards are maintained. Satisfactory performance can only be ensured if the installation
recommendations, operating routines and maintenance schedules laid out in this manual are
adhered to.
Particular attention should be paid to electrical installation and water treatment.
1.3 PRODUCT OVERVIEW
TheFultonElectropack100kWelectricsteamboilerisahighlyefcientunitdesignedtomeetthe
requirements of the lower demand steam user.
The Electropack 100 kW contains a pressure vessel, feedwater pump and system controls
including a step controller to automatically switch elements on and off with steam demand to
create a fully contained steam raising unit with easy access removable cabinet panels
The Electropack 100 kW is similar to the Electropack 18-72 kW range with differences such as a
larger pressure vessel and elements entering from the top of the boiler instead of the front. The
100 kW does not have a self contained feedwater tank like the 18-72 kW range due to the larger
pressure vessel. Feedwater and condensate return tanks can be supplied separately.
CONTINUED ON NEXT PAGE
EP100-IOMM-2017-11
Fulton Ltd
Page 2
INTRODUCTION - 1
Figure. 1 - General Arrangement
17
1
2
3
7
8
9
10
11
12
13
14
15
16
EP100-IOMM-2017-11
Fulton Ltd
Page 3
INTRODUCTION - 1
1. Boiler control panel
2. Control panel lock
3. Boiler door isolator switch
4. Feedwater pump
5. Operating pressure control switch
6. High limit pressure control switch
7. Water level gauge (optional)
8. Water level gauge blowdown valve
9. Steam pressure gauge
10. Side access panel
11. Front access panel
12. Main steam stop valve
13. Boiler steam safety valve
14. Boiler water sample point
15. Feedwater check and isolating valves
16. Main boiler blowdown valve
17. Feedwater inlet
18. Water level probes
19. Boiler elements
20. Pressure vessel
Key
4
5
6
19
18
20
Figure. 2 - General Arrangement Inside
EP100-IOMM-2017-11
Fulton Ltd
Page 4
EP100-IOMM-2017-11
Fulton Ltd
Page 5
INSTALLATION - 2
2.1 GENERAL
SECTION 2 - INSTALLATION
2.2 PRE-INSTALLATION
Prior to delivery of the boiler, consideration should be given to the following:
(Planning regulations may call for more consents than those listed below, always check with your
Local Planning Authority).
A. Local Planning consents where appropriate.
B. Consideration given to access for delivery and positioning of the boiler.
C. Preparation of a suitable base, which must be able to support the total weight of the system
under operating conditions.
The locations of services to the site required for the system, under operating conditions.
D. Electricity supply, check the loading required/available.
E. Drainage system, check the suitability of the drainage system.
F. Local regulations for discharge into existing drains.
G. Suitable access for delivery and off-loading.
H. Safe access to the plant when installation is complete.
The installation of the Fulton Electropack electric steam boiler should be carried out by competent
personnel in accordance with all relevant safety regulations. It is the responsibility of the installer
to ensure that these regulations are complied with.
EP100-IOMM-2017-11
Fulton Ltd
Page 6
INSTALLATION - 2
2.2.1 SITING
Theboilerhouseshouldbesufcientlysizedtoalloweasyandsafeaccesstoallpartsofthe
boiler for operational and maintenance purposes.
Reference should be made to to
ascertain the relevant dimensions and weights, special note should be taken of the required
clearance for maintenance.
Theooringmustbelevel,laidinanon-combustiblematerialandbeofsufcientstrengthto
support the boiler.
All connections for services are mounted at the rear of the boiler.
For connection sizes, refer to .
1. Feedwater Inlet
Anisolatingvalveanddisctypenon-returnvalvearesuppliedttedtotheboiler.Thisshouldbe
connected to the feedwater pump discharge which is mounted inside the cabinet.
2. Steam Safety Valve Discharge
The outlet from this valve should be piped to a safe discharge point and the piping should be
so arranged that condensate trapped in the discharge pipe is drained away from the valve.
3. Steam Outlet Valve
4. Boiler Blowdown Valve
Connection must be made from the Blowdown valve to a blowdown receptacle of approved
design. Regulations exist covering such items and care must be taken to ensure compliance with
these regulations. If in any doubt regarding blowdown arrangements consult Fulton Ltd.
5. Water Sample Outlet
Ifthewatersampleoutletisused,thevalveshouldbettedascloseaspossibletotheboiler.To
take a sample safely, a water sample cooler (not supplied as standard) should be installed.

The water level gauge blowdown cock should be connected to the auxiliary blowdown line from
the blowdown valve by 3/8 in. soft copper tubing.
CAUTION

be altered. This valve is provided as a safety device for the boiler and should not be used as the sole
protection for other equipment using steam from the boiler.
!
2.3 BOILER CONNECTIONS
EP100-IOMM-2017-11
Fulton Ltd
Page 7
INSTALLATION - 2
Figure. 3 - Boiler Connection Points
2.3.1 STEAM SAFETY VALVES
Safetyvalvesarefactoryttedandpre-set,theyMUSTNOTbeadjusted.Thedischargeoutlet
should be piped to a safe discharge point and the piping so arranged that any condensate
trapped in the pipework will drain away from the valve.
Note: It is recommended that the safety valve discharge pipework is installed to the requirements of BS806
clause 4.9.7. / BSEN 134801-1:2002
a) The lift pressure is indicated on the safety valve 
b) Thesafetyvalvettedtotheboilerisdesignedtopreventtheboilerexceedingitsdesign
pressure.
c) Any system connected to the boiler not capable of accepting boiler pressure must be protected
by a separate safety valve set to the required pressure.
WARNING

other items not capable of accepting boiler pressure.
!
1
23
4
5
6
EP100-IOMM-2017-11
Fulton Ltd
Page 8
INSTALLATION - 2
2.5 ELECTRICAL REQUIREMENTS
The quality of the water used in the boiler will affect the life and performance of the boiler and
elements.
Feedwater contains solids and dissolved gases, these may promote encrustations of scale;
foaming, priming, surging; corrosion and pitting; or caustic embrittlement. To prevent this
happening it is strongly recommended that a reputable water treatment concern is consulted prior
to commissioning the boiler.
Note: See Appendix A - TI-139-Recommended Water Conditions.
Note: Elements damaged due to adverse water conditions cannot be replaced under guarantee. Should chemical
dosage of the boiler feedwater be required a connection point and a water sampling point are provided at the rear
of the boiler.
2.4 WATER SUPPLY
CAUTION
WATER SOFTENER and CHEMICAL TREATMENT
The chemicals required to operate the water softeners and chemical treatment plants
CAN BE SUPPLIED by Fulton.
It is the responsibility of the operator to ensure adequate supplies of chemical are available

Costly repairs could be required should the plant operate without chemicals or the wrong
dosage of chemicals.
!
An individual wiring diagram for the boiler is located with the control panel. When referring to the
electricalspecicationoftheboiler,thewiringdiagramnumbershouldbequoted.
The power ratings and requirements are given in Appendix A - TI-130-EP100 Dimensions &
. The boiler contains all necessary electrical protection.
A suitable 3-phase, neutral and earth isolated and fused supply is required and must be
connected in accordance with local electrical regulations.
Anelectricalisolatorshouldbesecurelyttedascloseaspossibletotheboiler.
It is recommended that the electrical supply cable to the boiler is located through the rear of the
unit in the bottom left corner. Ensure the cable is not rubbing against areas capable of damaging
it.Thecableshouldberoutedfromthispointandsecuredinaglandnut(notsupplied)ttedthe
bulkhead at the base of the electrical panel.
Care should be taken to ensure the supply cable is the correct size and installed in accordance
with local regulations.
EP100-IOMM-2017-11
Fulton Ltd
Page 9
INSTALLATION - 2
3
2
10
5
4
1
6
9
7
8
Figure. 4 - Electrical Panel
1. Miniature relays
2. MCB
3. Door electrical isolator (supply cable connection point)
4. LC relays
5. Element circuit breakers
6. Cooling fan
7. Fuse terminal
8. Step controller
9. Pump circuit breakers
10. Element contactors
11. Pump contactor
12. Pump overload
13. Supplycableaccesshole(twithglandnutsuitablefortheelectricalsupplycableused)
14. LOGO! PLC. (pressure controls)
Key
11
12
13
14
EP100-IOMM-2017-11
Fulton Ltd
Page 10
INSTALLATION - 2
2.6 COMMISSIONING THE BOILER
1. Isolate boiler (door isolator and mains supply)
2. Remove front access panel
Remove right side access panel
3. Check all electrical connections for tightness
4. Insulation test the elements
5. Set the steam pressure controls (see Section 3.2.2.1 - Setting Steam Pressure Controls)
6. Ensure Boiler switch is in the OFF position
Connect to the mains electrical supply
7. Close boiler blowdown valve
Close main steam valve
8. Open all valves in the feedwater line
Check for leaks
9. Ensure Boiler switch is in the OFF position
Ensure Pump switch is in the OFF position
10. Ensure master step controller Block one - Switch 3 is in the ON position
11. Replace front access panel
Replace right side access panel
12. Switch main isolator ON
Turn boiler door isolator ON
13. Fill the feedwater pump
Close the isolating valve on the discharge side of the feedwater pump (at rear of boiler).
Removetheprimingplugfromthepumpheadandslowlyllthepumpwithwater.Replacethe
priming plug and tighten securely.
These procedures should be carried out by a competent person.
Although every care is taken to ensure that the boiler has been despatched from the factory
fully tested, it is possible that during transportation and installation, pipework and electrical
connections may be loosened or broken. On completion of the installation and prior to switching
on the boiler it is advisable to carry out the following checks:
WARNING
The boiler electrical circuit must be isolated prior to doing the following tests.
!
CONTINUED ON NEXT PAGE
EP100-IOMM-2017-11
Fulton Ltd
Page 11
INSTALLATION - 2
14. Feedwater pump checks
Bleed the feedwater pump (see Figure. 5)
Remove the feedwater pump cover to expose the pump drive shaft coupling (see Figure. 5)
Turn Pump switch ON
Check the rotation of the feedwater pump. Correct rotation is anti-clockwise when viewed from
the top of the pump.
Turn Pump switch OFF and wait until the drive shaft stops rotating before replacing the cover.
Note: The pump impeller blades can be damaged by incorrect rotation. If the rotation is incorrect turn the selector
switch to the OFF position. Isolate the boiler and alter the phase connections between the pump contactor
overload and the pump. Re-check the pump rotation.
WARNING
Do not make contact or place anything in touch with the moving parts of the pump drive. The cover is
removed for a visual inspection of the pump rotation. Stop the pump to replace the cover.
!
15. Fill the boiler
Open the isolating valve on the discharge side of the feedwater pump (at rear of boiler)
Turn Pump switch ON
Low water light and low water reset button will illuminate
Audible alarm sounds
Allowfeedwaterpumptolltheboiler
Check feedwater pump stops when correct water level is reached
Press low water reset button to cancel alarm and Low water warning lights
16. Elements automatic on/off check with Low water
Put the step controller into Commissioning mode (master unit, block 1, DIP switch 3 OFF)
Turn Boiler switch ON
Turn Pump switch OFF
Ensure Element Switches are in the ON position
Elements should energise indicated by the Element Switch lights
Figure. 5 - Feedwater Pump
Feedwater pump bleed nipple
Removable cover to check
pump rotation
CONTINUED ON NEXT PAGE
EP100-IOMM-2017-11
Fulton Ltd
Page 12
INSTALLATION - 2
WARNING
The boiler electrical circuit must be isolated prior to doing the following tests.
!
Turn Boiler switch OFF
Turn Pump switch OFF
Turn boiler door isolator OFF
Remove access panels
Check for steam/water leaks
Put step controller into Operation Mode (master unit, block 1, DIP switch 3 ON)
Replace access panels
Slowly open the steam valve to release pressure from the boiler to below high pressure set
point
Check for steam leaks in connecting pipework
Turn boiler door isolator ON
Turn Boiler switch ON
Turn Pump switch ON
Press High Pressure Reset button to cancel alarm and energise the elements
The boiler is now ready for placing into full operation.
Open Boiler Blowdown valve and drain water from the boiler until:
a) Low water light illuminates
b) Low water reset button illuminates
c) Audible alarm sounds
Close Boiler Blowdown valve
Check that the elements de-energise and Element lights switch off in Low water condition
Turn Pump switch ON
Checkfeedwaterpumpstartsandllstheboilertothecorrectwaterlevel
Press low water reset button to cancel alarm and Low water warning lights
Check that the elements energise and element lights illuminate when correct water level is
restored
17. Elements automatic on/off check with High pressure
Set the Steam Pressure Control to its maximum
Set the High Limit Pressure Control to 0.5 barg below the safety valve setting
With the Boiler switch ON, the boiler will slowly raise steam pressure
Check that the elements de-energise when the set high limit pressure is reached.
The High Pressure Reset button will illuminate and an audible alarm will sound
Check that the pressure reading on the pressure gauge at boiler cut-out corresponds with the
High Pressure Controller setting
Reset the Steam Pressure Control to the required working pressure
EP100-IOMM-2017-11
Fulton Ltd
Page 13
INSTALLATION - 2
2.7 CLEANING STEAM LINES AND PRESSURE VESSELS
Duringtherstweekofboileroperation,cleanalloilanddirtfromtheboiler,thesteamlineand
condensate return line.
1. Disconnect the condensate return pipe adjacent to the condensate return tank.
2. Directthereturnstoaoordrainorothersafedischargepointandmakesafe.
3. Leaveinthispositionforoneweektoallowallimpuritiestoushthrough.
4. Drain the boiler completely each day.
5. Aftertheweekiscompleted,drainandushthecondensatereturntank,removingall
installation sediment. Reconnect the condensate return pipe to the condensate return tank.
EP100-IOMM-2017-11
Fulton Ltd
Page 14
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46
  • Page 47 47
  • Page 48 48
  • Page 49 49
  • Page 50 50
  • Page 51 51
  • Page 52 52
  • Page 53 53
  • Page 54 54
  • Page 55 55
  • Page 56 56
  • Page 57 57
  • Page 58 58
  • Page 59 59
  • Page 60 60
  • Page 61 61
  • Page 62 62
  • Page 63 63
  • Page 64 64
  • Page 65 65
  • Page 66 66

Fulton Electropack 100 kW User manual

Type
User manual

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI