PLENUM FAN
Installation and maintenance instructions
4
FläktGroup DC_9933GB 20180321_R0 Specifications are subject to alteration without notice
If the air handling unit is supplied with a control system, the flow
can be read directly in the control panel display.
TEMPERATURE CORRECTION
The flow scale on the indicating instrument and the flow formula
above apply to air with a temperature of +20 °C. For other tempera-
tures, the flow must be corrected using the following formula:
where q = the actual flow through the fan, q20 = the flow reading
and t = the current temperature in °C.
MAINTENANCE
The fan must be inspected and cleaned every 6/12th month.
The length of the interval has been determined on the basis of
approx. 2000 hours of operation during a 12-month period and
for a normal comfort installation.
In environments where the dust content is high in the supply
and/or extract air, the air handling unit will have to be inspected
and cleanedmore often.
The fan is accessible through the inspection door and cleaned
with the fan in place.
CLEANING
Both the supply air and the extract air fan should be inspected
and cleaned whenever the need arises. Dust tends to collect
mainly on the inner side of the fan blades.
The best way to clean the fan impeller is by using a vacuum
cleaner equipped with a soft nozzle. Be careful to remove all
the impurities from the fan blades so that the fan will not come
out of balance.
After adjusting or cleaning the fan, check that it runs free of
vibration.
TO REMOVE THE FAN FROM THE AIR HANDLING
UNIT CASING, ASYNCHRONOUS AND PM-MOTORS
The fan can be withdrawn from the casing in the following way:
1. Remove the frame of the inspection door including the door
and the fixed panel by removing the bolts beneath the cover
plenums.
2. Disconnect the motor cable/control cable to the frequency
inverter and pull the cables through the rotor wall/filter wall.
3. If a shear absorber is fitted: Remove the bolts (2 bolts) that
secure its brackets. Ignore the bolts on the rear side; they
need not be backed off.
If a pressure suppressor and steel spring anti-vibration
mountings are fitted: Remove the bolts to the fan beams in
the floor at both ends.
4. If steel spring anti-vibration mountings are fitted:
Remove the bolts that hold the fan connection against
the fan outlet.
NB!
In the case of air handling units supplied with
a control system, the pressure tappings in
the end connection panels of the unit are not
connected to the airflow sensor of the fan.
If you still want to read the manometer pres-
sure with an external manometer, you can
connect the tubes from the airflow sensor of
the fan across T-nipples to the pressure tap-
pings in the end connection panel of the air
handling unit.
If this external means of measuring flow will
not be permanent, the tubes must be restored
to their original condition.
Warning!
In order to prevent personal injury and damage
to machinery, the safety isolating switch must
be switched off and the safety fuses of the fan
must be removed before beginning work on
the fan.
If two fans are installed in the fan section, the k-value is appli-
cable to the total airflow generated by both fans
q = q20 , m3/s
(273 + t)
293
Size GPEB-aaa-b k-factor Size
005-2 67,56 025
008-2, 009-2 54,40 028
008-3, 009-3 43,48 031
011-2, 014-2 36,01 035
011-3, 014-3, 018-2, 020-2 29,62 040
018-3, 020-3 22,56 045
023-2, 027-2 18,89 050
023-3, 027-3, 032-2, 036-2 14,43 056
032-3, 036-3, 041-2, 045-2, 047-2 11,63 063
041-3, 045-3, 047-3, 050-2, 054-2,
056-2, 063-2, 072-2
9,07 071
050-3, 054-3, 056-3, 063-3, 068-2,
072-3, 079-2
7,35 080
068-3, 079-3, 090-2 4,60 090