Fig. 7: Starting from the supply point at the bottom, press the
composite pipe into the channels.
Fig. 8: Attach reinforcement grid from top to bottom, lightly
tensioned and with 10 cm overlap, using the dowel upper
section.
Fig. 9: Before applying the plaster carry out the required
pressure test to at least 6 bar, according to the test report.
Fig. 10: The 15 mm thick single plaster layer can be smoothed
or matted as required.
Installation Guide
SpeedUp Wall Heating in Wet Systems
Danfoss A/S
Heating Solutions
Haarupvaenget 11
8600 Silkeborg
Denmark
Phone:+45 7488 8000
Fax: +45 7488 8100
www.heating.danfoss.com
Danfoss can accept no responsibility for possible errors in catalogues, brochures and other printed material. Danfoss reserves the right to alter its products without notice. This also applies to products
already on order provided that such alterations can be made without subsequential changes being necessary in specifications already agreed. All trademarks in this material are property of the respective
companies. Danfoss and the Danfoss logotype are trademarks of Danfoss A/S. All rights reserved.
VIETC202 Produced by Danfoss Heating Solutions © 11/2010