EU Air Handling Unit INSTALLATION
Mounting on the floor
The floor on which the unit is placed must be flat, to
ensure problem-free operation.
Check the floor carefully to avoid distortion of the unit
and thus ensure that the doors will not be difficult to
open and close.
EUAZ-05 adjustable feet are available to allow for indi-
vidual height adjustment of the EUAZ-04 base frame.
Place the support washer (supplied) under the foot as
shown in Fig. 8. It is important to make sure that the
unit is level.
If the air handling unit includes unit sections that are
provided with drains, space must be available for a
water trap (such as the EUAZ-08) as shown in Fig. 9.
Adjustment of the lateral and longitudinal position of
the air handling unit is best carried out by means of a
roller crowbar or the like, as shown in Fig. 10 and 11.
N.B. The unit should slope 2% towards the inspection
side to allow for drainage during cleaning. Flushing
water can be collected in the EUWZ-02 drainage
water trough (accessory).
Fitting adjustable feet
The feet are fitted with even spacing along the side rails
if the number of feet is greater than 4. In the case of 4
feet, 1 foot should be fitted at each end of the side
beams.
Adjustment of set-screws:
1) Release the locking
nut (A).
2) Adjust the height
with the set-screw (B).
3) Retighten the
locking nut (A).
EUWA 11-53 – General instructions, hygienic version