min. 20 cm min. 20 cmmax. 30 cm
Produced by Danfoss A/S © 04/2009
VICSB202
7 8
Lighter constructions require the insulation to be glued at the perimeter,
under SpeedUp header panels and through thresholds.
Second or third layers of insulation must always be cross-laid to the ones
below. The last layer must be cross-laid to SpeedUp heat panels above.
9 10
Enclose pipe section (maximum width 30 cm according to BEB/ZDB
Information leaflet) and fill up with bonded compound level with insulation.
Pipe sections with insulated pipes and above 20 cm must be covered
with a 1 mm metal sheet. *
Protect insulation from frequent pedestrian traffic to avoid damage.
*Note! For light floor constructions (e.g. when laying laminate/parquet
directly on the heat panel and all strongboard constructions) pipe
channels - in the additional insulation - with a width of more than 10 cm
must be covered with a metal plate (min. 1 mm). If the pipe channels
have a width of more than 15 cm a special loadbaring plate (min. 18 mm)
must be used.
Instruction Installation of additional insulation EPS / XPS for SpeedUp