ABB Relion REC670 Commissioning Manual

Type
Commissioning Manual

This manual is also suitable for

Relion
®
670 SERIES
Bay control REC670
Version 2.2 IEC
Commissioning manual
Document ID: 1MRK 511 403-UEN
Issued: May 2019
Revision: E
Product version: 2.2
© Copyright 2017 ABB. All rights reserved
Copyright
This document and parts thereof must not be reproduced or copied without written
permission from ABB, and the contents thereof must not be imparted to a third party, nor
used for any unauthorized purpose.
The software and hardware described in this document is furnished under a license and may
be used or disclosed only in accordance with the terms of such license.
This product includes software developed by the OpenSSL Project for use in the OpenSSL
Toolkit. (http://www.openssl.org/) This product includes cryptographic software written/
developed by: Eric Young ([email protected]) and Tim Hudson ([email protected]).
Trademarks
ABB and Relion are registered trademarks of the ABB Group. All other brand or product names
mentioned in this document may be trademarks or registered trademarks of their respective
holders.
Warranty
Please inquire about the terms of warranty from your nearest ABB representative.
Disclaimer
The data, examples and diagrams in this manual are included solely for the concept or product
description and are not to be deemed as a statement of guaranteed properties. All persons
responsible for applying the equipment addressed in this manual must satisfy themselves that
each intended application is suitable and acceptable, including that any applicable safety or
other operational requirements are complied with. In particular, any risks in applications where
a system failure and/or product failure would create a risk for harm to property or persons
(including but not limited to personal injuries or death) shall be the sole responsibility of the
person or entity applying the equipment, and those so responsible are hereby requested to
ensure that all measures are taken to exclude or mitigate such risks.
This document has been carefully checked by ABB but deviations cannot be completely ruled
out. In case any errors are detected, the reader is kindly requested to notify the manufacturer.
Other than under explicit contractual commitments, in no event shall ABB be responsible or
liable for any loss or damage resulting from the use of this manual or the application of the
equipment.
Conformity
This product complies with the directive of the Council of the European Communities on the
approximation of the laws of the Member States relating to electromagnetic compatibility
(EMC Directive 2004/108/EC) and concerning electrical equipment for use within specified
voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests
conducted by ABB in accordance with the product standard EN 60255-26 for the EMC directive,
and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive. The
product is designed in accordance with the international standards of the IEC 60255 series.
Table of contents
Section 1 Introduction.......................................................................................................11
1.1 This manual........................................................................................................................................11
1.2 Intended audience............................................................................................................................ 11
1.3 Product documentation..................................................................................................................12
1.3.1 Product documentation set.......................................................................................................12
1.3.2 Document revision history.........................................................................................................13
1.3.3 Related documents......................................................................................................................13
1.4 Document symbols and conventions...........................................................................................14
1.4.1 Symbols......................................................................................................................................... 14
1.4.2 Document conventions...............................................................................................................15
1.5 IEC 61850 edition 1 / edition 2 mapping..................................................................................... 15
Section 2 Safety information........................................................................................... 25
2.1 Symbols on the product................................................................................................................. 25
2.2 Warnings............................................................................................................................................ 25
2.3 Caution signs....................................................................................................................................26
2.4 Note signs..........................................................................................................................................27
Section 3 Available functions........................................................................................... 29
3.1 Main protection functions............................................................................................................. 29
3.2 Back-up protection functions....................................................................................................... 29
3.3 Control and monitoring functions................................................................................................31
3.4 Communication................................................................................................................................ 41
3.5 Basic IED functions..........................................................................................................................43
Section 4 Starting up........................................................................................................ 45
4.1 Factory and site acceptance testing........................................................................................... 45
4.2 Commissioning checklist............................................................................................................... 45
4.3 Checking the power supply........................................................................................................... 46
4.4 Energizing the IED........................................................................................................................... 46
4.4.1 Checking the IED operation...................................................................................................... 46
4.4.2 IED start-up sequence................................................................................................................46
4.5 Setting up communication between PCM600 and the IED.....................................................47
4.6 Writing an application configuration to the IED........................................................................51
4.7 Checking CT circuits........................................................................................................................ 51
4.8 Checking VT circuits........................................................................................................................ 52
4.9 Using the RTXP test switch............................................................................................................52
4.10 Checking the binary input/output circuits.................................................................................53
4.10.1 Binary input circuits.................................................................................................................... 53
4.10.2 Binary output circuits................................................................................................................. 53
4.11 Checking optical connections....................................................................................................... 53
Table of contents
Bay control REC670 1
Commissioning manual
© Copyright 2017 ABB. All rights reserved
Section 5 Configuring the IED and changing settings..................................................55
5.1 Overview............................................................................................................................................ 55
5.2 Configuring analog CT inputs....................................................................................................... 55
5.3 Supervision of input/output modules........................................................................................ 56
Section 6 Establishing connection and verifying the SPA/IEC communication........57
6.1 Entering settings............................................................................................................................. 57
6.1.1 Entering SPA settings.................................................................................................................57
6.1.2 Entering IEC settings.................................................................................................................. 57
6.2 Verifying the communication........................................................................................................58
6.2.1 Verifying SPA communication.................................................................................................. 58
6.2.2 Verifying IEC communication................................................................................................... 58
6.3 Fiber optic loop................................................................................................................................ 58
6.4 Optical budget calculation for serial communication with SPA/IEC ................................... 59
Section 7 Establishing connection and verifying the LON communication............... 61
7.1 Communication via the rear ports ...............................................................................................61
7.1.1 LON communication................................................................................................................... 61
7.1.2 The LON Protocol........................................................................................................................ 62
7.1.3 Hardware and software modules.............................................................................................62
7.2 Optical budget calculation for serial communication with LON ...........................................64
Section 8 Establishing connection and verifying the IEC 61850 communication.....65
8.1 Overview............................................................................................................................................ 65
8.2 Setting the station communication.............................................................................................65
8.3 Verifying the communication........................................................................................................65
Section 9 Establishing connection and verifying the IEEE C37.118/1344
communication................................................................................................. 67
9.1 Overview............................................................................................................................................ 67
9.2 Setting the PMU station communication (PMU Report)..........................................................67
9.3 Setting the PMU station communication (PMU configuration)............................................. 67
9.4 Setting the TCP/UDP client communication............................................................................. 68
9.5 Verifying the communication.........................................................................................................71
9.5.1 Verifying the IEEE C37.118/1344 TCP communication..........................................................71
9.5.2 Verifying the IEEE C37.118/1344 UDP communication.........................................................77
9.6 Optical budget calculation for PMU - PDC communication.................................................... 78
Section 10 Testing IED operation...................................................................................... 79
10.1 Preparing for test.............................................................................................................................79
10.1.1 Requirements............................................................................................................................... 79
10.1.2 Preparing the IED to verify settings........................................................................................ 80
10.2 Activating the test mode................................................................................................................81
10.3 Preparing the connection to the test equipment......................................................................81
10.4 Connecting the test equipment to the IED.................................................................................82
10.5 Releasing the function to be tested.............................................................................................83
10.6 Verifying analog primary and secondary measurement..........................................................84
Table of contents
2 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
10.7 Testing the protection functionality........................................................................................... 85
10.8 Forcing of binary input/output signals for testing..................................................................85
10.8.1 Forcing concept...........................................................................................................................85
10.8.2 How to enable forcing................................................................................................................ 86
10.8.2.1 Enable forcing by using LHMI................................................................................................86
10.8.2.2 Enable forcing using TESTMODE function block...............................................................86
10.8.3 How to change binary input/output signals using forcing................................................86
10.8.3.1 Forcing by using LHMI............................................................................................................ 86
10.8.3.2 Forcing by using PCM600...................................................................................................... 88
10.8.4 How to undo forcing changes and return the IED to normal operation.......................... 89
10.8.4.1 Undo forcing by using TESTMODE component.................................................................90
10.8.4.2 Undo forcing by using LHMI.................................................................................................. 90
10.8.4.3 Undo forcing by using PCM600............................................................................................ 90
Section 11 Testing functionality by secondary injection............................................... 91
11.1 Testing disturbance report............................................................................................................ 91
11.1.1 Introduction.................................................................................................................................. 91
11.1.2 Disturbance report settings...................................................................................................... 91
11.1.3 Disturbance recorder (DR)......................................................................................................... 91
11.1.4 Event recorder (ER) and Event list (EL)................................................................................... 92
11.2 Identifying the function to test in the technical reference manual ......................................92
11.3 Differential protection....................................................................................................................92
11.3.1 High impedance differential protection HZPDIF ................................................................. 92
11.3.1.1 Verifying the settings..............................................................................................................92
11.3.1.2 Completing the test.................................................................................................................93
11.4 Current protection...........................................................................................................................93
11.4.1 Instantaneous phase overcurrent protection 3-phase output PHPIOC .......................... 93
11.4.1.1 Measuring the operate limit of set values.......................................................................... 94
11.4.1.2 Completing the test................................................................................................................ 94
11.4.2 Directional phase overcurrent protection, four steps OC4PTOC......................................94
11.4.2.1 Verifying the settings..............................................................................................................94
11.4.2.2 Completing the test................................................................................................................ 95
11.4.3 Instantaneous residual overcurrent protection EFPIOC .................................................... 95
11.4.3.1 Measuring the operate limit of set values.......................................................................... 96
11.4.3.2 Completing the test................................................................................................................ 96
11.4.4 Four step residual overcurrent protection, (Zero sequence or negative sequence
directionality) EF4PTOC ............................................................................................................96
11.4.4.1 Four step directional earth fault protection...................................................................... 96
11.4.4.2 Four step non-directional earth fault protection.............................................................. 97
11.4.4.3 Completing the test.................................................................................................................97
11.4.5 Four step negative sequence overcurrent protection NS4PTOC ..................................... 97
11.4.5.1 Completing the test................................................................................................................ 98
11.4.6 Sensitive directional residual overcurrent and power protection SDEPSDE ................. 98
11.4.6.1 Measuring the operate and time limit for set values........................................................99
11.4.6.2 Completing the test...............................................................................................................103
11.4.7 Thermal overload protection, one time constant, Celsius/Fahrenheit
LCPTTR/LFPTTR.........................................................................................................................103
Table of contents
Bay control REC670 3
Commissioning manual
© Copyright 2017 ABB. All rights reserved
11.4.7.1 Measuring the operate and time limit of set values....................................................... 103
11.4.7.2 Completing the test.............................................................................................................. 104
11.4.8 Thermal overload protection, two time constants TRPTTR ............................................ 104
11.4.8.1 Checking operate and reset values.................................................................................... 104
11.4.8.2 Completing the test...............................................................................................................105
11.4.9 Breaker failure protection, phase segregated activation and output CCRBRF............105
11.4.9.1 Checking the phase current operate value,
IP>
................................................................105
11.4.9.2 Checking the residual (earth fault) current operate value
IN>
set below
IP>
............ 105
11.4.9.3 Checking the re-trip and back-up times............................................................................106
11.4.9.4 Verifying the re-trip mode....................................................................................................106
11.4.9.5 Verifying the back-up trip mode......................................................................................... 106
11.4.9.6 Verifying instantaneous back-up trip at CB faulty condition........................................107
11.4.9.7 Verifying the case
FunctionMode
=
CB Pos
...................................................................... 107
11.4.9.8 Verifying the case
RetripMode
=
Contact
......................................................................... 107
11.4.9.9 Verifying the case
FunctionMode
=
Current
or
CB Pos
.................................................... 108
11.4.9.10 Verifying the external start signal has timed out............................................................108
11.4.9.11 Verifying that backup signal is released when STALARM is reset................................109
11.4.9.12 Test of
FollowStart&Mode
behaviour................................................................................ 109
11.4.9.13 Test of
FollowStart
behaviour.............................................................................................109
11.4.9.14 Completing the test.............................................................................................................. 109
11.4.10 Stub protection STBPTOC....................................................................................................... 109
11.4.10.1 Measuring the operate limit of set values.........................................................................110
11.4.10.2 Completing the test............................................................................................................... 110
11.4.11 Pole discordance protection CCPDSC................................................................................... 110
11.4.11.1 Verifying the settings............................................................................................................ 110
11.4.11.2 Completing the test................................................................................................................111
11.4.12 Directional underpower protection GUPPDUP ....................................................................111
11.4.12.1 Verifying the settings.............................................................................................................111
11.4.12.2 Completing the test............................................................................................................... 113
11.4.13 Directional overpower protection GOPPDOP ......................................................................113
11.4.13.1 Verifying the settings.............................................................................................................113
11.4.13.2 Completing the test............................................................................................................... 113
11.4.14 Broken conductor check BRCPTOC ....................................................................................... 113
11.4.14.1 Measuring the operate and time limit of set values........................................................ 113
11.4.14.2 Completing the test............................................................................................................... 114
11.4.15 Capacitor bank protection CBPGAPC.................................................................................... 114
11.4.15.1 Verifying the settings and operation of the function..................................................... 114
11.4.15.2 Completing the test............................................................................................................... 118
11.4.16 Voltage-restrained time overcurrent protection VRPVOC................................................ 118
11.4.16.1 Verifying the settings............................................................................................................ 118
11.4.16.2 Completing the test............................................................................................................... 121
11.5 Voltage protection......................................................................................................................... 121
11.5.1 Two step undervoltage protection UV2PTUV ......................................................................121
11.5.1.1 Verifying the settings.............................................................................................................121
11.5.1.2 Completing the test............................................................................................................... 122
11.5.2 Two step overvoltage protection OV2PTOV ........................................................................122
Table of contents
4 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
11.5.2.1 Verifying the settings............................................................................................................ 122
11.5.2.2 Extended testing.................................................................................................................... 123
11.5.2.3 Completing the test...............................................................................................................123
11.5.3 Two step residual overvoltage protection ROV2PTOV ......................................................123
11.5.3.1 Verifying the settings............................................................................................................ 123
11.5.3.2 Completing the test...............................................................................................................124
11.5.4 Voltage differential protection VDCPTOV ........................................................................... 124
11.5.4.1 Check of undervoltage levels............................................................................................... 124
11.5.4.2 Check of voltage differential trip and alarm levels..........................................................125
11.5.4.3 Check of trip and trip reset timers..................................................................................... 126
11.5.4.4 Final adjustment of compensation for VT ratio differences ........................................ 127
11.5.4.5 Completing the test............................................................................................................... 127
11.5.5 Loss of voltage check LOVPTUV ............................................................................................ 127
11.5.5.1 Measuring the operate limit of set values......................................................................... 127
11.5.5.2 Completing the test...............................................................................................................128
11.6 Frequency protection....................................................................................................................128
11.6.1 Underfrequency protection SAPTUF .....................................................................................128
11.6.1.1 Verifying the settings............................................................................................................ 128
11.6.1.2 Completing the test...............................................................................................................129
11.6.2 Overfrequency protection SAPTOF .......................................................................................129
11.6.2.1 Verifying the settings............................................................................................................ 129
11.6.2.2 Completing the test...............................................................................................................130
11.6.3 Rate-of-change frequency protection SAPFRC .................................................................. 130
11.6.3.1 Verifying the settings............................................................................................................130
11.6.3.2 Completing the test...............................................................................................................130
11.6.4 Frequency time accumulation protection function FTAQFVR..........................................130
11.6.4.1 Verifying the settings.............................................................................................................131
11.6.4.2 Completing the test............................................................................................................... 132
11.7 Multipurpose protection...............................................................................................................132
11.7.1 General current and voltage protection CVGAPC................................................................132
11.7.1.1 Built-in overcurrent feature (non-directional).................................................................. 132
11.7.1.2 Overcurrent feature with current restraint....................................................................... 133
11.7.1.3 Overcurrent feature with voltage restraint.......................................................................133
11.7.1.4 Overcurrent feature with directionality.............................................................................134
11.7.1.5 Over/Undervoltage feature..................................................................................................134
11.7.1.6 Completing the test...............................................................................................................134
11.8 Secondary system supervision....................................................................................................134
11.8.1 Current circuit supervision CCSSPVC....................................................................................134
11.8.1.1 Verifying the settings............................................................................................................ 135
11.8.1.2 Completing the test...............................................................................................................135
11.8.2 Fuse failure supervision FUFSPVC..........................................................................................135
11.8.2.1 Checking that the binary inputs and outputs operate as expected ........................... 135
11.8.2.2 Measuring the operate value for the negative sequence function ............................. 136
11.8.2.3 Measuring the operate value for the zero-sequence function ..................................... 137
11.8.2.4 Measuring the operate value for the dead line detection function..............................137
11.8.2.5 Checking the operation of the du/dt and di/dt based function ................................. 137
Table of contents
Bay control REC670 5
Commissioning manual
© Copyright 2017 ABB. All rights reserved
11.8.2.6 Completing the test...............................................................................................................138
11.8.3 Fuse failure supervision VDSPVC............................................................................................138
11.8.3.1 Completing the test...............................................................................................................139
11.8.4 Voltage based delta supervision DELVSPVC........................................................................139
11.8.4.1 Verifying the signals and settings...................................................................................... 139
11.8.4.2 Completing the test.............................................................................................................. 140
11.8.5 Current based delta supervision DELISPVC.........................................................................140
11.8.5.1 Verifying the signals and settings......................................................................................140
11.8.5.2 Completing the test............................................................................................................... 141
11.8.6 Delta supervision of real input DELSPVC.............................................................................. 141
11.8.6.1 Verifying the signals and settings.......................................................................................141
11.8.6.2 Completing the test............................................................................................................... 141
11.9 Control..............................................................................................................................................142
11.9.1 Synchrocheck, energizing check, and synchronizing SESRSYN........................................142
11.9.1.1 Testing the synchronizing function....................................................................................143
11.9.1.2 Testing the synchrocheck functionality............................................................................ 144
11.9.1.3 Testing the energizing check...............................................................................................146
11.9.1.4 Testing the voltage selection...............................................................................................147
11.9.1.5 Completing the test...............................................................................................................149
11.9.2 Autorecloser for 1/2/3-phase operation SMBRREC .......................................................... 149
11.9.2.1 Preparation of the verification ............................................................................................151
11.9.2.2 Switching the auto recloser to On and Off
On
and
Off
...................................................151
11.9.2.3 Verifying the auto recloser .................................................................................................. 152
11.9.2.4 Checking the auto reclosing conditions............................................................................ 152
11.9.2.5 Completing the test...............................................................................................................154
11.9.3 Apparatus control APC............................................................................................................. 154
11.9.4 Voltage control TR1ATCC, TR8ATCC, TCMYLTC, TCLYLTC............................................... 154
11.9.4.1 Secondary test........................................................................................................................156
11.9.4.2 Check the activation of the voltage control operation.................................................. 156
11.9.4.3 Check the normal voltage regulation function.................................................................157
11.9.4.4 Check the undervoltage block function............................................................................. 157
11.9.4.5 Check the upper and lower busbar voltage limit............................................................. 157
11.9.4.6 Check the overcurrent block function................................................................................158
11.9.4.7 Single transformer................................................................................................................. 158
11.9.4.8 Parallel voltage regulation....................................................................................................159
11.9.4.9 Completing the test...............................................................................................................162
11.9.5 Single command, 16 signals SINGLECMD............................................................................. 162
11.9.6 Interlocking................................................................................................................................. 163
11.10 Scheme communication............................................................................................................... 163
11.10.1 Scheme communication logic for distance or overcurrent protection ZCPSCH ......... 163
11.10.1.1 Testing permissive underreaching..................................................................................... 163
11.10.1.2 Testing permissive overreaching........................................................................................163
11.10.1.3 Testing blocking scheme......................................................................................................164
11.10.1.4 Testing delta blocking scheme........................................................................................... 164
11.10.1.5 Checking of unblocking logic...............................................................................................164
11.10.1.6 Completing the test...............................................................................................................165
Table of contents
6 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
11.10.2 Current reversal and Weak-end infeed logic for distance protection 3-phase
ZCRWPSCH .................................................................................................................................165
11.10.2.1 Current reversal logic............................................................................................................ 165
11.10.2.2 Weak end infeed logic........................................................................................................... 166
11.10.2.3 Completing the test...............................................................................................................166
11.10.3 Local acceleration logic ZCLCPSCH....................................................................................... 167
11.10.3.1 Verifying the settings............................................................................................................ 167
11.10.3.2 Completing the test...............................................................................................................167
11.10.4 Scheme communication logic for residual overcurrent protection ECPSCH ............... 167
11.10.4.1 Testing the directional comparison logic function......................................................... 167
11.10.4.2 Completing the test...............................................................................................................168
11.10.5 Current reversal and weak-end infeed logic for residual overcurrent protection
ECRWPSCH .................................................................................................................................169
11.10.5.1 Testing the current reversal logic....................................................................................... 169
11.10.5.2 Testing the weak-end infeed logic..................................................................................... 169
11.10.5.3 Completing the test............................................................................................................... 171
11.11 Logic..................................................................................................................................................171
11.11.1 Tripping logic, common 3-phase output SMPPTRC ........................................................... 171
11.11.1.1 3 phase operating mode........................................................................................................171
11.11.1.2 1ph/3ph operating mode...................................................................................................... 171
11.11.1.3 1ph/2ph/3ph operating mode.............................................................................................172
11.11.1.4 Circuit breaker lockout.......................................................................................................... 173
11.11.1.5 Completing the test............................................................................................................... 173
11.12 Monitoring....................................................................................................................................... 173
11.12.1 Gas medium supervision SSIMG............................................................................................. 173
11.12.1.1 Testing the gas medium supervision for pressure alarm and pressure lockout
conditions................................................................................................................................ 174
11.12.1.2 Testing the gas medium supervision for temperature alarm and temperature
lock out conditions.................................................................................................................174
11.12.1.3 Completing the test...............................................................................................................174
11.12.2 Liquid medium supervision SSIML......................................................................................... 174
11.12.2.1 Testing the liquid medium supervision for level alarm and level lockout
conditions................................................................................................................................ 175
11.12.2.2 Testing the liquid medium supervision for temperature alarm and
temperature lock out conditions........................................................................................ 175
11.12.2.3 Completing the test...............................................................................................................175
11.12.3 Breaker monitoring SSCBR...................................................................................................... 175
11.12.3.1 Verifying the settings............................................................................................................ 175
11.12.3.2 Completing the test............................................................................................................... 177
11.12.4 Event function EVENT............................................................................................................... 177
11.12.5 Fault locator LMBRFLO............................................................................................................. 177
11.12.5.1 Measuring the operate limit.................................................................................................178
11.12.5.2 Completing the test...............................................................................................................179
11.12.6 Limit counter L4UFCNT............................................................................................................ 179
11.12.6.1 Completing the test...............................................................................................................179
11.12.7 Estimation of transformer insulation life LOLSPTR .......................................................... 179
11.12.7.1 Verifying the signals and settings...................................................................................... 179
Table of contents
Bay control REC670 7
Commissioning manual
© Copyright 2017 ABB. All rights reserved
11.12.7.2 Completing the test.............................................................................................................. 180
11.12.8 Through fault monitoring PTRSTHR ..................................................................................... 180
11.12.8.1 Verifying the signals and settings...................................................................................... 180
11.12.8.2 Completing the test............................................................................................................... 181
11.12.9 Current harmonic monitoring CHMMHAI..............................................................................181
11.12.9.1 Verifying the signals and settings.......................................................................................181
11.12.9.2 Completing the test...............................................................................................................182
11.12.10 Voltage harmonic monitoring VHMMHAI..............................................................................182
11.12.10.1 Verifying the signals and settings...................................................................................... 182
11.12.10.2 Completing the test...............................................................................................................183
11.13 Metering...........................................................................................................................................183
11.13.1 Pulse-counter logic PCFCNT....................................................................................................183
11.13.2 Function for energy calculation and demand handling ETPMMTR..................................183
11.13.2.1 Verifying the settings............................................................................................................ 183
11.13.2.2 Completing the test...............................................................................................................184
11.14 Station communication................................................................................................................ 185
11.14.1 Multiple command and transmit MULTICMDRCV / MULTICMDSND.............................. 185
11.15 Remote communication............................................................................................................... 185
11.15.1 Binary signal transfer................................................................................................................185
11.16 Basic IED functions........................................................................................................................186
11.16.1 Parameter setting group handling SETGRPS.......................................................................186
11.16.1.1 Verifying the settings............................................................................................................186
11.16.1.2 Completing the test...............................................................................................................186
11.17 Exit test mode.................................................................................................................................187
Section 12 Primary injection testing...............................................................................189
12.1 Transformer Voltage Control ATCC........................................................................................... 189
12.1.1 Load drop compensation function, LDC...............................................................................189
12.1.2 Voltage control of Parallel Transformers............................................................................. 190
12.1.3 Minimum Circulating Current (MCC) method...................................................................... 191
12.1.4 Master Follower (MF) method.................................................................................................192
12.1.5 Completing the test.................................................................................................................. 193
Section 13 Commissioning and maintenance of the fault clearing system...............195
13.1 Commissioning tests.................................................................................................................... 195
13.2 Periodic maintenance tests......................................................................................................... 195
13.2.1 Visual inspection........................................................................................................................196
13.2.2 Maintenance tests.....................................................................................................................196
13.2.2.1 Preparation..............................................................................................................................196
13.2.2.2 Recording.................................................................................................................................196
13.2.2.3 Secondary injection............................................................................................................... 196
13.2.2.4 Alarm test.................................................................................................................................197
13.2.2.5 Self supervision check........................................................................................................... 197
13.2.2.6 Trip circuit check.................................................................................................................... 197
13.2.2.7 Measurement of service currents....................................................................................... 197
13.2.2.8 Restoring..................................................................................................................................198
Table of contents
8 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
Section 14 Troubleshooting............................................................................................. 199
14.1 Checking the self supervision signals........................................................................................199
14.1.1 Checking the self supervision function.................................................................................199
14.1.1.1 Determine the cause of an internal failure........................................................................199
14.1.2 Self supervision HMI data........................................................................................................ 199
14.1.2.1 General IED status..................................................................................................................199
14.2 Fault tracing................................................................................................................................... 200
14.2.1 Internal fault indications......................................................................................................... 200
14.2.2 Using front-connected PC....................................................................................................... 201
14.2.3 Diagnosing the IED status via the LHMI hint menu............................................................202
14.2.4 Hardware re-configuration..................................................................................................... 204
14.3 Repair instruction.......................................................................................................................... 205
14.4 Repair support............................................................................................................................... 206
14.5 Maintenance................................................................................................................................... 206
Section 15 Glossary........................................................................................................... 207
Table of contents
Bay control REC670 9
Commissioning manual
© Copyright 2017 ABB. All rights reserved
10
Section 1 Introduction
1.1 This manual
GUID-AB423A30-13C2-46AF-B7FE-A73BB425EB5F v19
The commissioning manual contains instructions on how to commission the IED. The manual
can also be used by system engineers and maintenance personnel for assistance during the
testing phase. The manual provides procedures for the checking of external circuitry and
energizing the IED, parameter setting and configuration as well as verifying settings by
secondary injection. The manual describes the process of testing an IED in a substation which
is not in service. The chapters are organized in the chronological order in which the IED should
be commissioned. The relevant procedures may be followed also during the service and
maintenance activities.
1.2 Intended audience
GUID-C9B8127F-5748-4BEA-9E4F-CC762FE28A3A v11
This manual addresses the personnel responsible for commissioning, maintenance and taking
the IED in and out of normal service.
The commissioning personnel must have a basic knowledge of handling electronic equipment.
The commissioning and maintenance personnel must be well experienced in using protection
equipment, test equipment, protection functions and the configured functional logics in the
IED.
1MRK 511 403-UEN E Section 1
Introduction
Bay control REC670 11
Commissioning manual
© Copyright 2017 ABB. All rights reserved
1.3 Product documentation
1.3.1 Product documentation set
GUID-3AA69EA6-F1D8-47C6-A8E6-562F29C67172 v16
IEC07000220-4-en.vsd
P
l
a
n
n
i
n
g
&
p
u
r
c
h
a
s
e
E
n
g
i
n
e
e
r
i
n
g
I
n
s
t
a
l
l
i
n
g
C
o
m
m
i
s
s
i
o
n
i
n
g
O
p
e
r
a
t
i
o
n
M
a
i
n
t
e
n
a
n
c
e
D
e
c
o
m
m
i
s
s
i
o
n
i
n
g
D
e
i
n
s
t
a
l
l
i
n
g
&
d
i
s
p
o
s
a
l
Application manual
Operation manual
Installation manual
Engineering manual
Communication
protocol manual
Cyber security
deployment guideline
Technical manual
Commissioning manual
IEC07000220 V4 EN-US
Figure 1: The intended use of manuals throughout the product lifecycle
The engineering manual contains instructions on how to engineer the IEDs using the various
tools available within the PCM600 software. The manual provides instructions on how to set
up a PCM600 project and insert IEDs to the project structure. The manual also recommends a
sequence for the engineering of protection and control functions, as well as communication
engineering for IEC 61850.
The installation manual contains instructions on how to install the IED. The manual provides
procedures for mechanical and electrical installation. The chapters are organized in the
chronological order in which the IED should be installed.
The commissioning manual contains instructions on how to commission the IED. The manual
can also be used by system engineers and maintenance personnel for assistance during the
testing phase. The manual provides procedures for the checking of external circuitry and
energizing the IED, parameter setting and configuration as well as verifying settings by
secondary injection. The manual describes the process of testing an IED in a substation which
is not in service. The chapters are organized in the chronological order in which the IED should
be commissioned. The relevant procedures may be followed also during the service and
maintenance activities.
The operation manual contains instructions on how to operate the IED once it has been
commissioned. The manual provides instructions for the monitoring, controlling and setting of
the IED. The manual also describes how to identify disturbances and how to view calculated
and measured power grid data to determine the cause of a fault.
Section 1 1MRK 511 403-UEN E
Introduction
12 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
The application manual contains application descriptions and setting guidelines sorted per
function. The manual can be used to find out when and for what purpose a typical protection
function can be used. The manual can also provide assistance for calculating settings.
The technical manual contains operation principle descriptions, and lists function blocks, logic
diagrams, input and output signals, setting parameters and technical data, sorted per
function. The manual can be used as a technical reference during the engineering phase,
installation and commissioning phase, and during normal service.
The communication protocol manual describes the communication protocols supported by
the IED. The manual concentrates on the vendor-specific implementations.
The point list manual describes the outlook and properties of the data points specific to the
IED. The manual should be used in conjunction with the corresponding communication
protocol manual.
The cyber security deployment guideline describes the process for handling cyber security
when communicating with the IED. Certification, Authorization with role based access control,
and product engineering for cyber security related events are described and sorted by
function. The guideline can be used as a technical reference during the engineering phase,
installation and commissioning phase, and during normal service.
1.3.2
Document revision history
GUID-34B323E4-1319-4D42-80CE-29B0F2D36E2C v2
Document
revision
Date Product revision History
- 2017-05 2.2.0 First release for product version 2.2
A 2017-10 2.2.1 Ethernet ports with RJ45 connector added.
enhancements/updates made to ZMFPDIS and
ZMFCPDIS.
B 2018-03 2.2.1 Document enhancements and corrections
C 2018–06 2.2.2 LDCM galvanic X.21 added. Function PTRSTHR added.
Ordering section updated.
D 2018–11 2.2.3 Functions CHMMHAI, VHMMHAI, DELVSPVC, DELSPVC and
DELISPVC added. Updates/enhancements made to
HZPDIF, CCRBRF, REALCOMP, PTRSTHR and FNKEYMDx.
Ordering section updated.
E
2019-0
5
2.2.3 PTP enhancements and corrections
1.3.3 Related documents
GUID-94E8A5CA-BE1B-45AF-81E7-5A41D34EE112 v7
Documents related to REC670 Document numbers
Application manual 1MRK 511 401-UEN
Commissioning manual 1MRK 511 403-UEN
Product guide 1MRK 511 404-BEN
Technical manual 1MRK 511 402-UEN
Type test certificate 1MRK 511 404-TEN
1MRK 511 403-UEN E Section 1
Introduction
Bay control REC670 13
Commissioning manual
© Copyright 2017 ABB. All rights reserved
670 series manuals Document numbers
Operation manual 1MRK 500 127-UEN
Engineering manual 1MRK 511 398-UEN
Installation manual 1MRK 514 026-UEN
Communication protocol manual, DNP3 1MRK 511 391-UUS
Communication protocol manual, IEC 60870-5-103 1MRK 511 394-UEN
Communication protocol manual, IEC 61850 Edition 1 1MRK 511 392-UEN
Communication protocol manual, IEC 61850 Edition 2 1MRK 511 393-UEN
Communication protocol manual, LON 1MRK 511 395-UEN
Communication protocol manual, SPA 1MRK 511 396-UEN
Point list manual, DNP3 1MRK 511 397-UUS
Accessories guide 1MRK 514 012-BEN
Cyber security deployment guideline 1MRK 511 399-UEN
Connection and Installation components 1MRK 513 003-BEN
Test system, COMBITEST 1MRK 512 001-BEN
Application guide, Communication set-up 1MRK 505 382-UEN
1.4 Document symbols and conventions
1.4.1 Symbols
GUID-2945B229-DAB0-4F15-8A0E-B9CF0C2C7B15 v13
The electrical warning icon indicates the presence of a hazard which could
result in electrical shock.
The warning icon indicates the presence of a hazard which could result in
personal injury.
The caution hot surface icon indicates important information or warning about
the temperature of product surfaces.
Class 1 Laser product. Take adequate measures to protect the eyes and do not
view directly with optical instruments.
The caution icon indicates important information or warning related to the
concept discussed in the text. It might indicate the presence of a hazard which
could result in corruption of software or damage to equipment or property.
Section 1 1MRK 511 403-UEN E
Introduction
14 Bay control REC670
Commissioning manual
© Copyright 2017 ABB. All rights reserved
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46
  • Page 47 47
  • Page 48 48
  • Page 49 49
  • Page 50 50
  • Page 51 51
  • Page 52 52
  • Page 53 53
  • Page 54 54
  • Page 55 55
  • Page 56 56
  • Page 57 57
  • Page 58 58
  • Page 59 59
  • Page 60 60
  • Page 61 61
  • Page 62 62
  • Page 63 63
  • Page 64 64
  • Page 65 65
  • Page 66 66
  • Page 67 67
  • Page 68 68
  • Page 69 69
  • Page 70 70
  • Page 71 71
  • Page 72 72
  • Page 73 73
  • Page 74 74
  • Page 75 75
  • Page 76 76
  • Page 77 77
  • Page 78 78
  • Page 79 79
  • Page 80 80
  • Page 81 81
  • Page 82 82
  • Page 83 83
  • Page 84 84
  • Page 85 85
  • Page 86 86
  • Page 87 87
  • Page 88 88
  • Page 89 89
  • Page 90 90
  • Page 91 91
  • Page 92 92
  • Page 93 93
  • Page 94 94
  • Page 95 95
  • Page 96 96
  • Page 97 97
  • Page 98 98
  • Page 99 99
  • Page 100 100
  • Page 101 101
  • Page 102 102
  • Page 103 103
  • Page 104 104
  • Page 105 105
  • Page 106 106
  • Page 107 107
  • Page 108 108
  • Page 109 109
  • Page 110 110
  • Page 111 111
  • Page 112 112
  • Page 113 113
  • Page 114 114
  • Page 115 115
  • Page 116 116
  • Page 117 117
  • Page 118 118
  • Page 119 119
  • Page 120 120
  • Page 121 121
  • Page 122 122
  • Page 123 123
  • Page 124 124
  • Page 125 125
  • Page 126 126
  • Page 127 127
  • Page 128 128
  • Page 129 129
  • Page 130 130
  • Page 131 131
  • Page 132 132
  • Page 133 133
  • Page 134 134
  • Page 135 135
  • Page 136 136
  • Page 137 137
  • Page 138 138
  • Page 139 139
  • Page 140 140
  • Page 141 141
  • Page 142 142
  • Page 143 143
  • Page 144 144
  • Page 145 145
  • Page 146 146
  • Page 147 147
  • Page 148 148
  • Page 149 149
  • Page 150 150
  • Page 151 151
  • Page 152 152
  • Page 153 153
  • Page 154 154
  • Page 155 155
  • Page 156 156
  • Page 157 157
  • Page 158 158
  • Page 159 159
  • Page 160 160
  • Page 161 161
  • Page 162 162
  • Page 163 163
  • Page 164 164
  • Page 165 165
  • Page 166 166
  • Page 167 167
  • Page 168 168
  • Page 169 169
  • Page 170 170
  • Page 171 171
  • Page 172 172
  • Page 173 173
  • Page 174 174
  • Page 175 175
  • Page 176 176
  • Page 177 177
  • Page 178 178
  • Page 179 179
  • Page 180 180
  • Page 181 181
  • Page 182 182
  • Page 183 183
  • Page 184 184
  • Page 185 185
  • Page 186 186
  • Page 187 187
  • Page 188 188
  • Page 189 189
  • Page 190 190
  • Page 191 191
  • Page 192 192
  • Page 193 193
  • Page 194 194
  • Page 195 195
  • Page 196 196
  • Page 197 197
  • Page 198 198
  • Page 199 199
  • Page 200 200
  • Page 201 201
  • Page 202 202
  • Page 203 203
  • Page 204 204
  • Page 205 205
  • Page 206 206
  • Page 207 207
  • Page 208 208
  • Page 209 209
  • Page 210 210
  • Page 211 211
  • Page 212 212
  • Page 213 213
  • Page 214 214
  • Page 215 215
  • Page 216 216
  • Page 217 217
  • Page 218 218
  • Page 219 219
  • Page 220 220
  • Page 221 221
  • Page 222 222

ABB Relion REC670 Commissioning Manual

Type
Commissioning Manual
This manual is also suitable for

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI