10 Installation—Installing the FC-2000
The following procedure outlines the installation and field wiring of the
FC-2000’s modules and refers to illustrations in the Installation, Field
Wiring the Modules, and Power Supplies sections of this document. This
procedure, and its diagrams and instructions, must be followed closely to
avoid damage to the control panel and its associated equipment. To a
great extent, reliability depends upon proper installation and maintenance.
1. Cabinet--Mount the cabinet and draw all field wiring through the
knockouts provided (Figure 3). Ensure that the cabinet is properly
grounded to earth.
Note: If the door is to be hung on the left side, mount door hardware
now. The MPS-24A/MPS-24B rests on the lower door mount.
Do not draw wiring into the bottom nine inches of the cabinet,
or conflict with the power supply and batteries may result.
2. Chassis--Mount all chassis. Refer to Figures 12 and 13 for
installation of the CHS-4 and CHS-4L chassis.
3. Main Power Supply--Mount the main power supply to the cabinet as
illustrated in Figure 15. Do not wire anything at this time!
4. Audio Visual Supplies--If any optional Audio Visual Power Supplies
(AVPS-24) are to be employed, mount them to the chassis. Refer to
Figure 14 for mounting of the AVPS-24 to the CHS-4.
5. Audio Visual Cables--Connect the AVPS trouble cable(s). Connect
the auxiliary bell power harness to the AVPS-24. Refer to Figure 36
to connect these cables.
6. Auxiliary Relay Modules--If any optional Auxiliary Relay Modules
(ARM-4) are to be employed, mount them to the chassis as illustrated
in Figure 16.
7. Preliminary System Wiring--The main power supply and any
AVPS-24s or ARM-4s should be wired at this time while the
terminals are readily accessible. Refer to the Power Supplies section
of this document to wire the MPS-24A/B, the AVPS-24s (see
Figure 36) and any ARM-4s (see Figure 22).
8. Module Ribbon Cables--Connect the first row ribbon cable to the
CPU as illustrated in Figure 17. For each additional row of modules
installed in the cabinet, connect an expander row ribbon cable to the
CPU.
9. CPU-2000--Install the CPU module in the top left cabinet position as
illustrated in Figure 20. Connect the power ribbon and power harness
between the CPU and the main power supply as illustrated in
Figures 32 and 35.
10. Module Expander Boards--If optional expanders are to be used with
a module, install as illustrated in Figure 18.
Installation
Outline