Instruction Installation of an additional wood fibre insulation for SpeedUp Eco
7 8
Always cross-lay the second layer of insulation panels to the previous one.
The final layer of insulation must be cross-layed to the SpeedUp heat
panels above.
Enclose pipe section with panels (maximum width 30 cm according to
BEB/ZDB Information leaflet) and fix and then fill up with bonded
compound up to level of insulation.
9 10
Pipe sections with insulated pipes and with width from 20 cm must be
covered with a 1 mm aluminium plate and with 5 cm overlap.
Note!
For light floor constructions (e.g. when laying laminate/parquet directly
on the heat panel and all strongboard constructions) pipe channels - in
the additional insulation - with a width of more than 10cm must be cov-
ered with a metal plate (min. 1 mm). If the pipe channels have a width of
more than 15 cm a special loadbaring plate (min. 18 mm OSB or similar)
must be used.
Important: Protect insulation from frequent pedestrian traffic to avoid
damage.