3
Power Up and Test Relays
Apply power to the power supply only. As
shown in Figure 2, press the Relay
Control Button next to each relay’s
yellow plug-in termination to toggle it on/
off. The relay should “click” and the LED
status indicator should change state.
Confirm the operation by measuring the
continuity at the line-voltage terminations
of each relay.
Apply power to the relays. Being careful
not to touch any line-voltage wiring,
toggle each relay on/off again and
confirm that each relay controls the
appropriate load.
1 Press and hold the Channel Push Button for several seconds. The red channel
LED and the LEDs for relays currently controlled by that input will begin to flash.
2 Select the relays to be controlled. The LED for each relay “smartwired” to the
channel input selected will be flashing on/off. Press the associated Relay Control
Button to add/delete that relay to/from the group.
3 Press the Channel Push Button again. The LEDs will stop flashing and the input
switch will now control the relays selected.
Test. Press the Channel Push Button to toggle the group on/off/on. The input
LED will track the last action. Now, turn off each relay in the group using the individual
Relay Control Buttons. When the last relay is turned off, the channel LED should also
go off.
Figure 4 – Smartwiring a Relay Group to a Channel
3
PRESS
AND
HOLD
CHANNEL
PUSH
BUTTON
PRESS
CHANNEL
PUSH
BUTTON
AGAIN
1
FLASHING
RED LED
2
PRESS
RELAY
CONTROL
BUTTON
FLASHING
LED
Figure 3 – Smartwired Switching System Relay Scedule
Figure 2 – Power Up and
Test Relays
RELAY
CONTROL
BUTTON
TO RELAY
LED
Document Relay Wiring
Record the circuit controlled by each
relay on the Smartwired Switching
System Relay Schedule (Figure 3).
The relays associated with automation
channels A-H are recorded later.
Smartwiring a
Relay Group to a Channel
Each SS panel includes eight “channels”
(A-H) which may be smartwired to relays
within the panel. Channels are used to
group relays for common control.
When an SS system includes an
automation module (HCLK8SS Network
Clock or HBMS8SS Building Automation
System Interface Module), we strongly
recommend you turn to the installation
instructions for that automation module
and complete the documentation before
softwiring any relays to channels.
However, if automation is to be provided
by an interface to another system, or by
using manual switches only, the channels
may be used simply for grouping relays.
Follow the instructions in Figure 4.
HINxxy12SS
(
SP
)
/ 24SS
(
SP
)
/ 48SS
(
SP
)
Smartwired
™