Huawei F2A-8K36H Installation guide

Type
Installation guide
6.1
Install guide rails.
Installing Cables
7
Installing the Device into a Cabinet
6
6.3
Install mounting brackets.
Device Overview
1 2 Safety Guidelines Site Requirements
3Cabinet Requirements
4
1
2
Adjust the length of one guide rail according to the distance between the front and rear mounting rails, place the guide
rail horizontally at the determined installation position in the cabinet, and hook it to the cabinet's front and rear mounting
rails.
Install M6 screws at the front and rear sides of the guide rail, tighten them to 3 N·m of torque to secure the guide rail to
the cabinet, and then install another guide rail in the same manner.
6.2
Install floating nuts (for mounting brackets).
6.4
Install the device into the cabinet.
Considering the weight of the device, it is recommended that at
least two persons move it to the cabinet to prevent it from falling
and possibly causing injury.
STAT
BREAKOUT
0
1
2
3
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
Observe all safety regulations and precautions
NetEngine 8000 F2A-8K36H
Ensure that the guide rails
do not tilt inward.
CAUTION
CAUTION
DW
H
2
1
1.2 N•m
M4
STAT
BREAKOUT
0
1
2
3
STAT
BREAKOUT
0
1
2
3
Install two floating nuts in the positions slightly above the guide rail on each front mounting rail. Install the two floating
nuts in every other mounting hole.
To secure the mounting brackets to the chassis, use a torque screwdriver to tighten the three M4 cross recessed countersunk
head screws on each of the left and right mounting brackets to 1.2 N·m of torque.
Facing the front of the cabinet, horizontally slide the chassis into the cabinet until the mounting brackets are in close contact
with the mounting rails and aligned with the floating nuts. Secure the mounting brackets to the cabinet with M6 screws.
3 N•m
M6
3 N•m
M6
3 N•m
M5
7.8 N•m
M8
3 N•m
M6
Floating nuts
Power module
Fan module
Ground terminal
Ground terminal Power side
Port side
Floating nut
Power cable label
ESD wrist strap
Cable tie
Cross recessed countersunk head screw
Cross recessed pan head screw
Signal cable label
Fiber binding tape
Serial cable
Panel screw
Installation accessories:
Tweezer
Insulation tape
Label cable tie
Guide rail
IEC mounting bracket
Figures in the document are for reference only and may be
dierent from actual devices.
When installing a device in a cabinet, ensure that at least 1U
space is reserved above and below the device for appropriate heat
dissipation.
The airflow direction of power and fan modules must be the same
as that of the device to which they will be installed. For example,
power and fan modules to be installed on a device that adopts
port-side air intake must also utilize this type of airflow, and the
labels on these modules are red. Likewise, power and fan modules
to be installed on a device that adopts port-side air exhaust must
also utilize this type of exhaust, and the labels on these modules
are blue.
NOTE
Item
Weight without
packaging (full
configuration) [kg(lb)]
Power supply specifications
NetEngine 8000 F2A-8K36H
(Front-to-Rear and Rear-to-Front
Airflow)
86.1 mm x 442 mm x 600 mm
(3.39 in. x 17.4 in. x 23.62 in.)
280 mm x 660 mm x 875 mm
(11.02 in. x 25.98 in. x 34.45 in.)
DC power supply: 21 kg (46.30 lb)
Dimensions without packaging
(H x W x D) [mm(in.)]
Dimensions with packaging
(H x W x D) [mm(in.)]
AC power supply: 20.5 kg (45.19 lb)
Rated input voltage:
DC: –48 V to –60 V
AC: 90 V to 120 V(dual-live-wire)
/190 V to 240 V
HVDC: 190 V to 240 V
Input voltage range:
DC: -40 V to -72 V
AC: 90 V to 290 V
HVDC: 190 V to 290 V
Maximum input current:
DC: 50 A AC/HVDC: 16 A
To ensure personal and equipment safety, observe all the safety
precautions on the equipment and in this document.
and items do not cover all
the safety precautions and are only supplementary to the safety
precautions.
Follow all the safety precautions and instructions provided by
Huawei. The safety precautions outlined in this document are only
requirements of Huawei and do not cover general safety regulations.
Huawei is not liable for any consequence that results from violation
of regulations pertaining to safe operations or safety codes
pertaining to design, production, and equipment use.
NOTICE
DANGER WARNING CAUTION
Only trained and qualified personnel are allowed to install, operate, or
maintain the equipment. Familiarize yourself with all safety
precautions before performing any operation on the equipment.
Personnel Safety
Do not install or remove the equipment or power cables while
power is on.
To ensure equipment and personal safety, ground the equipment
before powering it on.
DANGER
Laser beams will cause eye damage. Do not look into bores of
optical modules or optical fibers without eye protection.
WARNING
Keep an unpacked device upright and handle it with care when
carrying it or installing it into a cabinet.
Do not touch unpainted surfaces of the equipment with wet or
contaminated gloves.
NOTICE
For details about how to install guide rails, see the
installation guide delivered with the guide rails.
Install the guide rails according to the left and right
marks on the guide rails.
NOTICE
Before installing, operating, or maintaining the
equipment, wear an ESD wrist strap and insert
the other end into the ESD jack on the chassis
or cabinet. Remove conductive objects like
jewelry and watches to prevent damages to
the equipment caused by electrostatic
discharge.
ESD protection
The routers must be used indoors. To ensure normal operations and
long service life of the router, the installation site must meet the
following requirements:
The equipment must be installed in a clean, dry, and well ventilated
standard equipment room where temperature can be controlled
within a proper range. The equipment room must be free from
leaking or dripping water, heavy dew, and humidity.
Take dustproof measures in the equipment room. Dust will cause
electrostatic charges on the chassis and aect connections of metal
connectors and joints. This shortens equipment service life and may
cause failures of the router.
The installation site must be free from acidic, alkaline, or other
corrosive gases.
The temperature and humidity in the installation site must be within
allowed ranges.
Item
Long-term operating
temperature [°C(°F)]
Storage temperature
[°C(°F)]
Storage relative
humidity [RH]
Requirement
–40°C to +70°C (–40°F to +158°F)
Port-side intake: –5°C to +45°C (23°F to 113°F)
Port-side exhaust: –5°C to +40°C (23°F to 104°F)
5% to 95% RH, non-condensing
Storage altitude
[m(ft.)] < 5000 m (< 16404.2 ft.)
NOTE
When the altitude is between 1800 m and
4000 m, the highest operating temperature
reduces by 1ºC every time the altitude
increases by 220 m.
Long-term operating
relative humidity [RH] 5% to 90% RH, non-condensing
Short-term operating
relative humidity [RH] 5% to 95% RH, non-condensing
5Power Supply Requirements
For hierarchical power supply protection, the current of each circuit breaker must be at least 16 A when the router adopts AC
power supply. Similarly, the current of each circuit breaker must be at least 50 A if the router adopts DC power supply.
The device supports front-to-rear and rear-to-front heat dissipation
modes. To ensure smooth and ecient heat dissipation, check the
airflow direction of the equipment room where the device is to be
installed, and ensure that cold air flows into the device from the air
intake vent and leaves from the air exhaust vent.
The device is air-cooled. The air intake and air exhaust vents must
be free from obstacles, such as labels, to prevent the air intake and
air exhaust vents from being blocked.
You are advised to select the power cable's cross-sectional area
and the device's circuit breaker according to the site survey result.
A 19-inch standard cabinet must be used, with a depth of greater
than or equal to 800 mm (23.62 in.)
For a cabinet with doors, reserve at least 110 mm clearance
between the device's front panel and the cabinet's front door, and
at least 100 mm clearance between the device's rear panel and the
cabinet's rear door. Note that the 110 mm clearance applies to
scenarios where there is no optical attenuator and the optical fibers'
LC connectors are 42 mm long at most. If there are optical
attenuators and the length of the optical fibers' LC connectors is
greater than 42 mm, the clearance is 110 mm plus the cable routing
space for the optical attenuators and optical fibers.
Each cabinet door must have 50% or higher porosity.
The cabinet must meet front-to-rear ventilation requirements.
The cabinet must be equipped with air filters.
The distance between front and rear mounting rails must be in the
range from 450 mm to 730 mm.
Huawei A610 cabinets are recommended. A self-purchased cabinet
must meet the following requirements:
Dimensions without packaging
(H x W x D)
2200 mm x 600 mm x 1000 mm
(86.61 in. x 23.62 in. x 39.37 in.)
Dimensions with packaging
(H x W x D)
2320 mm x 720 mm x 1290 mm
(91.34 in. x 28.35 in. x 50.79 in.)
The device is inserted into the cabinet from the front of the cabinet.
NOTE
NOTE
Install the ground cable between the device
and cabinet.
1Install the cabinet ground cable.
2
Install power cables.
Install DC power cables.
1Install AC or high-voltage DC power cables.
2
Install ground cables.
Ensure that power cable terminals are properly connected with correct polarity.
DC power cables need to be prepared onsite. For details, see
.
Install network cables
Before bundling network cables, use a network
cable tester to test cable connectivity.
Bundle the network cables in a rectangle shape.
Ensure that the cable ties are evenly spaced and
face the same direction.
Route cables at a proper distance from each
other. Otherwise, the installation of other cables
may be aected.
Route Ethernet cables, power cables, and
ground cables separately. The Ethernet cables
must not be damaged or broken or have joints.
NOTE
NOTICE
Install optical fibers.
Install corrugated pipes.
1Install optical cable.
2
Wear an ESD wrist strap or ESD gloves before installing optical modules.
NOTICE
The bending radius of the single-mode G.657A2 optical fiber and the multi-mode A1b
optical fiber must be greater than or equal to 5D (D: diameter of the optical fiber).
Cover empty optical ports and idle optical modules with dust caps.
Do not bundle optical fibers too tightly. You must be able to conveniently remove a
single fiber from the bundle.
Properly fix optical fibers onto the cabinet columns to prevent impact on the
surrounding devices.
Route cables.
Do not bundle or route outdoor cables (such as outdoor antenna feeders and
outdoor power cables) and indoor cables together in the cabinet or on the
cable tray.
NOTICE
To route optical fibers along both sides of a device, ensure that at least 110
mm spacing be reserved between the device's front panel and the cabinet's
front door, and at least 100 mm spacing between the device's fan side and
the cabinet's rear door. Note that the 110 mm spacing applies to scenarios
where there is no optical attenuator and the optical fibers' LC connectors are
42 mm long at most. If there are optical attenuators, the spacing is 110 mm
plus the optical attenuator height.
It is recommended that power cables and Ethernet cables are routed at a different side
of the device. Ensure that these cables do not span fan modules.
To facilitate cable routing and maintenance, you are advised to route optical fibers
along both sides of the device, as shown in the figure.
Cable connection table
Select DC power cables based on the types of
terminal blocks used in your equipment
room. For more information, see "DC Power
Cable" in the
Hardware Description.
5
Select appropriate fibers for optical modules.
For more information, see "Optical Fiber"
and "Optical Module" in the
Hardware Description.
1A
1B
2A
2B
Optical module +
fiber jumper
Optical port
NetEngine 8000
Select AC/HVDC power cables based on the
types of power sockets used in your
equipment room. For more information, see
"AC Power Cable" in the
Hardware Description.
No. Item Remarks
1
3
Connect To
Chassis
ground
point
Chassis ground cable
4This port connects the router to an operation
terminal or a network management station.
ETH
management
port
Ethernet cable
Terminal block
on the DC
PEM
DC power cable
2
NetEngine 8000F2A-8K36H
One end of a chassis ground cable is
connected to the ground screw on the
cabinet column, and the other end is
connected to the ground screw on the
chassis.
AC/HVDC power cable
AC/HVDC
power socket
NetEngine 8000
F2A-8K36H
F2A-8K36H
8 9 10
Checking After the Installation Performing a Power-on Check
Before performing a power-on check,
ensure that power switches on the
external power supply system and the
router are turned o.
Check whether the voltage of the input terminal on each power module is
within the normal range. (DC: –40 V to –72 V; AC: 90 V to 290 V)
For more information about indicators, see the .
F2A-8K36H Hardware Description
NOTE
Indicator status when the router is working normally
Component Indicator Status
Power module
Fan module
Management panel
Front system indicator
Steady green
STAT
Steady green
STAT Steady green
STAT Steady green
Obtaining Product Documentation
and Technical Support
Power on the device and check whether indicators on the device are normal.
Turn on the external power supply and check whether the output voltage
meets the power supply requirements of the device.
All assembled PGND cables are copper-based, with correct wire diameters. No switch or fuse
is allowed on the cables, and no short circuit occurs.
All ground cables, AC input cables, and intra-cabinet cables are connected correctly
according to the wiring diagram, and all screws are fastened. The input and output cables
are not short-circuited.
Any redundant parts of power cables or PGND cables are trimmed o.
The terminals at both ends of each power cable or PGND cable are crimped securely.
The wiring terminals on cables are wrapped tightly using PVC insulation tapes or heat
shrink tubes.
The wiring terminals with heat shrink tubes are heated using a heat gun.
Flat and spring washers are properly installed on each bolt of a wiring terminal.
All cables, especially the cables in the lower area of the cabinet, are securely connected.
Power and ground cables are bundled and separated from other cables.
The cable layout facilitates future maintenance and expansion.
The labels at both ends of each cable are correct and legible.
All bolts and screws are firmly fastened, especially on electrical connections. Flat and spring
washers are used with each bolt, and spring washers are placed on the top of flat washers.
Check ItemNo.
1
3
6
7
8
9
10
12
11
2
4
5
WARNING
Trademarks and Permissions
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.
No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.
Copyright © Huawei Technologies Co., Ltd. 2021. All rights reserved.
Supplier’s Declaration of Conformity (SDoC)
Unique Identifier: trade name: HUAWEI; product name: Router;
model number: NetEngine 8000 F2A-8K36H routers
Party issuing Supplier’s Declaration of Conformity
Huawei Technologies Co., Ltd.
Bantian, Longgang District,
Shenzhen, 518129, P.R.C
Tel: +86 755 28780808
Responsible Party- U.S. Contact Information
Huawei Technologies USA Inc.
5700 Tennyson Parkway, Suite 600
Plano, Texas 75024
Main: 214-919-6000 / TAC Hotline: 1-877-948-2934
FCC Compliance Statement ( for products subject to Part 15)
This device complies with part 15 of the FCC Rules. Operation is subject to the following
two conditions: (1) This device may not cause harmful interference, and (2) this device
must accept any interference received, including interference that may cause undesired
operation.
Open Source Software Notice
You can view the open source software notice by running the display copyright command in the user view.
Huawei Enterprise
Technical Support
Log in to Huawei enterprise technical support website
(https://support.huawei..com/enterprise), and select a specific
product model and version to find its documentation.
Log in to Huawei enterprise support community
(https://forum.huawei.com/enterprise) and post your
questions in the community.
For enterprise users:
Log in to Huawei carrier technical support website
(https://support.huawei.com/carrier), and select a specific
product model and version to find its documentation.
Log in to carrier enterprise support community
(https://forum.huawei.com/carrier) and post your questions in
the community.
For carrier usesrs:
Huawei Carrier
Technical Support
1U
×
×
STAT
BREAKOUT
0
1
2
3
STAT
BREAKOUT
0
1
2
3
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0 GE1
12
STAT
BREAKOUT
0
1
2
3
1
2
STAT
BREAKOUT
0
1
2
3
1
STAT
BREAKOUT
0
1
2
3
Power cable Ethernet cable
Power cable
STAT L/A
CLK
MGMT-ETH
CON/AUX
TOD/CLK-TEST
RST
HP-GE
GE0GE1
Front Rear
Long-term operating
altitude < 4000 m (< 13123.4 ft.)
110 V AC power supply requires dual-live-wire
input.
NetEngine 8000 F2A-8K36H Hardware
Description
CAUTION
CAUTION
CAUTION
Issue: 01
Part Number:31500GBC
Scan to Watch Quick Installation Guide
NetEngine 8000 F2A-8K36H
Quick Installation Guide