Installation Instructions
Set Drain
n
Connect the rough-in xture to the pipe and adjust the Coring
Sleeve to be ush, or slightly below slab level.
n
No need to estimate/anticipate nish oor level at rough-in,
no need to wrap threads or cover top with duct tape.
n
Apply adhesive (silicone) to the Coring Sleeve threads, if
desired, to lock it in place before the slab is poured.
Install/Adjust Finish Fixture
n
Install the Finish Fixture into the Coring Sleeve and adjust
to oor level - from ush*, to 1¼” above the Coring Sleeve.
Extensions are available for additional height.
n
No problem if ooring spec changes after rough-in.Flooring
contractor can make nal adjustments to height and
alignment as necessary for a perfect nish.
n
Apply adhesive (silicone) to the Finish Fixture threads, if
desired, to lock it in place.
*Minimum height with square strainer = "
Remove Coring Plug
n
After rough construction, and before the nish oor is
installed, remove the Coring Plug.
n
The Coring Plug has taken all the job site abuse, protected
the internal threads and prevented debris from entering the
drain lines.
n
Coring Plug is recyclable with all #2 (HDPE) materials.
Perfect Finish
n
The FinishLine allows for a perfect nish, reecting the
professionalism with which it was specied and installed.
n
No job site damage to strainers/covers.
n
No xtures too low or too high.
n
No tilted xtures.
n
No scraping duct tape.
n
No boxing out.
Pour/Finish Concrete Slab
n
Pour and nish the slab ush with the Coring Sleeve.
n
The ush surface makes it easy for concrete contractors to
provide a smooth, at slab nish.
n
No need to be present during the pour to make last-minute
corrections/adjustments.
Correct for Level
n
If the Finish Fixture surface is tilted, remove the
ring/strainer and install FinishLine Shims as needed to bring
low sides up to oor level.
n
Stack multiple Shims if necessary.