Miele 52840705USA Installation Plan

Type
Installation Plan
35.14 M.-Nr. 10 001 970
Installation Plan
Tumble dryer
PT 8407 EL (Electrically Heated)
en - US
It is essential to read the operating and installation instructions before
installing, commissioning or using the machine.
This avoids the risk of accidents or damage.
All rights reserved
U.S.A.
Miele, Inc.
National Headquarters
9 Independence Way
Princeton, NJ 08540
Phone:
Fax:
www.mieleusa.com
Technical Service & Support
Nationwide
Phone:
800-991-9380
Fax:
800-220-1348
800-991-9380
609-419-4241
2
35 5/8
35 3/8
3/4
3/4
20 1/2
25 5/8
55 1/8
41 7/8 25 1/4
45 7/8
41 3/4
2 5/8 1 1/2
55 1/8
3/4
63
23 3/8
24 3/4
PT 8407 EL - measurements in inches
3
<
45 7/8
35 3/8
35 5/8
41 3/4
63
2
5 7/8
6 1/4
6 3/8
PT 8407 EL - measurements in inches
4
24 3/8 11
63
52 7/8
7 7/8
5 7/8
5
12
63
5
12
PT 8407 EL - measurements in inches
5
55 1/8
3/4
55 1/8
3/4
2
31 1/8
2 1/82 1/8
15 1/2
2142
35 3/8
63
41 3/4
2 1/8
2 1/8
21
42
35 3/8
15 1/2
31 1/8
63
47 1/4
3/8
2
2
2
2
2
3/8
PT 8407 EL - measurements in inches
6
PT 8407 EL - measurements in millimeters
7
<
PT 8407 EL - measurements in millimeters
8
PT 8407 EL - measurements in millimeters
9
PT 8407 EL - measurements in millimeters
10
Installation plan: PT 8407 EL
Date: 02.09.2014 Page: 11
Technical datasheet
Tumble dryer:
Heating:
PT 8407
Electric (EL)
Legend:
Abbreviations in bold type:
Connection required
Abbreviations in circle with dashes:
Connection optional or required depending on model version
Optional ex
tras:
BS
Concrete base
Quality and density of concrete must comply with load.
Concrete base must be firmly secured to floor!
Recommended height
4
100 mm
Minimum height
2“
50 mm
Width min.
35 3/8
900 mm
Width min.
47 1/4“
1200 mm
Machine con
nections:
Electrical
connection
(convertible)
1.
Standard voltage
3 AC 208V
Frequency
60 Hz
Rated load
67264 BTU/h
19.7 kW
Fuse rating
3 x 65 A
4 x AWG 6
4 x 16 mm²
Connection cable, min. cross-section
Connection cable to be ordered separately
2.
Standard voltage
Frequency
Rated load
Fuse rating
3 AC 220 - 240V
60 Hz
74776 - 83653 BTU/h 21.9 - 24.5 kW
3 x 65 A
4 x AWG 6 4 x 16 mm²
Connection cable, min. cross-section
Connection cable to be ordered separately
Electrical connection must comply with national
regulations.
Connection using multi-pole wall socket in compliance
with IEC/EN 60309 and IEC/EN 60947 is recommended
in order to simplify electrical tests.
If machines are hard-wired, a multi-pole mains switch
must be provided on site.
A wall socket or main isolator must be accessible after
installation.
Installation plan: PT 8407 EL
Date: 02.09.2014 Page: 12
Equipotential
bonding
Connection with male thread
3/8“ x 1 3/8“
10 mm × 35 mm
with washers and nut.
Accessories not included.
If necessary, equipotential bonding with good galvanic
contact must be provided in accordance with all
appropriate national and local regulations.
Vented Max. nominal air flow in vented mode 28252 cu ft/h 800 m³/h
Max. permissible pressure loss 0.04 psi 300 Pa
Connection on machine side (ext. diameter) 5 7/8 150 mm
Connection pipe provided on site (int. diameter) 5 7/8 150 mm
Max. temperature 176 °F 80 °C
As relative humidity inside the vent duct can be as high
as 100%, suitable measures must be taken to prevent a
backflow of condensate into the machine.
Air intake Standard connection: Air intake from installation site
Unobstructed air intake into room recommended
(corresponding to 3 times the vent cross-section of
machine)
82.3 in² 531 cm²
A sufficient supply of fresh air should be ensured to
replace the air extracted.
Alternative connection: Ducted air intake (from
outside building)
Connector on machine (int. diameter) 6 3/8 161 mm
Connection pipe provided on site (ext. diameter) 6 1/4 160 mm
Lid removal exposes live components! For safety
reasons, the pipe connected for central air intake should
be at least 35 7/16” [900 mm] long and secured using
two screws.
Fittings Without base
2 × clamps
2 × screws DIN 571 (Ø × length) 1/4“ x 1 5/8 6 mm × 40 mm
2 × rawl plugs (Ø × length) 3/8“ x 2 10 mm × 50 mm
The machine should be bolted to the floor.
Fixing materials for floor screed are to be provided on
site.
1/4“ x 1 5/8 6 mm × 40 mm
3/8“ x 2 10 mm × 50 mm
On concrete platform
2 × clamps
2 × screws DIN 571 (Ø × length)
2 × rawl plugs (Ø × length)
Machine must be bolted to the floor!
Fixing materials for floor screed are to be provided on
site.
Machine data Unit width 35 5/8 906 mm
45 7/8 1164 mm
55 1/8“ 1400 mm
35 3/8 900 mm
Machine depth
Unit height
Casing width
Casing depth 41 3/4 1059 mm
36 1/4 920 mm
63“ 1600 mm
Minimum width of delivery access to installation site
Recommended rear wall gap
(measured to front of machine)
Min. wall gap (to rear edge of lid)
19 3/4 500 mm
421.08 lbs 191 kg
2170 N
2219.4 BTU/h 650 W
72.8 dB (A)
Net weight
Dynamic floor load, max.
Average heat dissipation
(dependent on ambient room temperature and
programme selected)
Noise level
Sound pressure level
(measured at a distance of 39 3/8” [1 m] from the
machine and at a height of 63” [1.6 m])
60 dB (A)
Installation should only be carried out by authorized installers in accordance with all local and national regulations!
Follow installation instructions when installing machine. All rights reserved.
(supplied)
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12

Miele 52840705USA Installation Plan

Type
Installation Plan

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI