Vessel manual – ECRE cascade cooler
0011001 en 2022.04 7/9
Shipping
Shipping
The vessel is delivered primed and with blinded connections. This ensures sufficient surface
protection during normal operating conditions. If, however, the vessel is going to be stored out-
side, the surface must be protected against corrosion. If operation is disengaged and vessel
storage is needed, preventive measures must be taken to eliminate any contamination through
open ports.
Mobility
The vessel may only be relocated in an empty state. Any excessive impact suffered during
transportation or relocation may damage the vessel substantially. If the vessel should be
craned on its own, slings must be used, and they must be strapped around the vessel arch.
Installation
Safety on site and the safety of personnel must be in compliance with the EN 378-3 standard.
Post-transport inspections must be carried out on arrival. In case of damage to the vessel, in-
stallation must be aborted immediately.
When relocating the vessel on site, make sure to leave sufficient space for inspection, mainte-
nance and emergency escape routes.
The bedplate or foundation must be robust to withstand the strains inflicted by the vessel and
absorb external vibrations.
During installation, all vessel ports and openings must be protected against impurities. Do not
expose any ports or openings until their services are needed.
Before the vessel is taken into service, make sure that the entire system is clean of impurities
and foreign substances. Piping connections must not induce further mechanical stress in the
vessel, under any circumstances. Vibrations should be minimised by using vibration dampers
or the like.
Welding or other externally induced thermal stress is not permitted. Protective measures must
be taken to safeguard the vessel from exceeding the maximum allowable pressure and
temperature.
If the vessel is going to be installed in a harsh environment, further corrosive protection must
be applied to all exposed areas.
Safety equipment
The site operator is responsible for all personal and site related safety equipment needed to
safely relocate, install and operate the vessel. Safety equipment is not part of the delivery. The
vessel manufacturer cannot be held liable for any defective or missing safety equipment.
Initial start-up and operation
Upon commissioning of the vessel, it is the site manager’s responsibility to ensure that all rele-
vant personnel and staff are briefed and trained in compliance with EN 378-3. This includes
training in maintenance of the vessel construction and operation of the vessel.
Refrigerant charging and draining must be carried out according to the instructions in the unit
documentation. Always perform leak testing before any charging.