Condair 2587516-C LINKS ProtoCessor Installation guide

Type
Installation guide

The Condair 2587516-C LINKS ProtoCessor is a gateway device that allows Condair humidification and evaporative cooling units to interface with building automation systems using BACnet MS/TP, BACnet/IP, Metasys N2, and LonWorks protocols. It provides seamless integration and data exchange between the Condair unit and the building management system, enabling centralized control and monitoring of the humidification or cooling process.

The Condair 2587516-C LINKS ProtoCessor is a gateway device that allows Condair humidification and evaporative cooling units to interface with building automation systems using BACnet MS/TP, BACnet/IP, Metasys N2, and LonWorks protocols. It provides seamless integration and data exchange between the Condair unit and the building management system, enabling centralized control and monitoring of the humidification or cooling process.

INSTALLATION AND
OPERATION MANUAL
ProtoCessor FPC-ED2 and
ProtoCessor FPC-ED4
Condair LINKS
2587516_D_EN_2001
Humidification and Evaporative Cooling
For Interfacing Condair Products:
Nortec… NH-EL, GS, EL, RS
To Building Automation Systems:
BACnet MS/TP, BACnet/IP, Metasys N2 and LonWorks
Technical Support
Thank you for purchasing the ProtoCessor for Condair.
Please call Condair for Technical support of the ProtoCessor product.
Sierra Monitor Corporation does not provide direct support. If Condair needs to escalate the concern, they
will contact Sierra Monitor Corporation for assistance.
Support Contact Information:
U.S.A.
Condair Inc.
2700 90th Street
Sturtevant, WI 53177
USA
Canada
Condair Ltd.
2740 Fenton Rd
Ottawa, Ontario
K1T 3T7
Condair Service:
1.866.667.8321
Fax:
1.613.822.9764
Email: na.info@condair.com
Website: www.condair.com
APPLICABILITY & EFFECTIVITY
Explains ProtoCessor FPC-ED2 hardware and how to install it.
The instructions are effective for the above as of OCT 2018.
Document Revision: 2.I
Web Configurator
Template Revision: 60
INSTALLATION AND
OPERATION MANUAL
Condair LINKS
ProtoCessor FPC-ED2
and ProtoCessor FPC-ED4
2587516_D_EN_2001
Thank you for choosing Condair
Installation date (DD/MM/YYYY):
Commissioning date (DD/MM/YYYY):
Site:
Model:
Serial number:
Manufacturer
Condair Ltd.
2740 Fenton Road, Ottawa, ON, Canada K1T 3T7
Tel. 1.866.667.8321, Fax 613.822.7964
na.info@condair.com, www.condair.com
Proprietary Notice
This document and the information disclosed herein are proprietary data of Condair Ltd. Neither this docu-
ment, nor the information contained herein shall be reproduced, used, or disclosed to others without the
written authorization of Condair Ltd., except to the extent required for installation, operation or maintenance of
the customer's equipment.
Liability Notice
Condair Ltd. does not accept any liability due to incorrect installation, maintenance or operation of the
equipment, or due to the use of parts/components/equipment that are not authorized by Condair Ltd.
Copyright Notice
Copyright 2019, Condair Ltd, All rights reserved.
Technical modification rights reserved.
Condair LINKS 2587516_D_EN_2001 I V
Contents
1 Quick Start Guide ........................................................................................................ 7
2 Certifications ................................................................................................................ 8
3 Introduction .................................................................................................................. 9
3.1 ProtoCessor Gateway ................................................................................................... 9
4 Setup for ProtoCessor ...............................................................................................10
4.1 Record Identification Data ............................................................................................10
4.2 Point Count Capacity and Registers per Device ...........................................................10
4.3 Configuring Device Communications ............................................................................10
4.3.1 Input COM Settings for Device with an Inserted ProtoCessor ..................................10
4.3.2 Set Modbus RTU Node-ID for the Device ................................................................11
5 Interfacing ProtoCessor to Device ............................................................................12
5.1 ProtoCessor FPC-ED2 and FPC-ED4 Mounted onto Board .........................................12
5.2 ProtoCessor FPC-ED2 and FPC-ED4 Showing Connection Ports................................13
5.3 BACnet MS/TP or Metasys N2: Wiring Field Port to RS-485 Network ..........................14
5.4 LonWorks (FPC-ED4): Wiring Field Port to LonWorks Network ....................................14
6 Use ProtoCessor Web Configurator to Setup the Gateway .....................................15
6.1 Connect the PC to ProtoCessor via the Ethernet Port ..................................................15
6.2 Connecting to ProtoCessor Web Configurator ..............................................................16
6.3 Selecting Profiles for Device Connected to ProtoCessor ..............................................16
6.4 BACnet/IP Setting IP Address for Field Network ..........................................................19
6.5 Select Field Protocol ....................................................................................................21
6.5.1 BACnet MS/TP Configuration ..................................................................................21
6.5.2 BACnet/IP Configuration .........................................................................................22
6.5.3 Metasys N2 Configuration .......................................................................................23
7 BACnet MS/TP and BACnet/IP: Setting Node_Offset to Assign
Specific Device Instances ...........................................................................................25
8 How to Start the Installation Over: Clearing Profiles ...............................................26
9 LonWorks (FPC-ED4): Commissioning ProtoCessor on a lonworks Network .......27
9.1 Commissioning ProtoCessor FPC-ED4 on a LonWorks Network .................................27
9.1.1 Instructions to Download XIF File from ProtoCessor FPC-ED4 Using Browser........27
A Troubleshooting ........................................................................................................... i
A.1 Lost or Incorrect IP Address ............................................................................................ i
A.2 Viewing Diagnostic information ...................................................................................... ii
A.3 Check Wiring and Settings ............................................................................................. ii
A.4 LED Diagnostics for Communications Between ProtoCessor and Device ..................... iii
A.5 Take Diagnostic Capture With the FieldServer Utilities .................................................. iv
VI | 2587516_D_EN_1909 Condair LINKS
A.6 Update Firmware .......................................................................................................... vii
A.7 BACnet: Setting Network_Number for more than one ProtoCessor on Subnet ............. vii
A.8 Securing the ProtoCessor with Passwords .................................................................. viii
B Vendor Information - Condair ................................................................................... viii
B.1 NHEL Modbus RTU Mappings to BACnet, Metasys N2 and LonWorks ....................... viii
B.2 GS Modbus RTU Mappings to BACnet, Metasys N2 and LonWorks ............................. ix
B.3 EL Modbus RTU Mappings to BACnet, Metasys N2 and LonWorks ............................... x
B.4 EL Modbus RTU Mappings to BACnet, Metasys N2 and LonWorks .............................. xi
C Reference ................................................................................................................... xiii
C.1 Specifications .............................................................................................................. xiii
C.2 Compliance with UL Regulations ................................................................................. xiii
Condair LINKS 2587516_D_EN_2001 I 7
1 Quick Start Guide
1. Record the information about the unit. (Section 4.1)
2. Set the device’s Modbus RTU serial settings (i.e. baud rate, parity, stop bits) and
Modbus Node-ID’s for the device that will be connected to ProtoCessor FPC-ED2
or FPC-ED4. (Section 4.3)
3. Metasys N2 (FPC-ED2): Set the Node-ID. (Section 4.3.2)
4. BACnet MS/TP or BACnet/IP: Set the BACnet Device Instance. (Section 7)
5. Connect ProtoCessor FPC-ED2’s 3 pin RS-485 port to the Field Protocol
cabling, (Section 5.3)
or connect ProtoCessor FPC-ED4’s 2 pin LonWorks port to the Field Protocol
cabling. (Section 5.4)
6. Use a browser to access the ProtoCessor’s embedded tool, which is referred to
in this manual as the Web Configurator, to select the device that will be attached
to ProtoCessor and set the Modbus Node-ID. Once the device is selected, the
ProtoCessor Automatically builds and loads the Configuration. (Section 6)
7. BACnet/IP (FPC-ED2): Use a browser to access the ProtoCessor Web
Configurator to change the IP Address. No changes to the configuration are
necessary. (Section 6.4)
8. LonWorks (FPC-ED4): The ProtoCessor must be commissioned on the
LonWorks Network. This needs to be done by the LonWorks administrator using
a LonWorks Commissioning tool. (Section 9)
8 | 2587516_D_EN_1909 Condair LINKS
2 Certifications
BTL MARK BACNET TESTING LABORATORY
LONMARK CERTIFICATION
The BTL Mark on ProtoCessor is a symbol that indicates that a
product has passed a series of rigorous tests conducted by an
independent laboratory which verifies that the product correctly
implements the BACnet features claimed in the listing. The mark is a
symbol of a high-quality BACnet product.
Go to http://www.BACnetInternational.net/btl/ for more information
about the BACnet Testing Laboratory. Click here for BACnet PIC
Statement.
LonMark International is the recognized authority for
certification, education, and promotion of interoperability
standards for the benefit of manufacturers, integrators and end
users. LonMark International has developed extensive product
certification standards and tests to provide the integrator and
user with confidence that products from multiple manufacturers
utilizing LonMark devices work together. Sierra Monitor has
more LonMark Certified gateways than any other gateway
manufacturer, including the ProtoCessor, ProtoCarrier and
ProtoCessor for OEM applications and the full featured,
configurable gateways.
Condair LINKS 2587516_D_EN_2001 I 9
3 Introduction
3.1 ProtoCessor Gateway
ProtoCessor is an external, high performance Building Automation multi-protocol gateway that
is preconfigured to automatically communicate between Condair’s products (hereafter called
“device”) connected to the ProtoCessor and automatically configures them for BACnet
®1
MS/TP,
BACnet/IP, Metasys
®2
N2 by JCI or LonWorks
®3
.
It is not necessary to download any configuration files to support the required applications. The
ProtoCessor is pre-loaded with tested Profiles/Configurations for the supported devices.
1
BACnet is a registered trademark of ASHRAE
2
Metasys is a registered trademark of Johnson Controls Inc.
3
LonWorks is a registered trademark of Echelon Corporation
10 | 2587516_D_EN_1909 Condair LINKS
4 Setup for ProtoCessor
4.1 Record Identification Data
Each ProtoCessor has a unique part number located on the side or the back of the unit.
This number should be recorded, as it may be required for technical support. The numbers
are as follows:
Table 1: ProtoCessor Part Numbers
Model
Part Number
ProtoCessor FPC-ED2 FPC-ED2-1409
ProtoCessor FPC-ED4
FPC-ED4-1410
FPC-ED2 units have the following 2 ports: RS-485 + Ethernet
FPC-ED4 units have the following 2 ports: LonWorks + Ethernet
4.2 Point Count Capacity and Registers per Device
The total number of Registers presented by the device attached to the ProtoCessor
cannot exceed:
Table 2: Supported Point Count Capacity
Total Registers
1500
1500
Table 3: Registers per Device
Registers per Device
Nortec NHEL 35
22
35
59
4.3 Configuring Device Communications
4.3.1 Input COM Settings for Device with an Inserted ProtoCessor
Set the serial device that the ProtoCessor is plugged into to have the same Baud Rate,
Data Bits, Stop Bits, and Parity settings as the ProtoCessor.
Table 4: COM Settings specifies the device serial port settings required to communicate
with the ProtoCessor.
Condair LINKS 2587516_D_EN_2001 I 11
Table 4: COM Settings
Serial Port Setting
Device
Protocol
35
Baud Rate
9600
Parity
Even
Data Bits
8
Stop Bits
1
4.3.2 Set Modbus RTU Node-ID for the Device
Set Modbus Node-ID for the device the ProtoCessor is plugged into. (See Section 6.5 to
input Node-ID)
The Modbus Node-ID needs to be uniquely assigned between 1 and 255.
o The Modbus Node-ID that is assigned for the device needs to be
documented
The Modbus Node-ID assigned is used for designating the Device
Instance for BACnet/IP and BACnet MS/TP
The Metasys N2 and Modbus TCP/IP field protocol Node-IDs are automatically set to be
the same value as the Node-ID of the Modbus RTU device.
12 | 2587516_D_EN_1909 Condair LINKS
5 Interfacing ProtoCessor to Device
5.1 ProtoCessor FPC-ED2 and FPC-ED4 Mounted onto Board
Figure 1: Mounted ProtoCessor BACnet FPC-ED2 (upper) and ProtoCessor FPC-ED4 (lower)
Condair LINKS 2587516_D_EN_2001 I 13
5.2 ProtoCessor FPC-ED2 and FPC-ED4 Showing Connection Ports
Figure 2: ProtoCessor FPC-ED2 (upper) and ProtoCessor FPC-ED4 (lower)
14 | 2587516_D_EN_1909 Condair LINKS
5.3 BACnet MS/TP or Metasys N2: Wiring Field Port to RS-485 Network
Connect the BACnet MS/TP or Metasys N2 RS-485 network wires to the 3-pin RS-485
connector on ProtoCessor ED2 as shown below in
Figure 3.
o The RS-485 GND (Pin 3) is not typically connected
See Section 7 for information on connecting to BACnet/IP network.
If the ProtoCessor is the last device on the BACnet MS/TP or Metasys N2 trunk,
then the End-Of-Line Termination Switch needs to be enabled (Figure 4).
o The default setting from the factory is OFF (switch position = right side)
o To enable the EOL Termination, turn the EOL switch ON (switch position
= left side)
Figure 3: Connection from ProtoCessor to RS-485 Field Network
Figure 4: RS-485 BMS Network EOL Switch
5.4 LonWorks (FPC-ED4): Wiring Field Port to LonWorks Network
Connect ProtoCessor to the field network with the LonWorks terminal using approved
cable per the FT-10 installation guidelines. LonWorks has no polarity.
Figure 5: LonWorks Terminal Connector
BMS RS-485
Wiring
ProtoCessor
Pin #
Pin
Assignment
RS-485 +
Pin 1
RS-485 +
RS-485 -
Pin 2
RS-485 -
-
Pin 3
RS-485 GND
+
End-of-Line Switch
Condair LINKS 2587516_D_EN_2001 I 15
6 Use ProtoCessor Web Configurator to Setup the Gateway
6.1 Connect the PC to ProtoCessor via the Ethernet Port
Connect a CAT5 Ethernet cable (Straight through or Cross-Over) between the local PC
and ProtoCessor.
The Default IP Address of ProtoCessor is 192.168.1.24, Subnet Mask is 255.255.255.0.
If the PC and ProtoCessor are on different IP Networks, assign a static IP Address to the
PC on the 192.168.168.xxx network.
For Windows XP:
Go to > >
Right-click on Local Area Connection > Properties
Highlight >
For Windows 7:
Go to > >
> >
Right-click on Local Area Connection > Properties
Highlight >
For Windows XP and Windows 7, use the following IP Address:
Click twice.
16 | 2587516_D_EN_1909 Condair LINKS
6.2 Connecting to ProtoCessor Web Configurator
After setting a local PC on the same subnet as the ProtoCessor (Section 6.1), open a
web browser on the PC and enter the IP Address of the ProtoCessor; the default
address is 192.168.1.24.
NOTE: If the IP Address of the ProtoCessor has been changed by previous
configuration, the assigned IP Address must be gathered from the network
administrator.
6.3 Selecting Profiles for Device Connected to ProtoCessor
In the Web Configurator, the Active Profiles section is shown on the lower left side of the
screen.
The Active Profiles section lists the currently active device profiles, including previous
Web Configurator additions. This list will be empty for new installations, or after clearing
all configurations. (
Figure 6)
To add an active profile to support a device, click the ADD button under Active Profiles.
This will present a drop-down box underneath the Current Profile column that lists all the
available profiles. (
Figure 7)
For every device that is added, assign a unique Modbus Node-ID. This specification
must match the device’s network settings.
Condair LINKS 2587516_D_EN_2001 I 17
Figure 6: Web Configurator Showing no Active Profiles
Once the Profile for the device has been selected from the drop-down list, enter the
value of the device’s Modbus Node-ID which was assigned in Section 4.3.2.
18 | 2587516_D_EN_1909 Condair LINKS
Figure 7: Web Configurator Showing Available Profiles for Selection
Then press the “Submit” button to add the Profile as a device to be configured.
Completed additions will be listed under “Active Profiles” as shown in
Figure 8.
Condair LINKS 2587516_D_EN_2001 I 19
Figure 8: Web Configurator Showing Active Profile Additions
6.4 BACnet/IP Setting IP Address for Field Network
After setting a local PC to the same subnet as the ProtoCessor (Section 6.1), open a
web browser on the PC and enter the IP Address of the ProtoCessor; the default
address is 192.168.1.24.
The Web Configurator is displayed as the landing page. (Figure 9)
To access the Web GUI, click on the “Diagnostics & Debugging” button in the
bottom right side of the page.
20 | 2587516_D_EN_1909 Condair LINKS
Figure 9: Web Configurator Screen
From the Web GUI landing page, click on “Setup” to expand the navigation tree and
then select “Network Settings” to access the IP Settings menu. (Figure 10)
Figure 10: Changing IP Address via Web GUI
Modify the IP Address (N1 IP Address field) of the ProtoCessor Ethernet port.
If necessary, change the Netmask (N1 Netmask field).
Type in a new Subnet Mask.
If necessary, change the IP Gateway (Default Gateway field).
Type in a new IP Gateway.
NOTE: If the ProtoCessor is connected to a router, the IP Gateway of the ProtoCessor
should be set to the IP Address of that router.
Reset ProtoCessor.
Unplug Ethernet cable from PC and connect it to the network hub or router.
Record the IP Address assigned to the ProtoCessor for future reference.
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46

Condair 2587516-C LINKS ProtoCessor Installation guide

Type
Installation guide

The Condair 2587516-C LINKS ProtoCessor is a gateway device that allows Condair humidification and evaporative cooling units to interface with building automation systems using BACnet MS/TP, BACnet/IP, Metasys N2, and LonWorks protocols. It provides seamless integration and data exchange between the Condair unit and the building management system, enabling centralized control and monitoring of the humidification or cooling process.