Bradley S19-230T Installation guide

Category
Sanitary ware
Type
Installation guide
Installation
P.O. Box 309, Menomonee Falls, WI USA 53052-0309
PHONE 800.BRADLEY (800.272.3539) FAX 262.251.5817
bradleycorp.com
215-160T Rev. G; ECN 12-05-003C
© 2012 Bradley
Page 1 of 4 10/18/2012
S19-230T
Freestanding Eye/Face Wash
Table of Contents
Pre-Installation Information . . . . . . . . . . . . . . . . . . . . . . . . . 2
Installation Instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Assembly of Components . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Parts List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2
S19-230T Installation
10/18/2012 Bradley 215-160T Rev. G; ECN 12-05-003C
IMPORTANT
Read this installation manual completely to ensure proper installation, then file it with the
owner or maintenance department. Compliance and conformity to drain requirements and
other local codes and ordinances is the responsibility of the installer.
Separate parts from packaging and make sure all parts are accounted for before discarding
any packaging material. If any parts are missing, do not begin installation until you obtain the
missing parts.
Flush the water supply lines before beginning installation and after installation is complete.
Test the unit for leaks and adequate water flow. Main water supply to the eyewash should be
“ON” at all times. Provisions shall be made to prevent unauthorized shutoff.
The ANSI Z358.1 standard requires an uninterrupted supply of flushing fluid. Bradley plumbed
emergency fixtures require a minimum of 30 PSI (0.21 MPa) flowing pressure. Flushing fluid
should be tepid per ANSI Z358.1.
The inspection and testing results of this equipment should be recorded weekly to verify
proper operation. This equipment should be inspected annually to ensure compliance with
ANSI Z358.1.
Workers who may come in contact with potentially hazardous materials should be trained
regarding the placement and proper operation of emergency equipment per ANSI Z358.1.
For questions regarding the operation or installation of this product, visit www.bradleycorp.
com or call 1-800-BRADLEY.
Product warranties may also be found under “Product Information” on our web site at www.
bradleycorp.com.
Installation
THIS
SIDE
UP
Packing List
P.O. Box 309, Menomonee F
alls,
WI 53051
R
TEST THIS
UNIT EACH
WEEK
Test-operate valv
e(s) each week and sign
below.
Report an
y malfunctions immediatel
y.
Ventil(e) wöc
hentlich im
Testbetrieb prüfen,
bestätigt
durch Untersc
hrift. Jeglic
he Störung sofor
t melden.
Date
Datum
Date
Signed
Unterschrift
Signe
Date
Date
Date Signed
Signed
Signed
DIESES GERÄT 1ST
WÖC
HENTLICH ZU
PRÜFEN.
ESSAI HEBDOMA
DAIRE
Test le fonctionnement des v
alves chaque semaine et
signe en bas. S'il y à quelqu
e chose qui ne v
a pas fait
un rappor
t immédiatement.
P.O. BOX 309, MENOMONEE FALLS, WI 53052-0309 USA
TEL: 1-800-BRADLEY FAX: (262-251-5817)
http://www.bradleycorp.com
114-051
3
Installation S19-230T
Bradley 215-160T Rev. G; ECN 12-05-003C 10/18/2012
Installation Instructions
NOTICE! Avoid cleaners containing organic solvents,
alcohols, and hydrocarbons. Rinse with
water after cleaning.
Flush the water supply line before beginning
installation.
Supplies Required:
• Pipe sealant
• Piping to ½" NPT water supply inlet on unit
• Piping to 1¼" NPT drain outlet for eyewash
• Sign-mounting hardware
Step 1: Assemble eyewash components
1. Assemble eyewash components as shown on page 4.
• Apply pipe sealant (supplied by installer) to all
male-threaded pipe joints.
The top of the eyewash heads should be 33"–45"
(838mm–1143mm) from the floor.
Step 2: Connect water supply
1. Connect the water supply piping (supplied by
installer) to the ½" NPT inlet on the eyewash.
2. Connect the tailpiece to the 1¼" NPT drain outlet on
the eyewash.
3. Mount the safety sign to the wall using sign-
mounting hardware (supplied by installer).
4. Open the water supply lines. Test for leaks and
adequate water flow.
29½"
(749mm)
Suggested
Height To
Floor
36"
(914mm)
Suggested
Height To
Floor
15½" (394mm)
8¹⁄₈"
(206mm)
5¼"
(133mm)
7½"
(191mm)
Ø 10¾" (273mm)
Figure 1
4
S19-230T Installation
10/18/2012 Bradley 215-160T Rev. G; ECN 12-05-003C
Assembly of Components and Parts List
P.O. Box 309, Menomonee Falls, WI 53051
R
TEST THIS UNIT EACH WEEK
Test-operate valve(s) each week and sign below.
Report any malfunctions immediately.
Ventil(e) wöchentlich im Testbetrieb prüfen, bestätigt
durch Unterschrift. Jegliche Störung sofort melden.
Date
Datum
Date
Signed
Unterschrift
Signe
Date
Date
Date Signed
Signed
Signed
DIESES GERÄT 1ST WÖCHENTLICH ZU PRÜFEN.
ESSAI HEBDOMADAIRE
Test le fonctionnement des valves chaque semaine et
signe en bas. S'il y à quelque chose qui ne va pas fait
un rapport immédiatement.
P.O. BOX 309, MENOMONEE FALLS, WI 53052-0309 USA
TEL: 1-800-BRADLEY FAX: (262-251-5817)
http://www.bradleycorp.com
114-051
1.5
1.4
1.3
1.2
1.1
3
5
8
7
9
6
4
5.1
10
1
2.2
2.3
2.1
2
Items 1.1–1.5 come preassembled as Item 1.
Items 2.1–2.3 come preassembled as Item 2.
Prepack S45-122 includes Items 5, 5.1, 6, 7
Prepack S45-123 includes Items 5.1, 6, 7
Prepack S45-1789 includes Items 1.2, 1.4, 1.5
Item Part No. Qty Description
1 S90-094 1 Eyewash Bowl Assembly
1.1 111-039 1 Inlet Drain Fitting
1.2 124-028 1 Center Seal Gasket
1.3 187-053 1 Stainless Steel Eyewash Bowl
1.4 173-009 1 Cup Strainer
1.5 113-1150 1 Supply Pipe
2 S05-064D 1 EFW Sprayhead Assembly
2.1 S05-091P 1 EFW Yoke Assembly
2.2 S45-2453 1 Service Kit EFW - Black
Sprayheads
2.3 S53-063 2 Dust Cover
Item Part No. Qty Description
3 113-006LQ 1 Pipe 1/2" x 3-1/2"
4 169-025 1 Street Elbow 1/2"
5 S27-282 1 1/2" Ball Valve w/Nut
5.1 110-215 1 Nut Only
6 128-135 1 Plastic Eyewash Handle
7 142-002DA 1 Lockwasher
8 204-421 1 Emergency Inspection Tag
9 114-051 1 Safety Sign
10 269-167 1 Tailpiece
1¼" NPT
Drain Outlet
½" NPT
Supply Inlet
Figure 2
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4

Bradley S19-230T Installation guide

Category
Sanitary ware
Type
Installation guide

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI