Step
2
Installing the Side Discharge
Chute with Gate
Parts needed for this step:
1
Side discharge chute
1
Bolt, (5/16 x 7–1/2 inches)
1
Locknut, (5/16 inch)
1
Plastic spacer
1
Spring
Procedure
An unco v er ed discharge opening could
allo w the la wn mo w er to thr o w objects in
the operator’ s or bystander’ s dir ection and
r esult in serious injur y . Also, contact with
the blade could occur .
• Nev er operate the la wn mo w er unless
y ou install a co v er plate, a mulch plate, or
a g rass chute and catcher .
• Mak e sur e the g rass deflector is in the
do wn position.
Note: Ensure the g rass deflector is installed in
the lo w er holes in the mo w er dec k brac k ets .
1. Place the new spacer and spring onto g rass
deflector . Place one end of spring behind dec k
edg e .
Note: Mak e sure the end of the spring is
installed behind the dec k edg e before installing
the bolt as sho wn in .
2. Install bolt and n ut in the lo w er hole . Place the
end of the spring around the g rass deflector
( Figure 2 ).
3. Tighten the n ut until the end of the bolt is flush
with the end of the n ut. Do not o v er tighten.
Important: T he g rass deflector must be
a ble to lo w er do wn into position. Lift the
deflector up to test that it lo w er s into the
full do wn position.
Figure 2
1. Bolt
4. Spring
2. Spacer
5. Spring installed
3. Locknut 6. Grass Deector
Step
3
Installing the Handle to the
Height-of-Cut Panel
Parts needed for this step:
1
Handle assembly
1
Bolt, 3/8 x 3 inches
Procedure
1. R emo v e the top bolt that holds the
height-of-cut panel and pin with lanyard to the
mac hine ( Figure 3 ). Discard the bolt.
2. Loosen the bottom bolt that holds the
height-of-cut panel to the mac hine ( Figure 3 ).
3