AKC 121A Version 2.3x Menu operation RC.1M.A5.02 © Danfoss 05/2004 11
|
DefTime A Actual defrost cutin time or duration of the latest fi nished
6:02:02 defrosting period in section A
|
S5 °C B Defrost sensor temperature in section B
6:02:03
|
DefTime B Actual defrost cutin time or duration of the latest fi nished
6:02:04 defrosting period in section B
|
Defrost Start Settings of defrost start
Method
6:03
Man. Def Manual defrost is activated when ON
ON/OFF (changes automatically to OFF)
6:03:01
|
Def Sched Defrost will be started in accordance with the settings in defrost
ON/OFF tables 1, 2 and 3 (6:06, 6:07 and 6:08)
6:03:02
|
PumpDown A Delay time prior to start of gas defrost. Section A
0-60 The evaporator is drained of refrigerant through the
6:03:03 mian valve in the suction line. Set in minutes.
|
PumpDown B Delay time prior to start of gas defrost. Section B
0-60 The evaporator is drained of refrigerant through the
6:03:04 mian valve in the suction line. Set in minutes.
|
Defrost Stop Defi nition of how defrost stop is made, and how start-up after
Temp(1)/Time(2) defrost take place
6:04
Temp/TimeA 1: Temperature stop (time as security)
1 - 2 2: Stop on time
6:04:01 (section A)
|
MaxDefTimA Max. permissible defrost time in minutes. Section A.
5 - 180 (Security time on temperature stop)
6:04:02
|
DefStop °C A Temperature value of defrost stop. Section A
0 - 60
6:04:03
|
DrainDown A Delay time when defrost completed. Section A.
0 - 60 The evaporator is drained of condensed refrigerant through
6:04:04 the drain valve. Set in minutes.
|
Temp/TimeB 1: Temperature stop (time as security)
1 - 2 2: Stop on time
6:04:05 (section B)
|
MaxDefTimB Max. permissible defrost time in minutes. Section B.
5 - 180 (Security time on temperature stop)
6:04:06
|
DefStop°C B Temperature value of defrost stop. Section B
0 - 60
6:04:07
|
DrainDown B Delay time when defrost completed. Section B.
0-60 The evaporator is drained of condensed refrigerant through
6:04:08 the drain valve. Set in minutes.
|
Fan Del. m Time delay before fans are started (the time starts when the
0 - 60 defrost period for both sections has been completed)
6:04:09
|
CentralDef ON: Valve A and B are open during the defrost period.
ON-OFF OFF: Valve A and B are closed during the defrost period.
6:04:10 (Defrost sequence: Pumpdown, defrost, draindown)
|
ComDefStop Defi nition of how refrigeration is restarted
ON - OFF ON: Refrigeration must not be started until both sections have
6:04:11 completed their defrost
OFF: Refrigeration can be started individually in both sections