Abt POLYDRAIN PDX-Pin Lock Installation guide

Type
Installation guide
PolyDrain
Pre-Engineered Surface Drainage
PDX - Pin Lock
Installation Guide
P.O. Box 837 - 259 Murdock Road - Troutman, NC 28166
Tel (704) 528-9806 - Fax (704) 528-5478 - www.abtdrains.com
Toll free in the USA, Canada, and Mexico (800) 438-6057
COMPONENTS
DESCRIPTION
ITEM
PDX Channels
1
EPS Foam Insert2
Frame / Angle Rail3
1803 Cast Leg Bracket
4
Leg Clamp Screw
5
U - Leg6
Plain End Plate7
Inlet / Outlet End Plate8
End Rail9
Grate10
Removable Grate Retaining Pins11
Fixed Grate Retaining Pin12
Hexagon Head Screw
13
USEFUL OR REQUIRED TOOLS
COMPONENT IDENTIFICATION
3
12
13
2
1
6
4
5
11
9
7
8
10
Some products sold by ABT contain chemicals known to the State of California to cause cancer, birth defects or other reproductive harm. Products sold by ABT may
contain these chemicals in a smaller amount than Proposition 65's concern, or not at all, however, we have chosen to issue this warning on all of our products as an
act of caution and because our customers have the right to know.
WARNING: These products can expose you to chemicals such as nickel, lead, chromium, cobalt, styrene, methylene chloride, or silica, which are
known to the State of California to cause cancer and birth defects or other reproductive harm. For more information go to www.P65Warnings.ca.gov.
3. SUPPORT LUMBER ATTACH
1. EXCAVATION
T = per Structural Engineer
2. LEG ATTACH
DETAIL AB
SCALE 1/5.125
1. EXCAVATION
T = per Structural Engineer
4. DISCHARGE PLACE & ALIGN
Locate and Align Outlet Channel First. Start
at Deep End and Work to Shallow End.
5. CHANNEL PLACE & ALIGN
6. RAIL CONNECTION
H
AB
AM
AN
AP
AR
T
T T
T
2" Min
Anchor Slab
Above U-Leg
1/2" Min
Above Dirt
Finished Grade
Elevation
Support
Lumber
Tie Wire
Blank or Horiz. Outlet
End Plate (as Specified)
End Rail
Grade
Stake
Caulk or Adhesive
(as Specified)
Vertical Outlet Piping
(as Specified)
Set Top of Rails to
Finished Elevation
T T
T
1/2" Min
Above Dirt
2" Min
Anchor Slab
Above U-Leg
T
Align and Set
Channels to Grade.
Secure to Grade Stakes
Locate and Drive Grade
Stakes Where Needed
Caulk Channel Joints as Specified
Install Remaining Leg
Bracket Screws After
Positioning Channels
11. GRATE INSTALLATION
10. FLOOR CONCRETE
PLACEMENT
9. ENCAPSULATION CONCRETE
PLACEMENT AND CONSOLIDATION
7. PLACE ANCHOR SLAB
See Step 1 for Dimension
8. FINAL ALIGN & U-LEG TRIM
REV 030719.00
Use Vibrator to
Consolidate Concrete
Place Evenly Both Sides
Batter Boards as Required
Expansion Joint Materal
per Structural Engineer
Hook Grate Under Fixed Pins
Pivot Grates to Seat on Rail
Remove Foam After
Concrete Placement
Remove Suspension
Lumber as Required
Verify Trench Alignment
and Elevation
Cut Excess
Length from
U-Legs
Clean Debris from Hole and
Insert Clevis Pins to Retain Grates
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4