Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #1/54
INSTALLATION
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #2/54
Introduction...................................................................................................................................................................................4
Preparation before installation....................................................................................................................................................5
Vehicle partition..........................................................................................................................................................................................................6
Box preparation............................................................................................................................................................................7
Drilling.........................................................................................................................................................................................................................7
Roof top and cut mounting............................................................................................................................................................................................................8
Nosemount..................................................................................................................................................................................................................................11
Evaporator ..................................................................................................................................................................................................................................12
Harness and hoses hole.............................................................................................................................................................................................................14
Drain water hose hole.................................................................................................................................................................................................................15
Mushrooms...............................................................................................................................................................................................................16
Preparation .................................................................................................................................................................................................................................16
Set up..........................................................................................................................................................................................................................................18
Unit installation...........................................................................................................................................................................19
Evaporator installation...............................................................................................................................................................22
Hoses...........................................................................................................................................................................................23
Mounting recommendations......................................................................................................................................................................................24
Preparation...............................................................................................................................................................................................................25
Unit connection...........................................................................................................................................................................27
Refrigeration hoses...................................................................................................................................................................................................29
Evaporator connection...............................................................................................................................................................33
Refrigeration hoses...................................................................................................................................................................................................33
RAT sensor...............................................................................................................................................................................................................35
Drain pan..................................................................................................................................................................................................................36
INSTALLATION Table of content
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #3/54
Driver cab preparation ...............................................................................................................................................................37
Cab command harness fitting ...................................................................................................................................................38
Compressor connection ............................................................................................................................................................40
Injection thermostat ..................................................................................................................................................................................................42
Commissioning...........................................................................................................................................................................47
Leak checking...........................................................................................................................................................................................................47
Unit vacuum..............................................................................................................................................................................................................48
Refrigerant charge....................................................................................................................................................................................................49
Settings.....................................................................................................................................................................................................................51
CPR adjustment..........................................................................................................................................................................................................................51
TXV setting .................................................................................................................................................................................................................................53
INSTALLATION Table of content
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #4/54
This document gives the correct rules to follow in order to correctly install the VIENTO 200 / 300 / 350 units.
SAFETY FIRST
MANDATORY BEFORE ANY ELECTRICAL OPERATION:
DISCONNECT THE VEHICLE BATTERY:
- First remove the battery ground (-)
- then remove the positive battery (+)
PERSONAL PROTECTIVE EQUIPMENT
Always use adequate personal protective equipment before doing anything on this refrigerant unit.
BODYBUILDER RECOMMENDATIONS
Drain hose from the evaporator to the outside must have an angle to insure water to be drained out.
A descent of 10 cm minimum must be applied between evaporator drain water hoses and the hoses
inside the body (picture page 36).
Installation Introduction
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #5/54
1. Unpack the box contents in your warehouse.
KEEP THE DOCUMENT DELIVERED WITH THE
UNIT !
2. Unpack the box.
3. Check if the box content corresponds to the bill of material
on the packaging.
Condenser
Evaporator
Mounting kit
Cab command
In the event of any abnormality (missing, damaged part or
part number etc), fill in the form "Advance Warning, DOA,
Claim"
Installation Preparation before installation
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #6/54
Take care not to obstruct the air intakes on the
evaporator section and the ventilation ducts.
For any mobile partition installation, contact our
Technical Department or refer to the following chart:
MODELS Evaporator X Y
MXS 600
Viento 200
MXS 850
MXS 850
Viento 300
MXL 850
500 mm
MXS 1100
Viento 350
MXL 1100
1000 mm
150 mm
Installation Preparation before installation Vehicle partition
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #7/54
RECOMMENDATIONS
Before box preparation and unit installation commences, protect the vehicle roof and the refrigeration
box floor (cover, cardboard…).
There are 3 possibilities to fit the unit:
Roof top
Nosemount
Roof cut mounting
Installation Box preparation Drilling
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #8/54
1. Present the drilling template – not supplied - (refer to the
bodybuilder drawing)
2. Mark out the 4 fixing holes and the electrical harness and
hoses hole
3. Drill the fixing holes.
drill 10 mm
4. For roof top mounting: drill a hole 80 mm to pass hoses
and harnesses.
Installation Box preparation Drilling Roof top and cut mounting
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #9/54
5. Install the 4 silent blocks:
put silicone to waterproof on the bottom.
put silicone to waterproof on the 4 screws before to install
the host unit.
Installation Box preparation Drilling Roof top and cut mounting
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #10/54
6. To pass harnesses and hoses between condenser and
evaporator, drill the electrical harness and hoses hole.
Roof cut mounting : on vertical face of the vehicle
Roof top mounting: on the roof of the body (refer to
bodybuilder drawing)
Installation Box preparation Drilling Roof top and cut mounting
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #11/54
1. Present the drilling template – not supplied (refer to the
bodybuilder drawing)
2. Mark out fixing and electrical harness and hoses holes.
3. Drill the fixing holes
- drill 10 mm
4. Drill the electrical harness and hoses hole.
Installation Box preparation Drilling Nosemount
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #12/54
NOTE :
- The drilling depends on the evaporator you
have to install.
- Let a minimum space of 15 cm between the
box wall and the rear of the evaporator.
1. Mark the fixing holes for the evaporator (refer to the
bodybuilder drawing).
If needed, use the fixing material adapted to reinforcement
done by the bodybuilder.
If you don't have reinforcement, you will have to use
mushrooms (refer to section "Mushrooms" page 16).
Installation Box preparation Drilling Evaporator
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #13/54
If body reinforced, install the insert using the adapted tool
(manual or pneumatic).
Installation Box preparation Drilling Evaporator
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #14/54
2. Drill the electrical harness and hoses hole inside the box.
Installation Box preparation Drilling Harness and hoses hole
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #15/54
1. If body is not prepared to pass harnesses, refrigerant and
water drain hoses, drill the hose inside body.
RECOMMENDATIONS
A descent of MINIMUM 10 cm must be applied
between the drain water hoses pipe and the
hoses inside the body to help to drain water out.
Installation Box preparation Drilling Drain water hose hole
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #16/54
1. From box inside, drill 4 holes 5 mm in the roof through
and through (drill of minimum size 140mm)
2. Countersink with a drill 12,5 mm the 4 tapping drill holes
realized at the previous step.
RECOMMENDATIONS
Take care not to damage the 5 mm drilling of
the box external skin.
3. From box outside, countersink with a circular slitting saw
22 mm.
RECOMMENDATIONS
Take care not to damage the 12,5 mm drilling
of the box internal skin.
Installation Box preparation Mushrooms Preparation
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #17/54
4. Measure the roof thickness.
5. Adjust the mushroom length (L) to the roof thickness
minus the internal skin thickness (E –E')
L: mushroom length
E: roof thickness
E': internal skin thickness
Mushroom in place
1. mushroom
2. silicon gasket
3. skin of external box
4. polyurethane foam
5. skin of internal box
6. evaporator upper side
7. washer
8. screw M12
Installation Box preparation Mushrooms Preparation
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #18/54
1. Apply silicon on the internal side of the mushroom head.
2. Put mushrooms in holes previously realized in box roof.
3. With a mallet, slightly crush the silicon gasket.
4. Follow silent block installation. Take care to clean silent
block surface for a better sticking/water proof ness.
Installation Box preparation Mushrooms Set up
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #19/54
1. Remove the grill:
remove the 4 fixing screws
remove the grill
Installation Unit installation
Operation & Service Manual
Carrier Transicold Europe 31/03/07 Viento - Installation/Rev- #20/54
2. Remove the top cover:
remove the 3 rear fixing screws
push the cover and remove it.
RECOMMENDATIONS
Do not try to un-tight the 2 front screws of top
cover. They are part of the caplocks system.
Installation Unit installation
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46
  • Page 47 47
  • Page 48 48
  • Page 49 49
  • Page 50 50
  • Page 51 51
  • Page 52 52
  • Page 53 53
  • Page 54 54

Carrier 300 Operation & Service Manual

Type
Operation & Service Manual

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI