PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
2
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
Section 1: Introduction
These instructions will guide you through the process of replacing an
existing Eaton Visor, CVL, or SML transient voltage surge suppres-
sor (TVSS) unit with an SPD Series surge protective device (SPD).
These instructions are specific to the replacement of those devices
when integrated within an Eaton PRL3a panelboard. Because SPD’s
vary in application (bus connected versus interfaced through a circuit
breaker, 3-phase versus single-phase, etc), the pictures utilized in
this document may not be reflective of your specific application.
Please read all instructions carefully as you perform each step. If
you require any support throughout the replacement process, please
contact the Eaton Technical Resource Center at 1-800-809-2772,
Option 4, Option 2.
1.1 PRL3a Panelboard Preparation
DANGER
HAZARDOUS VOLTAGES WILL CAUSE SEVERE INJURY OR DEATH. TURN
OFF ALL POWER SUPPLYING THE PANELBOARD BEFORE REMOVING THE
TVSS UNIT AND INSTALLING THE REPLACEMENT SPD. USE A METER TO
ENSURE THAT NO VOLTAGE IS PRESENT IN THE PANELBOARD BEFORE
MOVING FORWARD WITH THESE INSTRUCTIONS.
1. Remove the panelboard trim and hardware. Keep the trim and
hardware for re-installation.
2. Identify the TVSS unit that is to be removed and replaced. If it is
a Visor, move to Section 2.1. If it is a CVL/SML, move to
Section 2.2.
Section 2: Visor and CVL/SML Disassembly
Instructions
2.1 Visor Disassembly Instructions
ote:N Refer to Figure 1 while performing all Visor disassembly steps.
1. Remove Item 11 (dead front cover - attached by four screws).
This will also remove Item 10 (insulating barrier) attached to
Item 11 via plastic rivets.
Figure 1. Visor Disassembly Reference Drawing.
2. Remove panelboard dead front cover assembly and hardware.
Keep dead front cover assembly and hardware for re-installation.
3. If the Visor unit is interfaced via a circuit breaker, move to Step 5.
Otherwise, if the Visor unit is mounted directly to the electrical
bus, refer to Figure 2. Remove the Item 13 screws (three places
for 3-phase units, two places for single-phase units) that attach
the bus connectors to the vertical chassis bus and move to
Step 6.
Figure 2. Visor Unit Mounted to the Electrical Bus.
3
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
4. Visors interfaced to the system via a circuit breaker will have
either two wires (single-phase units) or three wires (3-phase
units) connected between the unit and a circuit breaker.
Disconnect these wires from the circuit breaker.
5. Refer to Figure 1 and remove the Item 12 screw (two places).
These screws affix the neutral wire (white/gray) and ground wire
(green) to the Visor. Note that Item 12 (and the corresponding
neutral and ground wire connections) may be located on either
side of the Visor. Disconnect the neutral wire (if present) from
the panelboard neutral assembly.
6. Remove the Item 14 screw (two places) and remove the Visor
assembly from the panelboard. Remove each Item 5 bracket by
removing the Item 15 screw (two places). Discard all hardware
and miscellaneous parts removed during the process.
ote:N For top incoming applications, there is a bus support located directly
above the area from which the Visor was removed. For bottom incoming
applications, there is a bus support located directly below the area from
which the Visor was removed. This bus support will be used as a reference
point when locating the new SPD assembly (Figures 4 and 8).
2.2 CVL/SML Disassembly Instructions
ote:N Refer to Figure 3 while performing all CVL/SML disassembly steps.
1. Remove Item 1 (dead front cover - attached by four screws).
Figure 3. CVL/SML Disassembly Reference Drawing.
2. Remove the panelboard dead front cover assembly and hardware.
Keep the dead front cover assembly and hardware for re-installa-
tion.
3. CVL/SML units will have either two wires (single-phase units) or
three wires (3-phase units) connected between the unit and a
circuit breaker. Disconnect these wires from the circuit breaker.
Also, disconnect the neutral wire (white/gray) from the panel-
board neutral assembly and ground wire (green) from the panel-
board ground assembly.
4. Remove the Item 6 screw (four places) and remove the CVL/SML
unit from the panelboard assembly.
ote:N For top incoming applications, there is a bus support located directly
above the area from which the CVL/SML was removed. For bottom incom-
ing applications, there is a bus support located directly below the area from
which the CVL/SML was removed. This bus support will be used as a refer-
ence point when locating the new SPD assembly (Figures 4 and 8).
Section 3: SPD Series Unit Installation
Instructions
ote:N If SPD is to be interfaced via a circuit breaker, skip to Step 10 in this
section. If SPD is to be direct bus mounted, go to Step 1 in this section.
1. Refer to Figure 4 for orientation of the Item 9 bracket. In order
to properly locate the Item 9 bracket onto chassis rail, select the
appropriate Figure 5 illustration based upon top or bottom incom-
ing direction of the panelboard main conductors. Locate the Item
9 bracket onto chassis rail per appropriate illustration “Bracket to
Rail” dimensions, noting the bus support as zero reference point.
Attach each Item 9 bracket using two of the Item 15 screws
Figure 4. SPD Installation Reference Drawing.
 
 
 
 
DRAFTER MODEL FILENAME
ENGINEER
MFG. ENG.
NEXT ASSY
TOOL REF.
REFERENCE
SHOP/GENERAL ORDER NO.
ENGINEERING CHANGE NOTICE NO.
UNLESS SPECIFIED TOLERANCES PER
TH IS D O CUM EN T, INC LUD ING TH E D RAW ING AN D INF ORM A TIO N
CO NT AIN E D TH ER EON , IS CON FIDE NT IAL AN D IS THE EX CLU SIVE
PRO PER TY O F EA TO N CO RPO RA TION, AND IS ME RE LY ON L OA N
AND SUB JECT T O RE CALL BY EAT ON COR POR AT ION A T AN Y TI ME .
BY TA KING PO SSE SSIO N OF TH IS DOCU MEN T, TH E R EC IPIE NT AC K NO WL ED GE S AN D AG R EES THA T
TH IS D O CUM EN T C AN N OT BE U S ED IN AN Y M ANN ER A DVE RSE TO T HE IN TE RES TS OF EAT ON, A ND
TH AT NO PO RT ION OF TH IS D OCU M EN T MA Y BE C OPI ED O R O TH ER WI SE R EPR OD UC ED WIT HO UT
TH E PR IOR WRIT TEN C ONSE NT OF E AT ON C ORP OR ATIO N. IN TH E CA SE OF CO NFL ICTIN G
CO NT RA CTUA L PR OV ISIO NS, THIS NO TICE SHA LL G OVE RN THE ST ATU S O F TH IS DO C UM ENT .
EATON CORPORATION - CONFIDENTIAL AND PROPRIETARY
DATE
DATE
DATE
MODEL REV
SCALE PROJECT NO.
PRODUCT
DWG NO.
PARTS LIST REV
TITLE BLOCK REV - 4
TITLE
SHEET OF
THIRD ANGLE
PROJECTION
C
1 3
DSF
RBH
5/14/2009
5/14/2009
42C3241G03.iam
1
_
NTS
3376
42C3241
142C3241
PRL3A
ASSY, SPD, BUS CONN.
DIMENSIONS TO BE INTERPRETED
ASME Y14.5M - 1994
IN ACCORDANCE WITH
REVISION HISTORY
1
.000
1.000 (3)
(DEVICE TO CONN.)
2.063 (2)
(BRACKET TO RAIL)
2.750 (3)
(CONN. TO BUS)
3.438 (2)
(BRACKET TO RAIL)
5.500(4X)
16
REFERENCE TOP OF PANEL
6
14
10
15
9
1 SPD TO BE INSTALLED DIRECTLY ADJACENT TO MAIN
INCOMING DEVICE OR CHASSIS MOUNTED NEUTRAL
(IF PRESENT).
4
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
Figure 5. SPD Direct Bus Mounted Dimensions.
2. Refer to Figure 6 for proper orientation of bus connectors (Items
1, 2, and 3). Locate and install bus connectors per the appropri-
ate Figure 5 illustration ”Connector to Bus” dimensions. For
3-phase applications, all three bus connectors (Items 1, 2, and 3)
and the Item 13 screws will be required, one per phase – A, B,
and C. For single-phase applications, only two bus connectors
(Items 1 and 3) and the Item 13 screws will be required, one per
phase – A and C. Ensure the bus connection screws (Item 13)
are properly torqued1
. Do not over tighten them.
ote:N To avoid alignment issues, ensure that the bus connector vertical edge
remains parallel with the vertical edge of the chassis bus during the torquing
process.
.000
6.188
TOP INCOMING
BOTTOM INCOMING
11
11
REFERENCE TOP OF PANEL
REFERENCE TOP OF PANEL
2.750 (2)
(BRACKET TO RAIL)
4.125 (2)
(BRACKET TO RAIL)
3.438 (3)
(CONNECTOR TO BUS)
.000
2.750 (2)
(BRACKET TO RAIL)
3.438 (3)
(CONNECTOR TO BUS)
4.125 (2)
(BRACKET TO RAIL)
6.188
(BUS SUPPORT)
(BUS SUPPORT)
Figure 6. Bus Connector Orientation.
3 Refer to Figure 4 for Item 6 bracket orientation. Connect the
Item 6 bracket to each side of the SPD with two of the Item 14
screws.
4. For 3-phase applications, remove the B-phase bus adapter as
shown in Figure 7. Locate SPD such that the bus connectors
(Items 1, 2, and 3) align with the bus mounting holes in the top
of the SPD per Figure 6. Ensure that the Item 9 bracket and the
Item 6 bracket are properly aligned per Figure 4.
Figure 7. B-Phase Bus Adapter.
 
 
 
 
DWG NO
MODEL REV
SHEET OF
TITLE
ALL REV. NOTES
LISTED ON SHT. 1
REVMODEL FILENAME T.BLK
REV-4
C
42C3241
2 3 1
ASSY, SPD, BUS CONN.
PRL3A
42C3241G03.iam 1
2 "B" PHASE BUS ADAPTER (PROVIDED
BY SPD SUPPLIER) MUST BE REMOVED
BY FACTORY FOR ALL APPLICATIONS.
3 "B" PHASE ADAPTER (OMITTED BY SPD
SUPPLIER) IS NOT REQUIRED FOR SINGLE
PHASE APPLICATIONS.
12
1
3
13
2
1 REF. SPD (200KA
MAX SURGE RATING)
REAR VIEW
REF. "B" PHASE
BUS ADAPTER
 
 
 
 
DWG NO
MODEL REV
SHEET OF
TITLE
ALL REV. NOTES
LISTED ON SHT. 1
REVMODEL FILENAME T.BLK
REV-4
C
42C3241
2 3 1
ASSY, SPD, BUS CONN.
PRL3A
42C3241G03.iam 1
2 "B" PHASE BUS ADAPTER (PROVIDED
BY SPD SUPPLIER) MUST BE REMOVED
BY FACTORY FOR ALL APPLICATIONS.
3 "B" PHASE ADAPTER (OMITTED BY SPD
SUPPLIER) IS NOT REQUIRED FOR SINGLE
PHASE APPLICATIONS.
12
1
3
13
2
1 REF. SPD (200KA
MAX SURGE RATING)
REAR VIEW
REF. "B" PHASE
BUS ADAPTER
5
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
5. Start the Item 12 screws per Figure 6, but do not tighten at this
time. Start Item 10 screws per Figure 4, but do not tighten at
this time.
6. Once the fit is confirmed, first tighten and torque3 the Item 12
screws per Figure 6. Then tighten the Item 10 screws per
Figure 4. Move to step 11.
7. For SPD units interfaced via a circuit breaker, refer to Figure 4
for orientation of the Item 9 bracket. In order to properly locate
the Item 9 bracket onto chassis rail, select appropriate Figure 8
illustration based upon top or bottom incoming direction of panel-
board main conductors. Locate the Item 9 bracket onto chassis
rail per appropriate illustration “Bracket to Rail” dimensions, not-
ing the bus support as zero reference point. Attach each Item 9
bracket using two of the Item 15 screw.
Figure 8. SPD Interfaced Via Circuit Breaker Dimensions.
.000
6.188
TOP INCOMING
BOTTOM INCOMING
3
3
REFERENCE TOP OF PANEL
REFERENCE TOP OF PANEL
2.750 (2)
(BRACKET TO RAIL)
4.125 (2)
(BRACKET TO RAIL)
.000
2.750 (2)
(BRACKET TO RAIL)
4.125 (2)
(BRACKET TO RAIL)
6.188
(BUS SUPPORT)
(BUS SUPPORT)
8. Refer to Figure 4 for the Item 6 bracket orientation. Connect the
Item 6 bracket to each side of the SPD with two of the Item 14
screws.
9. Refer to Figure 4 for proper alignment of the Item 6 and Item 9
brackets. Connect and tighten the brackets using the Item 10
screws (one each side).
10. For SPD units interfaced via a circuit breaker, the SPD phase
wires must be connected to the circuit breaker disconnect. Cut
any extra length from each SPD phase wire, strip the end, termi-
nate the wire into appropriate circuit breaker lug, and torque2.
ote:N SPD phase wires are labeled appropriately according to the intended
application (3-phase [Phase A, Phase B, and Phase C] versus single-phase
[Phase A and Phase C]). The phase wires of the SPD MUST be terminated
into the corresponding pole of the circuit breaker disconnect.
11. Locate the neutral assembly in the panelboard. Refer to Figure 9
and install the neutral wire (Item 5 - gray) to the side of the SPD
closest to the neutral bar using the Item 10 screw and torque3.
ote:N The word “Neutral’ is denoted on the SPD’s enclosure. Be sure that
only one neutral connection is made to the SPD. Cut any extra wire length,
strip the end, terminate the wire, and torque1 at the panelboard neutral
assembly.
Figure 9. Neutral and Ground Wires.
12. Locate the ground assembly in the panelboard. Refer to
Figure 9 and install the ground wire (Item 4 - green) to the side
of the SPD closest to the ground bar using the Item 10 screw
and torque3.
ote:N The word “Ground’ is denoted on the SPD’s enclosure. Be sure that
only one ground connection is made to the SPD. Cut any extra wire length,
strip the end, terminate the wire, and torque1 at the panelboard ground
assembly.
13. Reinstall the panelboard dead front cover assembly.
14. Refer to Figure 10. Install Item 11 SPD dead front cover with four
of the Item 10 screws. Reference Figure 5 (direct bus mounted
applications) or Figure 8 (interfaced via a circuit breaker applica-
tions) for orientation and location of dead front cover as needed.
Install the Item 7 and 8 labels on the dead front cover.
 
 
 
 
DWG NO
MODEL REV
SHEET OF
TITLE
ALL REV. NOTES
LISTED ON SHT. 1
REVMODEL FILENAME T.BLK
REV-4
C
42C3241
3 3 1
ASSY, SPD, BUS CONN.
PRL3A
42C3241G03.iam 1
TOP INCOMING
BOTTOM INCOMING
REFERENCE TOP OF PANEL
REFERENCE TOP OF PANEL
5
10
4
10
10
11
7
8
6
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
1
Figure 10. Label Locations.
15. For Visor Replacement Only: Depending on the size of the Visor
unit that was replaced, blank dead front cover(s) are required
to fill in any open space and must be installed directly above
or below the SPD dead front cover using four of the Item 10
screws.
16. Install any other items that were removed during the disassem-
bly process and reapply power to the panelboard. Ensure that
all indicator lights on the SPD Series are green and the audible
alarm is not active. If there is a problem, check all connections
and verify that proper phase voltages are present. If all connec-
tions and voltages are verified and problems still exist, please
contact the Eaton Technical Resource Center at 800-809-2772,
Option 4, Option 2.
Footnotes:
1 – Refer to the panelboard torque label (located on panelboard dead
front cover) for torque requirements.
2 – Refer to the circuit breaker marking for torque requirements.
3 – Refer to the SPD marking for torque requirements.
 
 
 
 
DWG NO
MODEL REV
SHEET OF
TITLE
ALL REV. NOTES
LISTED ON SHT. 1
REVMODEL FILENAME T.BLK
REV-4
C
42C3241
3 3 1
ASSY, SPD, BUS CONN.
PRL3A
42C3241G03.iam 1
TOP INCOMING
BOTTOM INCOMING
REFERENCE TOP OF PANEL
REFERENCE TOP OF PANEL
5
10
4
10
10
11
7
8
7
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
EATON CORPORATION www.eaton.com
Notes:
Instruction Manual IM01005034E
Effective March 2010
PRL3a Panelboard TVSS Unit Removal
and SPD Installation Instructions
Eaton Corporation
Electrical Group
1000 Cherrington Parkway
Moon Township, PA 15108
United States
877-ETN-CARE (877-386-2273)
Eaton.com
© 2010 Eaton Corporation
All Rights Reserved
Printed in USA
Publication No. IM01005034E / TBG000315
March 2010
PowerChain Management is a registered
trademark of Eaton Corporation.
All other trademarks are property of their
respective owners.
This Instruction Manual is published solely for information purposes
and should not be considered all-inclusive. If further information is
required, you should consult an authorized Eaton sales representa-
tive.
The sale of the product shown in this literature is subject to the
terms and conditions outlined in appropriate Eaton selling policies
or other contractual agreement between the parties. This literature
is not intended to and does not enlarge or add to any such contract.
The sole source governing the rights and remedies of any purchaser
of this equipment is the contract between the purchaser and Eaton.
NO WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING
WARRANTIES OF FITNESS FOR A PARTICULAR PURPOSE OR
MERCHANTABILITY, OR WARRANTIES ARISING FROM COURSE
OF DEALING OR USAGE OF TRADE, ARE MADE REGARDING
THE INFORMATION, RECOMMENDATIONS, AND DESCRIPTIONS
CONTAINED HEREIN. In no event will Eaton be responsible to the
purchaser or user in contract, in tort (including negligence), strict
liability or otherwise for any special, indirect, incidental or conse-
quential damage or loss whatsoever, including but not limited to
damage or loss of use of equipment, plant or power system, cost
of capital, loss of power, additional expenses in the use of existing
power facilities, or claims against the purchaser or user by its cus-
tomers resulting from the use of the information, recommendations
and description contained herein.
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8

Eaton PRL3a panelboard TVSS unit removal and SPD Installation guide

Type
Installation guide

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI