MG500-EU-EN v1.0 7/13
7
Operation
Poweringthemeter
PresstheONbuttontoturntheuniton.Pressthe OFFbuttontoturntheunitoff.Ifthemeter
doesnotswitchONpleasecheckthatfresh‘C’1.5Valkalinebatteriesareinstalledinthebattery
compartmentlocatedatthebottomoftheinstrument.
InsulationResistanceTestingProcedure
Warning:Thecircuitundertestmustbecompletelyde‐energizedandisolatedbeforemaking
testconnections.
1. After turning the unit on, make sure that the Replace Battery messageis not displayed.If
theReplaceBatterymessageisdisplayedreplacethebatteriesbeforeproceeding.
2. The test voltage defaults to
2500V on power up. Select the desired test voltage using the
Voltage Adjust buttons (±500V) that step through the available test voltages in 500V
incrementsorbypressingoneofthepresettestvoltagebuttons(10kV,5kV,2.5kV,1Kv).
3. ThedisplayshowstheConnectLeadspromptalongwiththeselected
testvoltagevalue.
ConnecttheGreentestleadtotheGreentestsocketonthemeterandthentotheGround
sideoftheinsulatorundertest.
Connectthe Red lead to the Red testsocketon the meter and the Blue guard cable to the
blue socket on the
meter.Connect the service end of the Red cable to other side of the
insulatorundertest.
IfaLeakageGuardleadisrequiretocollect surfaceleakage,connectthe separateBluetest
lead into the Blue guard lead from the Red test lead which is plugged into the Blue test
socketonthemeterandthencliptheserviceendofthecabletothesurfaceoftheinsulator
undertest.
4. MomentarilyPresstheTESTSTART/STOPbuttontostarttesting.
ForDARorPItesting–refertotheseparatetestprocedurebelow.
5. The Insulation resistance test will
complete in 10 seconds.The test voltage percentage
steadily counts down to zero during the test as can be seen on the display. The resistance
testresultvaluewillappearonthedisplaywhenthetesthascompleted.
6. TheHOLDiconwillappearinplaceofthebargraphwhenthe
testiscompleteandafterthe
voltagehasbeendischarged.
WARNING:DONOTREMOVETHETESTLEADSBEFORETHEHOLDDISPLAYAPPEARS.
7. Themeterautomaticallydischargesthesystemattheendofthetest.
8. Totakeanothertest,presstheTESTSTART/STOPbutton,theConnectLeadspromptshould
appearonthedisplay;theinstrumentisnowreadytorunanewtest.
9. Theinstrumentautomaticallypowersdownafter5minutesofinactivity.