Anova CIRCLEPVCING, CIRCLEBRING, CIRCLEBRS2IG Installation guide

  • Hello! I've reviewed the installation instructions for the ANOVA tandem bike racks, models CIRCLEBRS2IG, CIRCLEPVCING, and CIRCLEBRING. The document provides detailed steps for inground mounting, including concrete preparation and proper digging techniques. I'm ready to answer your questions about the installation process.
  • What is the minimum psi rating for the concrete footing or slab?
    How long should the concrete be cured before installing the bike rack?
    How deep should the holes or slots be for the posts?
anovafurnishings.com
888.535.5005 tel
Installation Instructions
CIRCLEBRS2IG
TOOLS NEEDED:
Step-by-Step Installation Sequence
Examine the footing or slab for damage or defects. The footing or slab should be reinforced concrete rated at a
3,000 psi minimum and be cured for at least 28 days prior to the installation of the bike rack.
CAUTION: Oversized holes and holes drilled too deep in the concrete will make it dicult to set the anchor.
Optional: Digging Iron
Shovel
Level
Tamper
CIRCLEPVCING
CIRCLEBRING
Tandem Bike Racks, Inground Mount
Installation Instructions
Step-by-Step Installation Sequence
06/11/2019 Copyright 2019 ANOV Manufactured in the U.S.
Note: Please contact Customer Care at 1-866-797-1761 when ordering replacement parts.
1.
5. Check the concrete manufacturer's specications to see how long the
concrete needs to dry before attempting the use of the installation.
2.
3.
4.
Using a shovel place approximately six inches of gravel into the hole then
tamp it down with a tamper. Repeat this step one more time so there is a total
of 6" of gravel.
NOTE: When digging the hole it is recommended that it has a slight angle and
increases in size the farther down it goes. This helps prevent frost upheaval.
Mix the concrete in a wheel barrel to the manufacturer's specications.
NOTE: We recommend seeking out a local contractor for the best option on
how to pour the concrete. Image 4 shows an example of how the concrete
could be poured.
Pour the concrete based on your local recommendation.
Dig out the holes or a slot for the posts using a shovel and a digging iron.
The holes or slot should be 15.25 " in depth (Double check spec sheet, found
online) and should be a minimum of 5" in diameter. The depth of the hole
should be below the frost line to prevent shiing.
1 2
CAUTION: Call your local utility companies to mark where there are any
cables or pipelines before digging any holes.
Frost Line
4
Frost Line
NOTE: Make sure that concrete is poured below frost line
CIRCLEBRS2IG
CIRCLEPVCING
CIRCLEBRING
Tandem Bike Racks, Inground Mount
/