APOLLO
®
IRON GATE VALVE IOM GUIDE Page 5 of 7
ES1493 IOM CI Gate Valve 1418 S. Pearl Street Pageland SC USA 29728
Product Marking
All APOLLO
Gate Valves are equipped with a nameplate attached under handwheel nut
(Figure 1). This plate provides the model number, part number, size, max pressure
rating, and date of manufacture.
FIGURE 1. APOLLO
IRON GATE VALVE NAMEPLATE EXAMPLE
INSTALLATION
APOLLO
gate valves are designed for use between the faces of ANSI 125 and 250 pound
flat flanges. Proper piping alignment prior to the installation should be. Raised faced
flanges are not recommended.
Gate valves are normally installed in horizontal pipe with vertical stem.
They can also be installed other than vertical, but this may require special construction
depending on valve size, service condition and medium. For a correct operation, Conbraco
recommends that the valve stem shall be oriented inclined above horizontal, with vertical
being the preferred orientation. Different positions may cause poor valve operation,
and/or a quick deterioration of the valve. The valve should be installed with the wedge in
the closed position, to ensure that the seat ring in the wedge is not damaged during
installation.
Installation Instructions
Step 1. Check to make sure that the pipe flange and valve sealing faces are clean and
free from any debris (pipe scale, welding slag, etc.).
Step 2. Check the valve nameplate to ensure that the pressure and valve materials are
correct for the application.
WARNING! – APOLLO
®
gate valves should never be installed where service
conditions could exceed the valve ratings. Failure to heed warning may
result in personal injury or property damage.
Step 3. Place the valve between the two flanges of the pipe and put the seal gasket
between the valve flange and the pipe flange; make sure that it is correctly
positioned.
Step 4. Assemble the valve to the pipe using properly sized bolts for application. See
Tables 4 and 5 below. Progressively tighten to the torque value recommended by
the seal gasket provider. See Figure 2 for recommended method.
After the valve installation on the line and before the line pressurization, the following
activities must be performed:
- the packing bolts must be verified for tightness, DO NOT OVERTIGHTEN.
- the torque of the body-bonnet bolts must be verified for tightness
- the valve must be fully stroke operated