2
General Installation Guidelines
nVent.com | 13
For three-phase supply voltages, the total area is
generally divided into multiples of three equal
subsections, allowing for installation of a single
cable in each subsection. Heating cables of the
same length and wattage, installed in each
subsection, will provide a balanced electrical load.
It may not be possible to use a balanced electrical
load for small areas, therefore one or two heating
cables, single-phase connected, must be used.
Ensure that the cold lead length is sufficient to reach
the junction box. The standard cold lead length for
pre-engineered (SUB) cables is 15 ft (4.6 m), but
heating cables may have been custom designed
using longer cold leads. Plan the location of all
junction boxes and supply points so that they are
located within reach of the heating cable cold leads.
Typical junction box installation details are shown in
Section4.
The location of all joints in the ramp or slab
should be recorded on the layout drawing. Plan the
general layout of the heating cables to avoid cross-
ing control and expansion joints. In some cases, the
placement of these joints may have to be relocated
in order to divide the area equally since the quantity
of heating cables supplied may have been based
on equal subsection areas. If necessary, control
joints can be crossed using one of the two methods
shown in Figure 9. Crossing expansion joints should
be avoided, but if this is not possible, use the
method shown in Figure 10.
Types of Joints
Control joints are intended to control where the slab
will crack. Their exact location is determined by the
concrete installers before the concrete is poured.
Because of the reinforcement in the base slab, there
is rarely a shearing action caused by differential
vertical movement between the concrete on either
side of the crack. As a precautionary measure, how-
ever, either of the two methods of crossing control
joints shown in Figure 9 should be used. Minimize
the number of times the joint is crossed as shown in
Figure 9. When installing cables using the two-pour