PREPARATION (Fig. 1)
1. Shut off power at the circuit breaker and remove the old
fixture including the mounting hardware.
2. Carefully unpack your new fixture and lay out all the parts
on a clear area. Take care not to lose any small parts
necessary for installation.
3. Remove finial (H) from the fixture. Secure the scrolled
end of arm (F) to the top of the fixture with finial (E). Next,
secure the straight end of arm (F) to backplate (P) using
knurled knobs (G) washers (I) and hex nuts (J).
4. Replace finial (H), previously removed.
5. Mount the reinforcement plate (K) to the junction box and
secure with screws (M) through the holes in the middle of
the plate. For additional stability on large fixtures, use the
4 screws and anchors (L & N) provided. The side of the
reinforcement plate marked “GND” must face out. (Fig. 1)
CONNECTING THE WIRES (Fig. 2)
6. Connect the electrical wire as shown in figure 2, making
sure that all wire connectors are secured. If your outlet
has a ground wire (green or bare copper), connect the
fixture ground wire to it. Otherwise, connect the fixture
ground wire directly to the reinforcement plate using the
green screw provided. After wires are connected, tuck
them carefully inside the outlet box.
COMPLETING THE INSTALLATION
7. Align the fixture to the mounting screws on the
reinforcement plate (K) and secure fixture with knurled
knobs (O). (Fig.1)
8. To prevent moisture from entering the outlet box and
causing a short, use clear caulking (i.e. Indoor/Outdoor
Silicone Sealant) to outline the outside of fixture back
plate where it meets the wall leaving a space at bottom to
allow moisture a means to escape. (Fig. 3)
9. Remove the bottom finial (A), lock washer (B) tube (R),
and metal leaf (Q). Carefully slide out the bottom
assembly (C). Remove any plastic bag material from the
socket cluster. Proceed to install the B10.5 2*60W bulbs
(not included) in accordance with the fixture’s
specifications. (DO NOT EXCEED THE MAXIMUM
WATTAGE RATING). (NE PAS DEPASSER LA
PUISSANCE NOMINALE MAXIMALE!).
10. Replace the bottom assembly (C) and secure with the
metal leaf (Q), tube (R), lock washer (B) and Finial (A).
Your installation is now complete. Return power to the
junction box and test the fixture.
Note: Illustration (Fig. 1) on this manual is for
installation purposes only. It may or may not be
identical to the fixture purchased.