Gibraltar Building Products RJL15 Operating instructions

Type
Operating instructions

This manual is also suitable for

1. Shingle up to the roof penetration. 2. Slide flashing over the vent pipe and secure with roofing nails.
The lead pipe flashing should be at least 1.5" taller than the
exposed vent pipe.
3. Roll the top of the lead pipe flashing into the vent pipe to create
a long lasting water resistant seal that is finished in appearance.
4. Continue shingling above the vent pipe. Apply roofing mastic to
the top of the flange before installing upper side shingles.
1 2
3 4
LEAD PIPE FLASHING
INSTALLATION GUIDELINES
These basic installation guidelines are for use with typical or standard applications. It is always recommended to seek advice from a licensed
professional, and to check with your local building inspector or building permit office for approvals and possible variations that may apply.
CAUTION!
Working above grade is inherently dangerous, be sure that proper fall protection measures are in place.
When working with power tools and sheet metal, gloves and eye protection are absolutely required.
  • Page 1 1

Gibraltar Building Products RJL15 Operating instructions

Type
Operating instructions
This manual is also suitable for

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI