3-2 Installation
2-Mb/s Remote Peripheral Equipment Appendix 1 to 553-2741-200
Chart 3-1
QCA146 RPE cabinet installation
Step Procedure
1Transport the cabinet as close as possible to its final location.
2Transport the remaining equipment to a convenient safe dry
location.
3Unpack and inspect the cabinet.
4Remove cabinet from pallet and place on floor.
5If casters are provided, tilt the cabinet and replace the levellers
on the cabinet with four casters.
6 Adjust floor levellers or casters when in final location. When
casters are provided, ensure that they are locked in position
when the cabinet is in its final location.
7Remove the front and rear cabinet covers.
8If required, install additional shelves as described in Chart 2-2.
9Install but do not connect a 6 AWG wire between the approved
building ground and the ground lug identified by a ground symbol
(Figure 2-1) at the rear of the cabinet.
10 At the building ground end of the wire, connect the 6 AWG wire to
the approved building using at least two fastening devices and
insulate the connections with electrical tape. Install a DO NOT
DISCONNECT tag on the connection.
11 With an ohm meter, measure the resistance between the ground
pin on the ac power cord plug and the ground lug at the rear of
the cabinet (Figure 2-1). The resistance should be 0 Ω. If
greater than 0 Ω, check power cord connections at rear of
cabinet.
12 Ensure that the AC BRKR or the AC POWER breaker on the
faceplate of the -48 V rectifier in the cabinet is set to OFF.
13 Connect the power line cord to the commercial ac power supply.