3M Cold Shrink QS-III Splice Kit 5513A-2/0-AL, 15 kV, Standard, 1/case Operating instructions

Category
Signal cables
Type
Operating instructions
3M
Cold Shrink Splice Kit QS-III
5513A
for UniShield
®
, Wire Shielded, Longitudinally Corrugated (LC),
and Tape Shielded (Ribbon Shielded) Cable or Transitions to
Concentric Neutral (CN)/Jacketed Concentric Neutral (JCN) Cables
Instructions
IEEE Std. 404
15 kV Class
150 kV BIL
CAUTION
Working around energized systems may cause serious injury or death. Installation should
be performed by personnel familiar with good safety practice in handling electrical
equipment. De-energize and ground all electrical systems before installing product.
Kit Selection Table
Kit Number Cable Insulation O.D. Range Conductor Size Range
5513A
0.64" to 1.01"
(16,3 to 25,7 mm)
2–4/0 AWG*
(35–95 mm
2
)
* Splices (including size transitions) can be made to smaller or larger conductors (but larger conductors may require special neutral
handling), provided both cables are within the Insulation O.D. Range and the connector meets the dimensional requirements
shownbelow.
Connector Dimensional Requirements
Minimum Inches (mm) Maximum Inches (mm)
Outside Diameter 0.40" (10,2 mm) 1.10" (28 mm)
Length
Aluminum (Al/Cu) Compression
4.50" (114 mm)
Length
Copper Compression and 3M
Shearbolt Connector
QCI 2-250
5.00" (127 mm)
March2011
78-8125-9950-0-C 3
2 78-8125-9950-0-C
1.0 Kit Contents
a. 3M
ColdShrinkSpliceBody5415A(1ea.)
b. ColdShrinkJacketingTube(1ea.)
c. ColdShrinkAdapterTube(2ea.)
d. ShieldingSleeve,1/3NeutralMaximum(1ea.)
e. GroundStrap(1ea.)
f. ConstantForceSpringGroundConnectors(5ea.)
g. RedCompoundTubes(non-siliconegrease)(2ea.)
h. Scotch
®
MasticSealingStrips2230,6"length(6ea.)
i. Scotch
®
RubberMasticTape2228Rolls,2"x36"(2ea.)
j. CopperFoilTape,1/2"x10"(2ea.)
k. 3M
CableCleaningPadsCC-3(1ea.)
l. CablePreparationTemplate(1ea.)
m.InstructionBooklet(1ea.)
Note: Donotuseknivestoopenplasticbags.
Note: Connectornotshown,butifincluded,itisindicatedonthepackaginglabel.
Note: Kitcontains0,1or2ofitem“C,”ColdShrinkAdapterTube,asneededperconductorsize.
78-8125-9950-0-C 3
2.0 Prepare Cables
2.1 For Tape, LC, Wire Shield or UniShield
®
Cable:
2.1.1 Preparecablesaccordingtostandardprocedures.Refertotemplateprovidedorillustrationbelowfor
properdimensions.(Figure1).
6 3/4"
(171 mm)
13 1/4"
(337 mm)
3 1/2"
(89 mm)
Cable Jacket
Metallic
Shield
Semi-con
Insulation
6 3/4"
(171 mm)
13 1/4"
(337 mm)
3 1/2"
(89 mm)
Cable Jacket
Wire Shield
Semi-con
Insulation
6 3/4"
(171 mm)
13 1/4"
(337 mm)
Insulation
Shield Wires
3 1/2"
(89 mm)
Tape & LC Shielded Cables
Wire Shielded Cable
UniShield
®
Cable
Figure1
Note: CablesmustbewithintheinsulationO.D.rangeofthesplicekitandtheconnectormustmeetthe
dimensionalrequirementsshownonthefrontpage.
4 78-8125-9950-0-C
2.1.2 For Tape shield and LC shield: Secureendofeachmetallicshieldwithacoppertapestrip.
For Wire shield and UniShield
®
:Carefullybendshieldwiresbackovercablejacketsandtemporarily
securewithvinyltape.(Figure2).
Tape & LC Shielded Cables
Wire Shielded Cable
UniShield
®
Cable
Foil Tape
Semi-con
Semi-con
Metallic Shield
Cable Jacket
Semi-con
Cable Jacket
Vinyl Tape Shield Wires
Cable Jacket
Vinyl Tape Shield Wires
Vinyl TapeNeutral Wires
Figure2
Gotosection3.0“ParkSpliceComponents.”ifnottransitionsplicingtoJCNorCNcable.
2.2 For Transitions to Jacketed Concentric Neutral (JCN) Cable:
2.2.1 Preparecablesaccordingtostandardprocedures.Refertotemplateprovidedorillustrationbelowfor
properdimensions(Figure3).
6 3/4"
(171 mm)
13 1/4"
(337 mm)
Neutral Wires
Semi-con
Insulation
6 3/4"
(171 mm)
13 1/4"
(337 mm)
Neutral Wires
Semi-con
Insulation
Concentric Neutral (CN)
Jacketed Concentric Neutral (JCN)
Figure3
Note: CablesmustbewithintheinsulationO.D.rangeofthesplicekitandtheconnectormustmeetthe
dimensionalrequirementsshownonthefrontpage.
78-8125-9950-0-C 5
2.2.2 Carefullybendneutralwiresbackoveredgeofcablejacketandtemporarilysecurewithvinyltape.
Tape & LC Shielded Cables
Wire Shielded Cable
UniShield
®
Cable
Foil Tape
Semi-con
Semi-con
Metallic Shield
Cable Jacket
Semi-con
Cable Jacket
Vinyl Tape Shield Wires
Cable Jacket
Vinyl Tape Shield Wires
Vinyl TapeNeutral Wires
Figure4
Gotosection3.0“ParkSpliceComponents.”
2.3 For Transitions to Concentric Neutral (CN) Cable:
2.3.1 Preparecablesaccordingtostandardprocedures.Refertotemplateprovidedorillustrationbelowfor
properdimensions(Figure5).Do not cut neutral wires on CN cables.
6 3/4"
(171 mm)
13 1/4"
(337 mm)
Neutral Wires
Semi-con
Insulation
6 3/4"
(171 mm)
13 1/4"
(337 mm)
Neutral Wires
Semi-con
Insulation
Concentric Neutral (CN)
Jacketed Concentric Neutral (JCN)
Figure5
Note: CablesmustbewithintheinsulationO.D.rangeofthesplicekitandtheconnectormustmeetthe
dimensionalrequirementsshownonthefrontpage.
2.3.2 Cleancablesemi-conasshown(Figure6).
Binder Wire
Folded Back Neutral Wires
Semi-Con
Clean
Figure6
6 78-8125-9950-0-C
2.3.3 Placeastripofmasticaroundcablesemi-connexttoneutralbinder.Foldneutralsintomasticandplace
anotherbinderwireontheothersideofthemastic(Figure7).
Binder Wire
Mastic Strip
Binder Wire
Figure7
2.3.4 Wraptwoadditionalstripsofmasticoverthefirstoneandcoverwithtwohalflappedlayersofvinyl
tape(Figure8).
2 additional mastic strips covered with 2 layers vinyl tape
Figure8
2.3.5 Foldneutralsovermasticsealandtemporarilysecureendswithvinyltape(Figure9).
Secure folded-back neutral wires with vinyl tape
Figure9
78-8125-9950-0-C 7
3.0 Park Splice Components
3.1 Cleanorcovercablejacketifnecessary,forcoldshrinkparkingposition.Slidejacketingtubeontoonecable
end.Slidesplicebodyontooppositecable,loosecoreendfirst.Forsizetransitions,parkspliceonsmallercable
(Figure10).
Note: Jacketingisnotoptional.Coldshrinkjacketingtubemustbeinstalled.
Loose Core End
Splice Body
Jacketing Tube
Figure10
Note: Ifspaceislimited,thejacketingtubeandsplicebodycanbeputonthecablestackedinsideeachother.
3.2 Positiontheexpandedshieldsleeveontoonecable.Theshieldsleeveisdesignedtocarryupto1/3neutral
current(Figure11).
Expanded Shield Sleeve
Figure11
8 78-8125-9950-0-C
4.0 Install Connector
Note: Ifusingacrimp-typeconnector,gotostep4.3.
4.1 If using a 3M
Shearbolt Connector QCI 2-250, refertotheinstructionsincludedwiththeconnectorfor
insulationcut-backdimension.Insulationremovallengthshallnotexceed21/2"(64mm)fromconductorend
(Figure12).
Refer to connector instructions for dimensions
Figure12
4.2 Install3M
ShearboltConnectorQCI2-250accordingtotheinstructionsincludedwiththeconnector
(Figure13).
Connector
Shearbolt
Figure13
Gotosection5.0“InstallSplice.”
78-8125-9950-0-C 9
4.3 If using a crimp type connector, removecableinsulationfor1/2connectorlengthplusanallowance*for
increasesinconnectorlengthduetocrimping.Insulationremovallengthshallnotexceed21/2"(64mm)from
conductorend.Do not install connector now (Figure14).
*Note: Thisassumesthattheinstallerhasdeterminedtheincreasedlengthofanaluminumconnectorcrimped
withaspecifictoolanddie.
Aluminum (Al/Cu) Crimp Connector Growth Chart
Conductor Size Typical growth allowance (per end)
2–3/0 AWG 1/8" (3 mm)
4/0 AWG 1/4" (6 mm)
Note: 1)Copperconnectorsdonotrequirealengthchangeallowance.
2)Maximumaluminumconnectorcrimpedlengthallowedis5.00"(127mm).
One-half connector length
+ growth allowance*
Figure14
4.4 For 2 through 1/0 AWG copper connectors, 2 and 1 AWG aluminum connectors, or connectors with an
O.D. between 0.40–0.55" (10,2–14,0 mm): SlidethecoldshrinkadaptertubewiththeWHITE CORE onto
theinsulationwiththeloosecoreribbonendgoingonfirst,awayfromthecableend.
For 2/0 through 4/0 AWG copper connectors or connectors with an O.D. between 0.50–0.64"
(12,7–16,3 mm): SlidethecoldshrinkadaptertubewiththeRED CORE ontotheinsulationwiththeloose
coreribbonendgoingonfirst,awayfromthecableend(Figure15).
Cold Shrink Adapter Tube
Loose Core End
Figure15
10 78-8125-9950-0-C
4.5 Installconnector.Seetable(oncover)forproperconnectordimensions.(Forstandard3M
Connectors,refer
totableattheendofthisinstructionforcrimpinginformation).Removeanyexcessoxidationinhibitorfrom
connectorendsifaluminumconnectorisused.Filesharpconnectorflashingifnecessary,takingcaretoremove
allmetalfilingsfromsplicearea(Figure16).
Connector
Figure16
5.0 Install Splice
5.1 Applyatapemarkertosemi-coninsulationshieldoncablewhichdoesnotcontainsplice.Measure81/2"
(216mm)fromcenterofconnector(Figure17).
Tape Marker
Semi-con
8 1/2"
(216 mm)
Figure17
5.2 If using cold shrink adapter tube:Positionadaptertubeovertheconnector.Shrinkadapternearcenterof
connectorbypullingandunwindingtheloosecoreendinacounter-clockwisedirection(Figure18).
Cold shrink adapter tube
Figure18
78-8125-9950-0-C 11
5.3 Cleancablesusingstandardpractice:
a.Donotallowsolventorabrasivetocontactthecablesemi-conductiveinsulationshield.
b.Donotreducecableinsulationdiameterbelow0.64"(16,3mm)specifiedforthesplice.
c.Theinsulationsurfacemustberound,smoothandfreeofcuts/voids.Sandingmaybenecessary,finish
sandingshouldbedonewitha300gritorhigherelectricalgradeabrasive.
d.Makecertainthatthecableinsulationissmooth,cleananddrybeforecontinuing.
5.4 Applyredcompoundoncableinsulations,makingcertaintofillinedgeofcablesemi-con.Do not use
silicone grease(Figure19).
Apply Red
Compound
Apply Red
Compound
Fill semi-con step Fill semi-con step
Figure19
5.5 Positionthesplicebodyoverconnectorarea,aligningendofthesplicebody(notthecore)atthecenter
ofthetapemarker.Slowlystarttoremovethesplicecorebypullingandunwindingtheloosecoreend
counterclockwise,allowingonly¼"(6mm)ofthesplicetoshrinkontothetapemarker.Carefullyslidethe
splicebodyoffthetapemarkerbypullingandtwistinguntiltheentiretapemarkerisexposed.Continue
removingthecoretocompletethesplicebodyinstallation(Figure20).
Note: Thesplicebodyendsmustoverlapontothesemi-conofeachcablebyatleast1/2"(13mm).
Note: Donotpushthesplicebodytowardthetapemarkerasthismaycausetheendtorollunder.Iftheend
doesrollunder,DONOTusesharp-edgedtoolstopullitoutasthiscouldcutanddamagethesplice.
Unwind Counter-clockwise
Align splice body with tape marker
Figure20
12 78-8125-9950-0-C
6.0 Connect Shield Sleeve
6.1 Centertheexpandedshieldsleeveoversplicebody.Hand-tightensleevefromsplicecenteroutwardin
bothdirections(Figure21).
Shield Sleeve
Hand-tighten sleeve from splice center outward
Figure21
6.2 For Tape Shielded and LC Shielded Cables:
6.2.1 Securesleevetocablemetallicshieldnexttoeachcablejacketusingtwowrapsofvinyltape
(Figure22).
Cable Jacket End
Vinyl Tape Shield Sleeve
Figure22
6.2.2 Bendendsofsleevebackovervinyltapeandsecurewithconstantforcespringsat11/2"(38mm)
and21/2"(64mm)fromjacketend.Trimoffexcesssleeve1/2"(13mm)fromsprings,ifnecessary
(Figure23).
Constant Force Springs
Folded over shield sleeve
Trim end of sleeve if necessary
1 1/2"
(38 mm)
2 1/2"
(64 mm)
Figure23
78-8125-9950-0-C 13
6.2.3 Wraptwolayersofstretchedvinyltapeoversprings(Figure24).
Vinyl Tape
Figure24
6.3 For Wire Shielded Cable:
6.3.1 Carefullyremovevinyltapefromdrainwires.Securesleevetocablesemi-conductinglayernexttoeach
cablejacketusingtwowrapsofvinyltape(Figure25).
Vinyl Tape
Drain Wires
Figure25
6.3.2 Bendendsofsleevebackovervinyltape.Positiondrainwiresovertheshieldsleeveandsecurewith
constantforcespringsat11/2"(38mm)and21/2"(64mm)fromjacketend.Trimoffexcesssleeve
1/2"(13mm)fromsprings,ifnecessary(Figure26).
Constant Force Springs
Drain wires over shield sleeve
Trim end of sleeve if necessary
1 1/2"
(38 mm)
2 1/2"
(64 mm)
Figure26
14 78-8125-9950-0-C
6.3.3 Wraptwolayersofstretchedvinyltapeoversprings(Figure27).
Vinyl Tape
Figure27
6.4 For UniShield
®
Cable:
6.4.1 Carefullyremovevinyltapefromdrainwires.Securesleevetocablesemi-conjacketnexttobent-back
shielddrainwiresusingtwowrapsofvinyltape(Figure28).
Vinyl Tape
Drain Wires
Figure28
6.4.2 Bendendsofsleevebackovervinyltape.Carefullypositiondrainwiresovertheshieldsleeve.Secure
withconstantforcesprings11/2"(38mm)and21/2"(64mm)ontodrainwires.Trimoffexcesssleeve
1/2"(13mm)fromsprings,ifnecessary(Figure29).
Constant Force Springs
Drain wires over shield sleeve
Trim end of sleeve if necessary
1 1/2"
(38 mm)
2 1/2"
(64 mm)
Figure29
78-8125-9950-0-C 15
6.4.3 Wraptwolayersofstretchedvinyltapeoversprings(Figure30).
Vinyl Tape
Figure30
6.5 For CN and JCN Cable:
6.5.1 Connectshieldsleevetometallic(LC,etc.)shieldfirst.Removevinyltapefromneutralwiresandroute
neutralwiresupwardnexttoendofcablejacket(orCNbinder)(Figure31).
Neutral Wires
Figure31
6.5.2 Securesleevetocablesemi-connexttoneutralwiresusingtwowrapsofvinyltape.Covertheendofthe
splicebody(asshownbelow)withtwohalf-lappedlayersofrubberorvinyltape(Figure32).
Neutral Wires Shield Sleeve (twisted)
Vinyl Tape
Rubber or Vinyl Tape
Figure32
16 78-8125-9950-0-C
6.5.3 Placea3-4"pieceofcablejacketovertherubberorvinyltapeandcablesemi-conasshownbelow.
Securewithvinyltape(Figure33).
Cable Jacket Piece
Figure33
6.5.4 Keepingtheconnectorascloseaspossibletothecable,connectshieldsleeveandneutralstogether,
usingasuitablecompressionconnector.(“INLINE,”“C,”or“H”type).Crimpconnectorfollowingthe
connectormanufacturersrecommendation.Trimexcessneutralwiresandsleeveextendingbeyondthe
connector(Figure34).
Compression connector
Figure34
6.5.5 Foldconnectorovershieldsleeve,ensuringthattheconnectorisoverthecablejacketpiece,andsecure
withvinyltape(Figure35).
Vinyl Tape
Figure35
78-8125-9950-0-C 17
7.0 Grounding (Optional)
Note: Usetheseinstructionsifcircuitgroundingisrequiredatthislocation.
7.1 Onmetallicshielded(non-neutral)cable,wrapthegroundstraparoundtheshieldsleeve(betweenthecable
jacketandconstantforcespring)withthetailstowardsthecablejacket(Figure36).
Ground Strap
Figure36
7.2 Securegroundstraptotheshieldsleeveusingaconstantforcespring(Figure37).
Constant Force Spring
Figure37
7.3 Wraptwolayersofstretchedvinyltapeoverspring(Figure38).
Vinyl Tape
Figure38
18 78-8125-9950-0-C
7.4 Placeonemasticsealingstriponthecablejacketunderthesolderblocksofthegroundstrap(Figure39).
Solder Block
Mastic Strip
Figure39
7.5 Placeotherstripoverthesolderblocks.Pressthemasticstripsaroundthesolderblockandtothecablejacket.
Iftailsoverlapatthesolderblocks,placeapieceofmasticbetweenthem(Figure40).
Second Mastic Strip
Figure40
8.0 Install Jacket
Note: Jacketingisnotoptional.
8.1 Applyonerollofslightlystretchedrubbermastictapearoundeachjacketend(tackysidetowardcable).Stretch
andtearofftheendoftherubbermasticasshownbelow.Ifgroundstrapwasapplied,tapeovermasticsealing
strips.ForCNcable,covermasticsealnexttobinder(Figure41).
Stretch and tear off last 1–2"
(25–50 mm) of rubber mastic
Rubber Mastic Rubber Mastic
Figure41
78-8125-9950-0-C 19
8.2 Begintoinstallthecoldshrinktubebycompletelycoveringtherubbermastic,andslowlypullingand
unwindingtheinnercorecounterclockwisetowardthesplicebody.Theoutercoreshouldremainrelatively
stationarywhileunwindingtheinnercore.Iftheoutercorebeginstomovetowardsthefirstmasticseal,gently
pulltheoutercoreandjacketingtubetowardsthesecondmasticsealandcontinueunwindingtheinnercore
(Figure42).
Unwind Counter-clockwise
Figure42
8.3 Continuetoinstallthecoldshrinktubeovertherubbermasticontheothercablebyslowlypullingand
unwindingtheoutercorecounterclockwise.Thisportionofthecoldshrinktubeinstallsdifferentlythantypical
coldshrinkproductsinthatasthetubeshrinks,theendrollsunder.Thetubemayneedaslightpushtogetover
thesecondmasticseal(Figure43).
Unwind Counter-clockwise
Figure43
Note: Inapplicationswherethespliceisregularlyexposedtohighlevelsofultra-violetradiation
(i.e.directsunlight),wraptwohalf-lappedlayersofScotch
®
Super33+
VinylElectricalTapeorScotch
®
VinylElectricalTapeSuper88overthere-jacketingtubes.
Note: Connectoptionalgrounding.
Crimping Tool - Die Sets (number of crimps/end)
Square D Co.
3M™ Conductor Burndy Corporation Thomas & Betts Corp. Anderson Div. Kearney
Connector Size
No. (AWG or MD6 MY29 Y34A Y35, Y39 Y1000** TBM 5 TBM 8 TBM 15 VC6-3** Type O
kcmil) Y45*, Y46* VC6-FT**
CI-22 (Al/Cu) 2 sol. BG (3) --- U243 (1) U25ART (1) --- --- Olive(2) 50(1) (1) 5/8-1 (3)
10003 (Cu) 2 str. W162(2) 2 AWG(1) A2CR(1) U2CRT(2) --- Brown(1) Brown(1) 33(1) (1) ---
20003 (Al/Cu) 2 str. W163(3) 2AWG (1) A2CAB(1) UTCABT(1) (1) Pink(2) Pink(2) 42H(2) (1) 1/2 (3)
CI-21 (Al/Cu) 2 str. BG (3) --- U243 (1) U25ART(1) --- --- Olive(2) 50(1) (1) 5/8-1 (3)
10004 (Cu) 1 --- 1 AWG(1) A1CR(1) U1CRT(2) --- Green(1) Green(1) 37(1) (1) ---
20004 (Al/Cu) 1 W163(3) 1AWG(1) A1CAB(1) U1CART(1) (1) Gold(2) Gold(2) 45(1) (1) 1/2 (3)
CI-21 (Al/Cu) 1 BG (3) --- U243 (1) U25ART(1) --- --- Olive(2) 50(1) (1) 5/8-1 (3)
10005 (Cu) 1/0 W163(2) 1/0(1) A25R(1) U25RT(1) --- Pink(2) Pink(2) 42(2) (1) ---
20005 (Al/Cu) 1/0 W241(2) 1/0(1) A25AR(1) U25ART(1) (1) Tan(2) Tan(2) 50(1) (1) 5/8-1 (3)
CI-1/0 (Al/Cu) 1/0 BG (3) --- U243 (1) U25ART(1) --- --- Olive(2) 50(1) (1) 5/8-1 (3)
10006 (Cu) 2/0 W241(2) 2/0(1) A26R(1) U26RT(2) --- Black(2) Black(2) 45(1) (1) ---
20006 (Al/Cu) 2/0 BG(4) 2/0(1) A26AR(2) U26ART(2) (1) Olive(2) Olive(2) 54H(2) (2) 5/8-1 (3)
11006 (Cu) 2/0 W241(3) 2/0(2) A26R(2) U26RT(2) --- Black(3) Black(3) 45(2) (2) ---
CI-2/0 (Al/Cu) 2/0 W249(3) --- --- U28ART(2) --- --- Blue(4) 76(2) (2) 840 (4)
10007 (Cu) 3/0 W243(2) 3/0(1) A27R(1) U27RT(2) --- Orange(2) Orange(2) 50(1) (1) ---
20007 (Al/Cu) 3/0 W166(4) 3/0(1) --- U27ART(2) (1) Ruby(2) Ruby(2) 60(2) (2) 737 (3)
11007 (Cu) 3/0 W243(3) 3/0(2) A27R(2) U27RT(3) --- Orange(3) Orange(3) 50(2) (2) ---
CI-3/0 (Al/Cu) 3/0 W249(3) --- --- U28ART(2) --- --- Blue(4) 76(2) (2) 840 (4)
10008 (Cu) 4/0 BG(3) 4/0(1) A28R(2) U28RT(2) --- Purple(2) Purple(2) 54H(2) (2) ---
20008 (Al/Cu) 4/0 W660(4) 4/0(2) A26AR(2) U28ART(2) (1) --- White(4) 66(4) (2) 840 (4)
11008 (Cu) 4/0 BG(4) 4/0(2) A28R(3) U28RT(3) --- Purple(3) Purple(3) 54H(3) (3) ---
CI-4/0 (Al/Cu) 4/0 W249(3) --- --- U28ART(2) --- --- Blue(4) 76(2) (2) 840 (4)
*Y45 and Y46 accept all Y35 dies (“U Series”). For Y45, use PT6515 adapter. For Y46, use PUADP adapter.
**Anderson VC6-3, VC6-FT and Burndy Y1000 require no die set.
3M and Super 33+ are trademarks of 3M Company. Scotch is a registered trademark of 3M Company.
UniShield is a registered trademark of General Cable Technologies Corporation.
Important Notice
All statements, technical information, and recommendations related to 3M’s products are based on information believed to be reliable, but the accuracy or
completeness is not guaranteed.
Before using this product, you must evaluate it and determine if it is suitable for your intended application.
You assume
all risks and liability associated with such use.
Any statements related to the product which are not contained in 3M’s current publications, or any contrary
statements contained on your purchase order shall have no force or effect unless expressly agreed upon, in writing, by an authorized officer of 3M.
Warranty; Limited Remedy; Limited Liability.
This product will be free from defects in material and manufacture for a period of one (1) year from the time of purchase.
3M MAKES NO OTHER
WARRANTIES INCLUDING, BUT NOT LIMITED TO, ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.
If this product is defective within the warranty period stated above, your exclusive remedy shall be, at 3M’s option, to replace or repair the 3M product or
refund the purchase price of the 3M product.
Except where prohibited by law, 3M will not be liable for any indirect, special, incidental or con-
sequential loss or damage arising from this 3M product, regardless of the legal theory asserted.
3
Electrical Markets Division
6801 River Place Blvd.
Austin, TX 78726-9000
800-245-3573
Fax 800-245-0329
www.3M.com/electrical
Please Recycle. Printed in USA.
© 3M 2011. All Rights Reserved.
78-8125-9950-0-C
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20

3M Cold Shrink QS-III Splice Kit 5513A-2/0-AL, 15 kV, Standard, 1/case Operating instructions

Category
Signal cables
Type
Operating instructions

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI