ASSEMBLY INSTRUCTION OF GAS HEATER TRANSFORMER
1. Take off side panels of unit.
2. Fasten transformer T3 and terminal block XG in places marked with arrows.
3. Connect wiring of transformers T3 with components according to schematic diagram of unit.
CAUTION! If transformer is to be installed in machine supplied with 3x230V, fuse F1 rated
at 2,5A (see schematic diagram of unit) should be replaced with fuse 4A included in set.
LIST OF ELEMENTS
Pos. Element Description from diagram Number
1 Transformer with wiring T3 0455 639 001
2 Wiring 0349 302 158
3 Terminal block XG 0349 302 127
4 Screw (1 piece) S6PSGC M6x12
5 Screw (1piece) FST 2,9x16
6 Washer Ø3,2