POWERTRAK
COOL SIDE DELAY SWITCH INSTALLATION
HIRED-HAND, INC. 1733 Co Rd 68 Bremen, AL 35033 Phone 1-800-642-0123 Fax 205-287-2000
Cool Side Delay Switch Installation 4801-0120 Rev 1/15 Page 1
Tools Required: Drill with 3/16" bit
3/4" Wrench
1/4" Allen Wrench
Crimping Tool
To Set Switch Position:
Manually raise or lower curtains to desired height.
Place template over side even with center of load block
(as shown below at left), then follow the instructions for
installation.
When installation is complete, manually raise and lower
curtain past the switch slowly to be sure that the switch
operates without binding.
Attach switch and bracket using
the two nuts and bolts provided.
Replace existing setscrews
with new longer setscrews.
Place bracket on new setscrews, and
secure with nuts. Be sure the bracket
can slide from side to side. Attach one end of tensioning
spring to bracket as shown,
and the other end around the
grease fitting.
Note: Nuts should not be
completely tightened so
that the bracket may slide
back and forth freely.
Lay template over side of
PowerTrak at desired height.
Mark and Drill holes. Notice!
Switch must be installed on machine
operating the curtain you want to open first.
(Typically the south side.)
Purpose of Equipment:
To create a Cool Side Delay by stopping the north side
machine from operating until the south side machine
hits a rocker switch set at a certain height.
Warning!
Disconnect all power sources to PowerTrak before
attempting to install the Auxiliary Switch. Electric Shock
may result.
* Note: For Serial Numbers 20825 and higher(DOM 3/4/96), you must add two 1/2 inch washers to
the setscrews between bracket and load nut.
Cumberland. 1004 E. Illinois St. Assumption, IL 62510 Phone 1-217-226-4421 Fax 1-217-226-4420