MGF GSSW-02.1A is a two sided excavation support system designed for simple assembly and robust support in weak, problematic, or saturated ground. It features telescopic struts for adjusting to required lengths, 4-leg chains for easy handling, and secure connections with pins and r-clips. The MGF GSSW-02.1A enables safe excavation and shoring, providing a stable environment for construction and maintenance work.

MGF GSSW-02.1A is a two sided excavation support system designed for simple assembly and robust support in weak, problematic, or saturated ground. It features telescopic struts for adjusting to required lengths, 4-leg chains for easy handling, and secure connections with pins and r-clips. The MGF GSSW-02.1A enables safe excavation and shoring, providing a stable environment for construction and maintenance work.

Trench Boxes
GSSW/02.1A 4
06.03.2012
1. If used in very weak, problematic or
saturated ground always ensure a site specific
temporary works design is provided.
2. Always inspect lifting points prior to every
lifting operation and ensure all personnel are
well clear of operation.
3. Flying of the box above the base of the
excavation is not recommended.
4. Only access the box via a suitable secured
ladder placed within the box. Never enter via
the ends/faces of an unsupported excavation.
5. Always ensure all pins and retaining clips
are correctly fitted prior to use.
6. If box becomes stuck in the ground only
use designated extraction chains to release
each corner at a time. N.B. Extraction loads of
up to 50t can be generated.
7. Do not allow personnel to enter the box
whilst excavator is moving box.
8. Always ensure the box is evenly supported
by the ground on opposite faces to avoid
boxes becoming unstable.
9. Always work from a position of safety.
Avoid working above on an unsupported edge,
an unprotected edge or under a suspended
load.
10. Very heavy equipment to be installed by
competent groundwork contractors only.
11. Take care to avoid accidently striking
struts or using struts for lifting/moving the box.
12. Avoid standing on steel panels especially
when wet.
13. Do not assemble panels on top of other
panels or on sloping ground as they can
potentially slide when attaching the top panel.
14. Warning! Assembled boxes do not have
fully rigid connections and panels can tilt or
rotate during assembly or handling. Do not
rest ladders against panels.
15. Keep hands and fingers away from pinch
points when making connections.
16. Prior to permitting entry always ensure;
panels are installed plumb, square and level to
each other. All components are fitted and show
no signs of damage or distress and a safe
means of access/egress is provided from
within the box.
www.mgf.co.uk
www.mgf.co.uk
MGF Trench Boxes are simple assembly, robust,
two sided excavation support systems, install with
an excavator utilising the dig and push or excavate
and lower in place techniques. This guide will
detail a dig and push installation sequence.
Assembly of a box commences by lowering the
first panel flat onto timber skids, using the
provided MGF 4-leg chains.
Adjust the telescopic struts to the required length
by sleeving the inner within the outer and
securing them together using a pin and r-clip.
Keep hands/fingers away from connection and
pinch points.
Lower the struts into the panel pockets and secure
using pins and r-clips.
Pins should be inserted from outside the panel.
Lower the second panel onto the struts using an
MGF 4 leg chain. Carefully align the panel
pockets with the strut ends. Lock into position
with pins and r-clips. Once secure, release the
4-leg chain.
Lift the assembled box into a vertical position by
using the MGF chain.
Installation normally commences by excavating to
a maximum of 1m below ground level (if site
conditions permit).
Lower the box into the excavation using an MGF 4
leg chain. Release the chains. An operative on
even ground should remove chains only if the box
upstand is 1m above ground level.
Carefully dig and push each panel down using the
excavator bucket on the corners of each panel.
Push the box downwards in no more than 300mm
increments. Excavating ahead of the panel cutting
edges as required. Take care to avoid damage.
Once the base unit is at a sufficient depth a top
unit can be added.
Lower the top onto base and connect together to
form a single box ensuring all 4 top to base
connection points are fully secured.
The pins are inserted from the outside and r-clips
are fitted from the inside.
Always ensure a safe secure means of access is
provided prior to entry.
Dig and push the assembled box to the required
depth.
If an additional top is required repeat steps J to K.
On reaching the final depth secure the box by
backfilling against the panels and if required
batter back the open ends of the excavation.
End safe panels or trench sheets can be used to
secure the ends.
Shoring Safety Products can now be installed.
Subject to a final inspection the excavation is now
safe to enter.
Note: Make sure the panels are installed plumb,
square and level to each other.
Extraction of the boxes normally commences by
backfilling around the installed structure. Any
shoring safety products attached to the boxes
should now be removed.
Attach an extraction chain in turn, to each top
extraction point. Slowly apply an upward force to
break any adhesion that may have occurred
between the panel and the ground.
Progressively backfill the excavation as the box is
removed.
Once the top unit is clear of the ground connect an
MGF 4 leg chain and remove the 4 pins at the
connection points, before lifting the top clear of the
excavation.
Repeat the extraction process for the base unit
until the base can be removed. Backfill and
compact the ground.
Standard Duty
4-Leg Chain
Extraction Chain
Only use chains supplied by MGF
for handling, installing and
removing MGF box systems.
See MGF channel
for installation guidance:
https://www.youtube.com/user/MGFLtd
Telescopic Strut
Connection
Strut Pocket
Connection
100 Thick Top to Base
Drop Down Connection
60 Thick Top to Base
Fork Down Connection
Lifting/Extraction
point
Connector Pin
and r-clip
ASSEMBLY
INSTALLATION
REMOVAL
  • Page 1 1

MGF GSSW-02.1A User manual

Type
User manual

MGF GSSW-02.1A is a two sided excavation support system designed for simple assembly and robust support in weak, problematic, or saturated ground. It features telescopic struts for adjusting to required lengths, 4-leg chains for easy handling, and secure connections with pins and r-clips. The MGF GSSW-02.1A enables safe excavation and shoring, providing a stable environment for construction and maintenance work.

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI