SCT/SC TROUBLE SHOOTING
PROBLEM LOOK FOR CORRECTION
MACHINE IS NOT
RINSING
PROPERLY.
5-CHECK FINAL RINSE
TEMPERATURE.
6-CHECK FINAL RINSE LEVER & REED
SWITCH.
7-EMPTY RINSE-DRY CONTAINER.
5-ADJUST BOOSTER THERMOSTAT, CHECK INCOMING
WATER TEMP. TO BOOSTER FIRST.
6-ADJUST LEVER & REED SWITCH IF NECESSARY.
7-REPLACE CONTAINER.
MACHINE WILL
NOT COME UP
TO
TEMPERATURE.
(ELECTRIC TANK
HEAT)
1-TRIPPED CIRCUIT BREAKER.
2-TANK HEAT SWITCH.
3-BLOWN FUSE.
4-TRIPPED HIGH LIMIT.
5-CHECK LINE VOLTAGE.
6-CHECK AMPERAGE.
7-LIME BUILD UP ON ELEMENTS.
8-THERMOSTAT OUT OF ADJUSTMENT,
CHECK TEMPERATURE GUAGE.
9-VENT DAMPERS INCORRECTLY SET
10-IMPELLER MAY BE DEFECTIVE.
1-RESET CIRCUIT BREAKER.
2-CHECK TO INSURE TANK HEAT SWITCH IS ON.
3-TEST FUSE'S ON TANK HEAT CONTACTORS.
4-RESET HIGH LIMIT.
5-CHECK LINE VOLTAGE WITH VOLTMETER.
6-CHECK ELEMENTS FOR PROPER AMPERAGE DRAW.
7-DELIME TANKS.
8-ADJUST THERMOSTAT, REPLACE IF NECESSARY,
REPLACE GAUGE.
9-ADJUST DAMPERS.
10-REPLACE IF NEEDED.
MACHINE WILL
NOT COME UP
TO
TEMPERATURE.
(STEAM TANK
HEAT)
1-STEAM SUPPLY VALVE CLOSED.
2-STEAM RETURN VALVE CLOSED.
3-DEFECTIVE STEAM VALVE.
4-DEFECTIVE STEAM TRAP.
5-LOW STEAM PRESSURE.
6-THERMOSTATS OUT OF
ADJUSTMENT.
7-LIME BUILD UP ON COILS.
8-FILL VALVE STAYING OPEN.
9-VENT DAMPERS INCORRECTLY SET
10-IMPELLER MAY BE DEFECTIVE.
1-OPEN STEAM SUPPLY VALVE.
2-OPEN STEAM RETURN VALVE.
3-CHECK FOR PROPER OPERATION.
4-CHECK FOR PROPER OPERATION.
5-15 TO 40 LBS PRESSURE.
6-ADJUST THERMOSTATS, REPLACE IF NECESSARY.
7-DELIME TANKS.
8-CHECK FILL VALVE & AUTO FILL FLOAT SWITCH.
9-ADJUST DAMPERS.
10-REPLACE IF NEEDED.
FINAL RINSE
WILL NOT COME
UP TO
TEMPERATURE.
1-STEAM SUPPLY VALVE CLOSED.
2-STEAM RETURN VALVE CLOSED.
3-DEFECTIVE STEAM VALVE.
4-DEFECTIVE STEAM TRAP.
5-LOW STEAM PRESSURE.
6-THERMOSTATS OUT OF ADJUSTMENT.
7-WATER TEMPERATURE AT INLET LOW.
8-FINAL RINSE FLOW PRESSURE SET
INCORRECTLY.
1-OPEN STEAM SUPPLY VALVE.
2-OPEN STEAM RETURN VALVE.
3-CHECK FOR PROPER OPERATION.
4-CHECK FOR PROPER OPERATION.
5-15 TO 40 LBS PRESSURE.
6-ADJUST THERMOSTATS, REPLACE IF NECESSARY.
7-WATER AT INLET SHOULD BE 140° F.
8-FLOW PRESSURE SHOULD BE 15 TO 20 LBS ADJUST
PRV VALVE.