WEG Hydrogenerators SH11 line brushless horizontal User manual

Type
User manual
Motors I Automation I Energy I Transmission & Distribution I Coatings
Hydrogenerators
SH11 Line
Brushless - horizontal
Installation, Operation and Maintenance Manual
Installation, Operation and Maintenance Manual
Document Number: 13607224
Model: SH11
Language: English
Revision: 02
July 2018
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 5
Dear Customer,
Thank you for purchasing a WEG generator. Our products are developed with the highest standards
of quality and efficiency which ensures outstanding performance.
Electricity plays a major role in the comfort and well-being of mankind. Since the generator is
responsible for generating this energy, it must be identified and treated as an electrical machine,
whose features require certain precautions, such as for storage, installation and maintenance.
All efforts have been made to ensure that the information contained in this manual is faithful to the
configurations and operation of the generator.
Therefore, we recommend that you read this manual carefully before proceeding with the installation,
operation or maintenance of the generator in order to ensure safe and reliable operation of your
equipment and facility. If you need any further information, please contact WEG.
Always keep this manual close to the generator, so it can be consulted whenever necessary.
ATTENTION
1.
It is imperative to follow the procedures contained in this manual for the warranty to be valid;
2.
The generator installation, operation and maintenance procedures must be performed only by qualified
personnel.
NOTES
1.
The total or partial reproduction of information supplied in this manual is authorized, provided that
reference is made to its source.
2.
If this manual is lost, an electronic PDF file is available at www.weg.net or another printed copy may be
requested.
WEG EQUIPAMENTOS ELÉTRICOS S.A.
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 7
INDEX
1
INTRODUCTION ............................................................................................... 11
1.1 SAFETY WARNINGS IN THE MANUAL ........................................................................................... 11
2
GENERAL INSTRUCTIONS ............................................................................... 12
2.1 QUALIFIED PERSONNEL ................................................................................................................ 12
2.2 SAFETY INSTRUCTIONS ................................................................................................................ 12
2.3 STANDARDS ................................................................................................................................... 12
2.3.1 Brazilian Standards ............................................................................................................................. 12
2.3.2 International Standards ....................................................................................................................... 12
2.4 ENVIRONMENTAL CONDITIONS .................................................................................................... 13
2.5 OPERATING CONDITIONS ............................................................................................................. 13
2.6 VOLTAGE AND FREQUENCY ......................................................................................................... 13
3
RECEIVING, HANDLING AND STORAGE ........................................................... 14
3.1 RECEIVING ..................................................................................................................................... 14
3.2 HANDLING ...................................................................................................................................... 14
3.3 STORAGE ....................................................................................................................................... 15
3.3.1 Outdoor storage ................................................................................................................................. 15
3.3.2 Extended storage ............................................................................................................................... 15
3.3.2.1 Storage location .................................................................................................................. 15
3.3.2.1.1 Indoor storage ................................................................................................ 15
3.3.2.1.2 Outdoor storage ............................................................................................. 15
3.3.2.2 Separate parts .................................................................................................................... 16
3.3.2.3 Space heater ....................................................................................................................... 16
3.3.2.4 Insulation resistance ............................................................................................................ 16
3.3.2.5 Exposed machined surfaces ................................................................................................ 16
3.3.2.6 Bearings .............................................................................................................................. 16
3.3.2.7 Terminal box ....................................................................................................................... 16
3.3.2.8 Inspections and records during storage ............................................................................... 17
3.3.2.9 Maintenance plan during storage ......................................................................................... 17
3.3.3 Preparation for commissioning ............................................................................................................ 18
3.3.3.1 Cleaning .............................................................................................................................. 18
3.3.3.2 Bearing inspection ............................................................................................................... 18
3.3.3.3 Bearing lubrication ............................................................................................................... 18
3.3.3.4 Insulation resistance verification ........................................................................................... 18
3.3.3.5 Others ................................................................................................................................. 18
4
INSTALLATION ................................................................................................. 19
4.1 INSTALLATION SITE ....................................................................................................................... 19
4.2 SHAFT LOCK .................................................................................................................................. 19
4.3 ROTATION DIRECTION ................................................................................................................... 19
4.4 INSULATION RESISTANCE ............................................................................................................. 19
4.4.1 Safety instructions .............................................................................................................................. 19
4.4.2 General considerations ....................................................................................................................... 19
4.4.3 Measurement on the stator windings................................................................................................... 19
4.4.4 Measurement on the rotor and exciter windings .................................................................................. 20
4.4.5 Additional Information ......................................................................................................................... 20
4.4.6 Polarization index ................................................................................................................................ 20
4.4.7 Conversion of the measured values ..................................................................................................... 20
4.4.8 Insulation assessment ......................................................................................................................... 21
4.5 PROTECTIONS ............................................................................................................................... 21
4.5.1 Thermal protections ............................................................................................................................ 21
4.5.1.1 Temperature sensors .......................................................................................................... 21
4.5.1.2 Temperature limits for the windings ..................................................................................... 22
4.5.1.3 Alarm and trip temperatures ................................................................................................ 22
4.5.1.4 Temperature and ohmic resistance of the PT100 thermoresistance ..................................... 23
4.5.2 Protections in the panel ...................................................................................................................... 23
4.5.3 Space heater ...................................................................................................................................... 23
4.6 COOLING ........................................................................................................................................ 23
4.7 ELECTRICAL ASPECTS .................................................................................................................. 24
4.7.1 Electrical connections ......................................................................................................................... 24
4.7.1.1 Main electrical connections.................................................................................................. 24
www.weg.net
8 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 1
3607224
4.7.1.2 Accessories connection ...................................................................................................... 24
4.7.2 Grounding ...........................................................................................................................................24
4.8 MECHANICAL ASPECTS ............................................................................................................... 24
4.8.1 Foundations ........................................................................................................................................24
4.8.2 Foundation loads ................................................................................................................................24
4.8.3 Base types ..........................................................................................................................................24
4.8.3.1 Concrete base .................................................................................................................... 24
4.8.3.2 Metal base ......................................................................................................................... 25
4.8.4 Natural frequency of the base ..............................................................................................................25
4.8.5 Mounting ............................................................................................................................................25
4.8.6 Anchor plate set ..................................................................................................................................25
4.8.7 Leveling ..............................................................................................................................................25
4.8.7.1 Support .............................................................................................................................. 26
4.8.8 Alignment ............................................................................................................................................26
4.8.9 Inspection of pedestal bearings ...........................................................................................................27
4.8.10 Couplings ...........................................................................................................................................27
4.8.10.1 Direct coupling ................................................................................................................... 28
4.8.10.2 Coupling of generators equipped with sleeve bearings ........................................................ 28
4.8.11 Bearing loads ......................................................................................................................................28
4.8.12 Magnetic center ..................................................................................................................................28
4.9 BRAKE ........................................................................................................................................... 29
4.10 HYDRAULIC UNIT .......................................................................................................................... 29
5
OPERATION PRINCIPLE .................................................................................... 30
5.1 EXCITATION ................................................................................................................................... 31
5.2 DE-EXCITATION ............................................................................................................................. 31
5.3 VOLTAGE REGULATOR ................................................................................................................. 31
6
COMMISSIONING ............................................................................................. 32
6.1 PRELIMINARY INSPECTION .......................................................................................................... 32
6.2 FIRST OPERATION (WITH NO LOAD)............................................................................................. 32
6.3 OPERATION ................................................................................................................................... 33
6.3.1 Connection to the load or electric power system (Grid) ........................................................................33
6.3.2 Synchronization of the generator with the power grid ..........................................................................33
6.3.3 Data recording ....................................................................................................................................33
6.3.4 Temperatures......................................................................................................................................34
6.3.5 Bearings .............................................................................................................................................34
6.3.5.1 High-pressure oil injection system ....................................................................................... 34
6.3.6 Vibration .............................................................................................................................................34
6.3.7 Vibration causes ..................................................................................................................................34
6.4 SHUTDOWN ................................................................................................................................... 34
7
MAINTENANCE ................................................................................................. 35
7.1 GENERAL ....................................................................................................................................... 35
7.2 GENERAL CLEANING .................................................................................................................... 35
7.3 WINDING INSPECTIONS ................................................................................................................ 35
7.4 WINDING CLEANING ..................................................................................................................... 35
7.4.1 Inspections .........................................................................................................................................36
7.4.2 Re-impregnation .................................................................................................................................36
7.4.3 Insulation resistance .............................................................................................................................36
7.5 COOLING SYSTEM MAINTENANCE ................................................................................................ 36
7.6 VIBRATION ..................................................................................................................................... 36
7.7 SHAFT GROUNDING DEVICE ........................................................................................................ 36
7.8 EXCITER MAINTENANCE ............................................................................................................... 36
7.8.1 Exciter.................................................................................................................................................36
7.8.2 Insulation resistance ............................................................................................................................36
7.8.3 Diode test ...........................................................................................................................................36
7.8.3.1 Diode Replacement ............................................................................................................ 37
7.8.4 Varistor test .........................................................................................................................................37
7.8.4.1 Varistor replacement ........................................................................................................... 37
7.9 BEARING MAINTENANCE .............................................................................................................. 37
7.9.1 Bearing data .......................................................................................................................................37
7.9.2 Bearing installation and operation ........................................................................................................37
7.9.3 Oil change ...........................................................................................................................................38
7.9.4 Sealing ................................................................................................................................................38
7.9.5 Sleeve bearing operation .....................................................................................................................38
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 9
7.9.6 Sleeve bearing maintenance ............................................................................................................... 38
7.9.7 Bearing protection setting ................................................................................................................... 39
7.9.8 Disassembly/assembly of the bearing temperature sensors ................................................................. 39
8
GENERATOR DISASSEMBLY AND ASSEMBLY .................................................. 40
8.1 DISASSEMBLY ............................................................................................................................... 40
8.2 ASSEMBLY ..................................................................................................................................... 40
8.3 TIGHTENING TORQUE ................................................................................................................... 40
8.4 AIR GAP MEASURMENT................................................................................................................. 41
8.5 SPARE PARTS ................................................................................................................................ 41
9
MAINTENANCE PLAN ....................................................................................... 42
10
ABNORMALITIES, CAUSES AND SOLUTIONS ................................................... 43
11
DECLARATION OF CONFORMITY ..................................................................... 45
12
ENVIRONMENTAL INFORMATION ..................................................................... 46
12.1 PACKAGE ....................................................................................................................................... 46
12.2 PRODUCT ....................................................................................................................................... 46
12.3 HAZARDOUS WASTE ..................................................................................................................... 46
13
WARRANTY TERM ........................................................................................... 47
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 11
1 INTRODUCTION
This manual contains information regarding synchronous generators SH11.
The generators are supplied with specific documents (drawings, connection diagram, characteristic curves, etc.). Those
documents, together with this manual, must be thoroughly evaluated before proceeding with the installation, operation or
maintenance of the generator.
All the procedures and standards contained in this manual must be observed in order to ensure proper operation of the
generator and the safety of the personnel involved. Following these procedures is also important to ensure the validity of the
generator warranty. Thus, we recommend carefully reading this manual before performing the installation, operation or
maintenance of the generator. If you need any further information, consult WEG.
1.1 SAFETY WARNINGS IN THE MANUAL
In this manual, the following safety warnings are used:
DANGER
Failure to observe the procedures recommend in this warning may result in death, serious injuries and
extensive equipment damage.
ATTENTION
Failure to observe the procedures recommend in this warning may result in equipment damage.
NOTE
This provides important information for correct understanding and proper operation of the product.
www.weg.net
12 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 13607224
2 GENERAL INSTRUCTIONS
All personnel involved with the assembly, operation or maintenance of electrical installations must be informed and updated
on the standards and safety instructions that guide the job and are advised to strictly comply with them. Before beginning
any job, the person in charge must make sure that all points have been duly observed and warn the respective personnel
about the danger inherent to the task to be performed.
Improper application, inadequate handled or maintenance of the generator, may cause serious injuries and/or material
damages. Therefore, it is highly recommended that such jobs be always performed by qualified personnel.
2.1 QUALIFIED PERSONNEL
The term qualified personnel means those who, because
of their training, experience, education level and
knowledge of the applicable standards, specifications,
accident prevention, safety standards and operating
conditions, have been authorized by the persons in charge
to execute the necessary tasks, and who are able to
recognize and avoid any possible danger.
Such qualified personnel must also know and be able to
provide first aid procedures if necessary.
The entire start-up, maintenance and repair tasks must
only be performed by qualified personnel.
2.2 SAFETY INSTRUCTIONS
DANGER
During normal operation of this equipment, a
hazard associated with energized or rotating
components with high voltage or elevated
temperatures exists.
Thus,
the operation with open terminal
boxes, unprotected couplings, improper
handling, or failure to comply with the
operating standards, may cause severe
personal injuries and material damages.
ATTENTION
When devices and equipment are used
outside the industrial environment, the user
must ensure the safety of the equipment by
adopting proper protection and safety
measures during installation (for example,
keeping people away, avoiding contact of
children, etc.).
Those responsible for the safety of the installation must
ensure that:
Only qualified personnel install and operate the
equipment;
They have this manual and all other documents
supplied with the generator at hand, as well as that they
perform the tasks in strict compliance with the service
instructions, relevant standards and specific product
documentation.
ATTENTION
Failure to comply with installation and safety
standards may void the product warranty.
Firefighting equipment and first aid notices
must be available in visible and easily
accessible locations at the work site.
Qualified personnel must also observe:
All the technical data regarding the allowed applica
tions
(operating conditions, connections and installation
environment), provided in the purchase order
documents, operating instructions, manuals and other
documentation;
The specific regulations and conditions for the loca
l
installation;
The use of suitable tools and equipment for handling
and transportation;
That the protective devices of the individual
components are removed shortly before installation.
Individual parts must be stored in vibration-free
environments, avoiding falls and ensuring their protection
against aggressive agents and/or that they do not
jeopardize people.
2.3 STANDARDS
The generators are specified, designed, manufactured and
tested according to the standards described in items
2.3.1 and 2.3.2.
The applicable standards are specified in the commercial
contract. May indicate other national or international
standards, depending on the application or installation
location.
2.3.1
Brazilian Standards
NBR 15623-2, Maquinas elétricas girantes - Dimensões
e
series de potências para máquinas elétricas girantes –
Padronização Parte 2: Designação de carcaças entre
355 a 1000 e flanges entre 1180 a 2360;
ABNT NBR 5117:2007, Máquina elétrica girante –
Máquina Síncrona – Especificação;
ABNT NBR 5052:1984, Máquina Síncrona – Ensaios;
ABNT NBR 6158:1995, Sistema de tolerância e ajustes;
ABNT NBR IEC60034-5, Maquinas elétricas girantes –
Parte 5: Graus de proteção proporcionados pelo
projeto completo de máquinas elétricas girantes
(código IP) – classificação;
ABNT NBR IEC60034-6, Maquinas elétricas girantes –
Parte 6: Métodos de resfriamento (código IC)
ABNT NBR IEC60034-7, Maquinas elétricas girantes –
Parte 7: Classificação dos tipos de construção, arranjos
de montagem e posição da caixa de terminais (código
IM)
ABNT NBR IEC60034-9, Maquinas elétricas girantes –
Parte 9: Limites de Ruído.
ABNT NBR IEC60034-14, Maquinas elétricas girantes –
Parte 14: Medição, avaliação e limites da severidade de
vibração mecânica de máquinas de altura de eixo igual ou
superior a 56mm.
2.3.2
International Standards
IEC-60072-2, Dimensions and output series for rotati
ng
electrical machines – Part 2: Frame numbers 355 to
1000 and flange numbers 1180 to 2360;
IEC60034-1 Rotating electrical machines – Part 1:
Rating and performance
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 13
IEC60034-2-1 Rotating electrical machines – Part 2-1:
Standard methods for determining losses and efficiency
from tests (excluding machines for traction vehicles)
IEC60034-4 Rotating electrical machines – Part 4:
Methods for determining synchronous machine
quantities from tests
IEC60034-5 Rotating electrical machines – Part 5:
Degrees of protection provided by the integral design of
rotating electrical machines (IP code) – classification
IEC60034-6 Rotating electrical machines – Part 6:
Methods of cooling (IC code)
IEC60034-7 Rotating electrical machines – Part 7:
Classification of types of construction, mounting
arrangements and terminal box position (IM code)
IEC60034-8 Rotating electrical machines – Part 8:
Terminal markings and direction of rotation
IEC60034-9 Rotating electrical machines – Part 9:
N
oise limits
IEC60034-14 Rotating electrical machines – Part 14:
Mechanical vibration of certain machines with shaft
heights 56mm and higher – Measurement, evaluation
and limits of vibration severity
ISO286-1 Geometrical product specifications (GPS) –
ISO code system for tolerances on linear sizes – Part 1:
Basis of tolerances, deviations and fits
ISO286-2 Geometrical product specifications (GPS) –
ISO code system for tolerances on linear sizes – Part 2:
Tables of standard tolerance classes and limit
deviations for holes and shafts
ISO1940-1 Mechanical vibration – Balance quality
requirements for rotors in a constant (rigid) state – Part
1: Specification and verification of balance tolerances;
ISO10816-5 Mechanical vibration – Evaluation of machine
vibration by measurements on non-rotating parts – Part 5:
Machine sets in hydraulic power generating and pumping
plants.
2.4 ENVIRONMENTAL CONDITIONS
The generators was designed according to the specific
environment characteristics (temperature and altitude) of
your application, and are described on the nameplate and
in the datasheet of the generator.
2.5 OPERATING CONDITIONS
In order for the product warranty to be valid, the generator
must operate according to the rated data indicated on its
nameplate, observing the applicable standards and the
information provided in this manual.
2.6 VOLTAGE AND FREQUENCY
The generator must be able to perform its main function
continuously in Zone A, but it does not have to fully meet
its performance characteristics at rated voltage and
frequency (refer to the point with rated characteristics in
Figure 2.1), and it may present some deviations. The
temperature rises may be above those at rated voltage
and frequency.
The generator must be able to perform its main function in
Zone B, but it may present greater deviations of its
performance at rated voltage and frequency than in Zone
A. The temperature rises may be higher than those
observed at rated voltage and frequency and, most likely,
will be higher than those in Zone A.
Prolonged operation in the periphery of Zone B is not
recommended.
Figure 2.1: Voltage and frequency variation limits (IEC60034-1)
Frequency (pu)
Zone B (outside zone A)
Point of rated conditions
Zone A
Voltage (pu)
www.weg.net
14 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 13607224
3 RECEIVING, HANDLING AND STORAGE
3.1 RECEIVING
All generators were tested and are in perfect operating
conditions. The machined surfaces are protected against
corrosion. The package must be inspected upon receipt
for occasional damages during transportation.
ATTENTION
Any damage must be
photographed,
documented and reported immediately to the
carrier, the insurer and WEG. The non-
communication of this damage will void the
warranty.
ATTENTION
Parts supplied in additional packages must
be checked upon receipt.
When lifting the package (or container), the proper
hoisting points, the weight indicated on the package or
on the nameplate, and the operating capacity of the
hoisting equipment must be observed.
Generators packed in wooden crates must always be
lifted by their own hoisting eye or by a proper forklift;
they must never be lifted by the package;
The package can never be overturned. Place it on the
floor carefully (without impact) in order to avoid damage
to the bearings;
Do not remove the grease for protection against
corrosion from the shaft end and, or the closing plugs
present in the terminal box holes. These protections
must remain in place until the moment of the final
assembly.
A complete visual inspection of the generator must
be
carried out after removing the package;
The shaft locking system must be removed just before
the installation and stored to be used in future
transportation of the generator.
3.2 HANDLING
Figure 3.1: Handling - generators IM1001/1005
For handling the hydro generator SH11 with mounting
IM1001/1005 assembled, they should only be used the
lifting lugs suitable for this purpose, as shown in Figure
3.1.
ANCHOR BASE
Figure 3.2: Handling - generators IM7311/7315
For handling the hydro generator SH11 with mounting
IM7311 / 7315 assembled, they should only be used the
lifting lugs on the anchor base, as shown in Figure 3.2.
If the lifting of the generator through the frame lifting lugs is
inevitable, WEG must be consulted.
ATTENTION
The air guides and other devices that may
have contact with the chains, shackles,
etc. (If any) must be removed.
The ventilation box, heat exchanger and
other devices that might have contact with
the chains, shackles, etc. They must be
removed.
Steel wire ropes, clevises and the lifting
e
quipment must be able to stand the
generator weight.
For handling and assembling generators
supplied disassembled, refer to the
handling and assembly manual supplied
with the generator.
NOTES
Observe the indicated weight. Do not lift
the generator causing jolts or put it down
abruptly on the floor, because this can
cause damage to the bearings;
The lifting lugs on the heat exchanger,
end shields, bearings, radiator, terminal
box, etc. are designed to handle these
components only separately;
Never use the shaft to lift the generator;
In order to move the generator, the shaft
must be locked with the shaft locking
device supplied with the generator.
FRAME LIFTING LUGS
Use for handling only the
frame in the event of
generator assembly or
disassembly.
Do not use them to handle
the complete generator.
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 15
3.3 STORAGE
If the generator is not installed immediately after reception,
it must remain inside the package and stored in a location
protected against moisture, vapors, sudden changes in
temperature, rodents and insects.
The generator must be stored in vibration-free locations in
order to avoid bearing damage.
ATTENTION
Space heaters must remain powered during
inside the generator.
Any damage to the paint or corrosion
protection of the machined parts must be
repaired.
3.3.1
Outdoor storage
The generator must be stored in a dry location, free of
flooding and vibrations.
Repair all damages occasionally caused to the packing
during transportation before storing the generator, which
is necessary to ensure proper storage conditions.
Place the generator on platforms or foundations which
ensure protection against humidity from the ground and
prevent it from sinking into the soil. Free air circulation
underneath the generator must be assured.
The cover used to protect the generator against the bad
weather must not be in contact with its surfaces. In order
to ensure free air circulation between the generator and
such covers, place wooden blocks as spacers.
3.3.2
Extended storage
When the generator is stored for a long period (two
months or more) before the start-up, it is exposed to
external agents, such as temperature variations,
moisture, aggressive agents, etc.
Empty spaces inside the generator, such as those in
bearings, terminal box, and windings, are exposed to
humidity, which may condense and, depending on the
type and degree of air contamination, aggressive
substances may also penetrate these empty spaces.
Consequently, after long periods of storage, the winding
insulation resistance may drop below the acceptable
values, internal components, such as bearings, may
oxidize, and the lubricant power of the lubricant agent in
the bearings may be adversely affected.
All of these influences increase the risk of damages before
the generator start-up.
ATTENTION
For the generator warranty to be valid, it is
necessary to make sure that all the
preventive measures described in this
manual, as well as constructive aspects,
maintenance, packing, storage and
periodical inspections be followed and
recorded.
The extended storage instructions are valid for
generators that remain stored for long periods (two
months or more) before start-up or generators already
installed and that are in a prolonged stoppage,
considering the same period.
3.3.2.1
Storage location
In order to ensure the best storage conditions for the
generator during long periods, the chosen location must
strictly meet the criteria described in sections 3.3.2.1.1
and 3.3.2.1.2.
3.3.2.1.1
Indoor storage
The storage site must be closed and covered;
The site must be protected against moisture, vapors,
aggressive agents, rodents and insects;
Corrosive gases, such as chlorine, sulfur dioxide or
acids, must not be present;
The site must be free of vibration;
The site must have a ventilation system with air fil
ter;
Ambient temperature between 5 °C and 60 °C, without
sudden temperature variations;
Relative humidity < 50%;
The site must be protected against dirt and dust
accumulation;
It must have a fire detection system;
The location must have a power supply for the space
heaters.
If any of these requirements is not met in the storage site,
WEG recommends that additional protections be
incorporated to the generator package during the storage
period, as follows:
A closed wooden crate or the like with an electrical
installation that allows the energization of the space
heaters;
If there is risk of infestation and fungus formation, the
package must be protected in the storage location by
spraying it or painting it with appropriate chemicals;
The package must be prepared carefully by an
experienced person.
3.3.2.1.2
Outdoor storage
ATTENTION
Outdoor storage of the generator is not
recommended.
In case outdoor storage is unavoidable, the generator must
be packed in a specific package for such condition, as
follows:
For outdoor storage (exposed to the weather), besides the
package recommended for indoor storage, the package
must be covered with protection against dust, moisture
and other foreign materials, using resistant canvas or
plastic.
The package must be placed on platforms or foundations
that ensure protection against dirt and moisture and keep
it from sinking into the soil;
After the package is covered, a shelter must be erected to
protect it against direct rain, snow and excessive sun heat.
ATTENTION
In case the generator remains stored for long
periods (two months or more), it is
recommended to inspect it regularly as
specified in the section 3.3.2.9
of this
manual.
www.weg.net
16 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 13607224
3.3.2.2
Separate parts
If parts are supplied separately (terminal boxes, end
shields, etc.), these parts must be packed as specified
in sections
3.3.2.1.1
and
3.3.2.1.2
of this manual.
The relative humidity inside the package must not
exceed 50%.
Rolling bearings must not be subject to shocks, falls or
storage with vibration or humidity, which can cause
marks on the internal races or on the balls, reducing
their useful life.
3.3.2.3
Space heater
ATTENTION
The space heaters must remain
powered
during storage to avoid moisture
condensation inside the generator and
ensure that the winding insulation resistance
remains within acceptable levels.
3.3.2.4
Insulation resistance
During the storage period, the insulation resistance of the
generator windings must be measured and recorded every
three months and before the generator installation.
Any insulation resistance reduction must be investigated.
3.3.2.5
Exposed machined surfaces
All exposed machined surfaces (e.g., shaft end and
flanges) are protected at the factory with a temporary
protective agent (rust inhibitor).
This protection coating must be reapplied every six
months or when removed and/or damaged.
Recommended Product:
Anticorit BW protective agent
Manufacturer
: Fuchs
3.3.2.6
Bearings
Depending on the machine mounting position and on the
lubrication type, the machine can be transported with or
without oil in the bearings.
The machine must be stored in its original operating
position and with oil in the bearings, when specified.
The oil level must be respected, remaining in the middle of
the sight glass.
ATTENTION
In order to keep the bearings in good
conditions during the storage period,
every
two months the shaft locking device must
be removed, and the generator rotor must
be rotated at least 10 full turns at a speed
of 30 rpm
to circulate the oil and preserve
the internal parts of the bearings.
NOTES
For bearings that have a high-pressure oil
injection system (jacking), this system must
be activated before rotating the machine
rotor.
For bearings without oil tank (dry crankcase),
the oil circulation system must be activated
before rotating the machine shaft.
The shaft must always be rotated in
the
rotation direction of the machine.
If it is not possible to rotate the machine shaft, as
recommended, after six months of storage, the following
procedure must be used for protecting both the bearing
internally and the contact surfaces against corrosion:
Close all the threaded holes with plugs;
Seal the gaps between the shaft and the bearing seal
on the shaft by applying water-proof adhesive tape;
Check if all the flanges (e.g., oil inlet and outlet) are
closed. If not, they must be closed with blind covers;
Remove the upper sight glass from the bearing and
apply the corrosion inhibitor spray (TECTYL 511 or
equivalent) inside the bearing;
Close the bearing with the upper sight glass.
NOTES
If the bearing has no upper sight glass, the
top cover of the bearing must be
disassembled to apply the corrosion inhibitor
spray.
Each six months of storage, repeat the procedure
described above.
If the storage period exceeds two years.
Disassemble the bearing;
Preserve and store the parts.
3.3.2.7
Terminal box
When the insulation resistance of the generator windings
is measured, the main terminal box and the other terminal
boxes must also be inspected, observing the following
aspects:
The inside must be dry, clean and free of dust
accumulation;
The contact elements cannot present corrosion;
The seals must be in proper condition;
The cable inlets must be correctly sealed.
ATTENTION
If any of these items are not in proper
condition, proceeds the adequate
maintenance and, if necessary, replace
damaged parts.
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 17
3.3.2.8
Inspections and records during storage
The stored generator must be inspected periodically and
inspection records must be filed.
The following points must be inspected:
1. Physical damages;
2. Cleanliness;
3. Signs of water condensation;
4. Protective coating conditions;
5. Paint conditions;
6. Signs of aggressive agents;
7. Satisfactory operation of space heaters. It is
recommended that a signaling or alarm system be
installed in the location in order to detect power
interruption on the space heaters;
8. Record the ambient temperature and relative humidity
around the generator, the winding temperature (using
RTDs), the insulation resistance and the polarization
index;
9. Storage site, so that it complies with the criteria
described in section 3.3.2.1.
3.3.2.9
Maintenance plan during storage
During the storage period, the generator maintenance must be performed and recorded according to the plan described in
Table 3.1
.
Table 3.1: Storage plan
Monthly
2
months
6
months
2
years
Before
start-up
Notes
STORAGE LOCATION
Inspect the cleanliness conditions
x
x
Inspect the humidity and temperature
conditions
x
Check for signs of insect infestation
x
PACKAGE
Inspect for damages
x
Check the internal relative humidity
x
Change the dehumidifier in the package (if
any)
x
Whenever necessary
SPACE HEATER
Check the operating conditions
x
WHOLE GENERATOR
Perform external cleaning
x
x
Check the painting conditions
x
Check the rust inhibitor on the exposed
machined parts
x
Reapply the rust inhibitor
x
WINDINGS
Measure the insulation resistance
x
x
Measure the polarization index
x
x
TERMINAL BOX AND GROUNDING TERMINALS
Clean the interior of the boxes
x
x
Inspect the seals and gaskets
x
x
BEARINGS
Rotate the shaft
x
Apply anti-corrosion spray
x
Clean the bearings and relubricate them
x
Disassemble and store the parts
If the storage period exceeds 2
years
www.weg.net
18 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 13607224
3.3.3
Preparation for commissioning
3.3.3.1
Cleaning
The internal and external parts of the generator must be
free of oil, water, dust, and dirt.
Remove the rust inhibitor from the exposed surfaces
with a cloth damped in a petroleum-based solvent;
Make sure that the bearings and cavities used for
lubrication are free of dirt and the cavity plugs are
correctly sealed and tightened. Oxidation and marks on
the bearing seats and on the shaft must be carefully
removed.
3.3.3.2
Bearing inspection
ATTENTION
If the generator storage period exceeds six
months, the sleeve bearings must be
disassembled, inspected and cleaned, before
starting the generator operation.
The sleeve bearings without oil tank (dry
crankcase), regardless of the generator storage
period, should necessarily be disassembled,
inspected and cleaned before starting the
generator operation.
Reassemble the sleeve bearings and carry out
lubrication.
Contact WEG to perform this procedure.
3.3.3.3
Bearing lubrication
Use the lubricant specified for bearing lubrication.
Information on the bearings and lubricants are indicated
on the bearing nameplate, and the lubrication must be
done as described in section 7.9 of this manual, always
considering the type of bearing.
3.3.3.4
Insulation resistance verification
Before putting the generator into operation, the insulation
resistance must be measured according to section 3.3.2.4
of this manual.
3.3.3.5
Others
Follow the other procedures described in section 6 of this
manual before putting the generator into operation.
www.weg.net
13607224 Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal l 19
4 INSTALLATION
4.1 INSTALLATION SITE
Generators must be installed in easily accessible places,
allowing periodic inspections, on-site maintenance and, if
necessary, removal for external services.
The following environmental conditions must be ensured:
Clean and well-ventilated location;
The installation of other equipment or walls must not
hinder or block the generator ventilation;
The area around and above the generator must be
sufficient for maintenance or handling;
The environment must be in accordance with the
generator protection degree.
4.2 SHAFT LOCK
The generator leaves the factory with a lock on the shaft to
prevent damages to the bearings during transportation.
This lock must be removed prior to generator installation.
ATTENTION
The shaft locking device must be installed
whenever the generator is removed from its
base (uncoupled) in order to prevent
damages to the bearings during
transportation.
The shaft end is protected at the factory with
a temporary protective agent (rust inhibitor).
During the generator installation, it is
necessary to remove this product from the
grounding brush (if any) contact track on the
shaft.
4.3 ROTATION DIRECTION
The rotation direction is indicated on a plate affixed to the
drive end of the generator and in the generator specific
documentation.
ATTENTION
Generators supplied with a single rotation
direction must not operate in the opposite
direction.
In order to operate the generator in the
opposite direction, consult WEG.
4.4 INSULATION RESISTANCE
4.4.1
Safety instructions
DANGER
In order to measure the insulation resistance,
the generator must be turned off and stopped.
The winding being tested must be connected
to the frame and grounded until all residual
electrostatic charges are removed. Capacitors
(if any) must also be grounded before
disconnecting and separating the terminals to
measure the insulation resistance.
Failure to comply with these procedures may
result in personal injury.
4.4.2
General considerations
When the generator is not immediately put into operation,
it must be protected against moisture, high temperatures,
and dirt, avoiding impacts to the insulation resistance.
The winding insulation resistance must be measured
before putting the generator into operation.
If the environment is too humid, the insulation resistance
must be measured periodically during storage. It is difficult
to establish fixed rules for the actual value of the winding
insulation resistance, as it varies according to the
environmental conditions (temperature, humidity),
generator cleanliness conditions (dust, oil, grease, dirt),
and quality and condition of the insulating material used.
The evaluation of the periodical follow-up records is useful
to conclude whether the generator is able to operate.
4.4.3
Measurement on the stator windings
The insulation resistance must be measured with a
megohmmeter. The testing voltage for the windings must
be in accordance with Table 4.1, and according to IEEE43
standard.
Table 4.1: Voltage for the winding Insulation resistance test
Winding rated
voltage (V)
Insulation resistance test -
continuous voltage (V)
< 1000 500
1000 - 2500 500 - 1000
2501 - 5000 1000 - 2500
5001 - 12000 2500 - 5000
> 12000 5000 - 10000
Before measuring the stator winding insulation resistance:
Disconnect all connections to the stator terminals;
Disconnect and insulate all CTs and PTs (if any);
Ground the generator frame;
Measure the winding temperature;
Ground all temperature sensors;
Check the humidity;
Disconnect the neutral grounding;
Ensure that the generator bars are not grounded.
The insulation resistance measurement of the stator
windings must be done in the main terminal box. The
instrument (megohmmeter) must be connected between
the generator frame and the winding. The frame must be
grounded and the three phases of the stator winding must
remain connected to the neutral point, as shown in Figure
4.1.
www.weg.net
20 l Installation, Operation and Maintenance Manual – Hydrogenerators – SH11 – brushless – horizontal 13607224
Figure 4.1: Megohmmeter connection
Whenever possible, each phase must be isolated and
tested separately. The separate test allows a comparison
between the phases. When a phase is tested, the other
two phases must be grounded to the same ground of the
frame, as shown in Figure 4.2.
Figure 4.2: Connection of the megohmmeter to separate phases
If the total winding measurement presents a value below
the recommended, the neutral connections must be
opened and the insulation resistance of each phase must
be measured separately.
ATTENTION
Much higher values may be frequently
obtained in generators being operated for a
long period of time. Comparison with values
obtained in previous tests on the same
generator - under similar load, temperature
and humidity conditions – may be an
excellent parameter to evaluate the winding
insulation conditions, instead of using the
value obtained in a single test as the basis.
Significant or sudden reductions are
considered suspicious.
4.4.4
Measurement on the rotor and exciter
windings
Measurement on the rotor winding:
Disconnect the rotor cables from the diode set and
from the discharge resistor (if any);
Connect the instrument to measure the insulation
resistance (megohmmeter) between the rotor winding
and the generator shaft. The measuring current must
not pass through the bearings.
Measurement of the main exciter stator winding:
Disconnect the power supply cables from the exciter;
Connect the instrument to measure the insulation
resistance (megohmmeter) between the exciter stator
winding and the generator frame.
Measurement on the main exciter rotor winding:
Disconnect the cables of the exciter rotor from the
diode set;
Connect the instrument to measure the insulation
r
esistance (megohmmeter) between the exciter rotor
winding and the generator shaft. The measuring current
must not pass through the bearings.
Measurement of the auxiliary exciter stator winding (PMG),
if any:
Disconnect the cables that connect the auxiliary exciter
to the voltage regulator;
Connect the instrument to measure the insulation
resistance (megohmmeter) between the auxiliary exciter
stator winding and the generator frame.
4.4.5
Additional Information
ATTENTION
After measuring the insulation resistance,
ground the tested winding in order to
discharge it.
The test voltage to measure the insulation
resistance of the rotor and space heater must
be 500 Vdc and for the other accessories
100 Vdc.
It is not recommended to measure the
insulation resistance of thermal protectors.
4.4.6
Polarization index
The polarization index is defined by the ratio between the
insulation resistance measured in 10 minutes and the
insulation resistance measured in 1 minute. This
measurement procedure is always carried out at relatively
constant temperatures. The polarization index allows the
evaluation of the generator insulation conditions.
DANGER
In order to avoid accidents, the winding must
be grounded immediately
after measuring the
insulation resistance.
4.4.7
Conversion of the measured values
The insulation resistance must be measured at 40°C. If the
measurement is performed at a different temperature, it is
necessary to correct the reading to 40°C by using a curve
of the insulation resistance variation as a function of the
temperature, obtained on the generator itself. If this curve
is not available, the approximate correction provided by
the curve in Figure 4.3, according to NBR 5383 / IEEE43,
may be used.
M
M
M
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46
  • Page 47 47
  • Page 48 48
  • Page 49 49
  • Page 50 50
  • Page 51 51

WEG Hydrogenerators SH11 line brushless horizontal User manual

Type
User manual

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI