3.1 Programming synergic lines
MEK 4S, MEK 4SP
The programming procedure is as follows:
S Connect the PAH 1 controller to connector 9.
S Switch 26 on MEK 4SP must not be in pulse mode.
S Set selector switch 22 to either setting 7 or 8 and
set switch 25 to setting B, connect PAH 1. T he wire
feed unit will now operate as if it is in manual
mode.
S Set the selector switch on the PAH 1 controller to
setting 1.
S Adjust the wire feed speed using knob 7 and adjust
the welding voltage using knob 8 for work point
1.
S Make a test weld, and if necessary adjust the
settings to produce a satisfactory weld.
S Press the save button 20, and hold it in until lamp 21 lights up, then release the
button.
S Repeat steps 4, 5, 6, 7 for settings 2, 3, 4 on the PAH 1 controller (creates work
points 2, 3, 4).
S Disconnect PAH 1, to return to synergic operation.
ESABFeed 30--4 and ESABFeed 48--4
Programme as follows:
S Set switch 10 in position B and use
switch 8 to select position 7 or 8.
S Connect PAH 1 to the remote control
unit socket. T h e wire feed unit now
functions the same as in m anual
operation
S Set the switch on PAH 1 to position 1.
S Set wire feed and welding voltage for
work point 1. You can adjust wire feed
and voltage between their minimum
and maximu m limits.
S Test weld, if necessary adjust set
data until the welding performance is
good. Store set data with the store button 6.
S Do the corresponding settings for work point 2, 3 and 4 ( T he switch on PAH 1 in
position 2, 3 and 4.)
When programming is complete and the programming box disconnected, the wire
feed unit is in synergic operation.