  • Hello! I am an AI chatbot trained to assist you with the Fiat Case IH AFS Pro 600 Setup. I’ve already reviewed the document and can help you find the information you need or explain it in simple terms. Just ask your questions, and providing more details will help me assist you more effectively!
Case IH AFS Pro 600 Display
Setup for Raven Controller
This document will guide you through how to
set up your AFS Pro 600 display to drive a
Raven Variable Rate Control System through
its serial (RS-232) interface.
2
AFS Pro 600 Raven Control
Table Of Contents
Hardware/Software Requirements
Step 1: Assign Com Ports
Step 2: Set Up Raven Options
Step 3: Add Raven Run Screen Windows to Layout
Step 4: Implement Setup
Step 5: Work Condition and Layer Assignment
Product Setup
Prescription Setup
GPS Offsets
Work State
Mapping Coverage and As-Applied Data
3
Hardware/Software Requirements
The following hardware requirements must be met for the
AFS Pro 600 Display to properly communicate with the
Raven Variable Rate Control System
AFS Pro 600
o Required Software Install
¾ Raven Controller (16.2.0.0)
¾ Com3 Manager (16.2.0.0)
¾ As Applied (16.2.0.0)
¾ Precision Farming (16.3.0.0)
¾ Generic Tractor (16.2.0.0) or Large Tractor (16.1.0.0)
¾ Framework (16.4.0.0)
Table of Contents
4
Hardware/Software Requirements
Continued
AFS Pro 600
o Hardware Install
¾ Com Port Adapter
This breaks out Com Ports A and B on the AFS Pro 600 Display and
provides proper connection and grounding for communication with the
Raven System
(PN 87732647) for existing AFS Pro 600-compatible tractor harnesses
(PN 87735690) for tractors without AFS Pro 600-compatible harness
<<<Insert Picture(s) of Com Port Adapter on Pro 600>>>
Table of Contents
5
Hardware/Software Requirements
Continued
Raven Variable-Rate Control System
o Supported models include:
¾ SCS 100 Series: 440/450/460/660 and other variants
¾ SCS 1000 Series: 4000/4400/4600/5000 and other variants
o
System must have serial (RS-232) interface
¾ Null Modem Serial Cable required for connection between AFS Pro
600 Display and Raven Controller Display
SCS 100 Series: Raven P/N 115-0159-822
SCS 10000 Series: Raven P/N 115-0171-395
Table of Contents
6
Hardware/Software Requirements
Continued
Raven 4400/4600 Special Settings
o All settings are found under Data Menu -> Serial.
¾ The “Data Direct” setting must be set to “Pass Data Through
Communications Port”
¾ “Variable Rate Control” must be enabled.
¾ Also unlike other controllers the “Trigger Units” and “Trigger Value”
have to be set before “Data Logger” can be turned on.
Table of Contents
7
Display Software Setup
Step 1: Assign Com Ports
Go to Toolbox>3rdCtrl
o If Raven System is connected to Com A (RS-232 port integrated
into main connector) select “Raven Controller” from the pull-
down list for Com A
o If Raven System is connected to Com B (RS-232 9-pin port on
bottom of display) select “Raven Controller from the pull-down
list for Com B
Table of Contents
8
Display Software Setup
Table of Contents
9
Display Software Setup
Table of Contents
10
Display Software Setup
Step 2: Setup Raven Options
Go to Toolbox>Raven
o Control Channel: If only one Raven System is installed, there will only
be one option. The letter before “Raven SCS” indicates the Com Port of
the system that you are configuring. The options selected on this page
correspond only to the single Raven System selected in this window. If
you are controlling two Raven Systems, each will have its own
configuration.
o Area Unit: This is the area units (SI - hectares, TU – 1000 sq. ft, US -
acres) that the Raven System is set to use. This setting must match the
setting on the Raven System or it will not work properly.
o Valve: This is the valve that the Raven System uses. There are different
control requirements for Standard and Fast Close valves so make sure
this setting matches the Raven System.
Table of Contents
11
Display Software Setup
Step 2 continued: Setup Raven Options
o SCS Series: Select the correct series from the pull-down list to match
the Raven System. There are communication interface differences
between series so it is important to select the correct series.
o Use Work State: “Yes” for this option uses the Pro 600 Work State
(Work Control) to control application rate. For information on Work
Control, click here.
¾ When the work state is “Off”, the Raven System is “shut off” by sending a
“zero” application rate. For Raven Systems with standard valves, this zero
rate will not actually force it to zero application rate. Instead, the Raven
System will beep to indicate that the master should be shut off.
¾ When the work state is “On”, the system sends the normal application rate,
which should be executed by the Raven System regardless of valve type.
Table of Contents
12
Display Software Setup
Step 2 continued: Setup Raven Options
o Product Form: Depending on the type of Raven System
selected, there are up to 3 product forms available. The
product form selected should match the product form that the
Raven System is set for. (Liquid, Granular, Other, None). The
“Other” product form is any non-granular product applied in
lb/ac or kg/ha.
o Look Ahead: This is the typical time it takes for the Raven
System to transition to a new rate after receiving a rate change
command. This number is important when prescriptions are
used so rate changes happen at prescriptions boundaries and
not after the boom has crossed a prescription boundary.
Table of Contents
13
Display Software Setup
Step 2 continued: Setup Raven Options
o Number of Booms: This is the number of booms that the Raven System
is set up to control. Make sure this number matches the Raven System
or it will not function correctly.
o Section/Boom Offsets: These are measured from the reference point to
the section. Sections should be set up from left to right. Section 1 is
the left-most section (looking in forward direction of motion). Section 2
should be adjacent to Section 1 and so on. [Additional GPS Offset Info]
¾ Forward Offset is the distance from the reference point to the front of the
section. Forward offset is aligned with the forward direction of motion. If the
section is aft (behind) the reference point, this number will be negative (-).
¾ Right Offset is the distance from the reference point to the left edge of the
section (not the center). Right offset is aligned perpendicular to the forward
direction of motion. If the left edge of the section is right (looking in forward
direction of motion) of the reference point, this number will be positive (+).
o
Boom Width: The boom widths are read directly from the Raven
System. These are not settable in the Pro 600 display and must be
configured correctly in the Raven System.
Table of Contents
14
Display Software Setup
(Raven Setup)
Table of Contents
Scroll Bar:
Scroll down to see
second page
15
Display Software Setup
(Raven Setup)
Table of Contents
This is the left edge
of the section,
not the center
Section widths
and status are
read from the
controller
Section is 15 ft
behind the
reference point
16
Display Software Setup
(Raven Run Screen Windows)
Step 3: Add Raven Run-Screen Windows (Toolbox>Layout)
o Example “A:Raven Set 1”
o “A:” – Denotes Com Port that Raven is connected to
o “1/2/3” – Denotes which product the window is for
¾ Raven 100 Series (440, 450, 660 etc.) have single product control only—run screen
windows for products 2 and 3 will not apply
o Master – Raven Master
¾ This does not actually control the Raven Master. For Standard Valve Systems the Pro 600
Display sends a rate of 0.1 to the Raven Controller when the Master Button is off (Raven
System will beep, but will not go the 0.1 rate). For Fast Close Valve Systems the Pro 600
Display sends a 0.0 rate to the Raven Controller when the Master Button is off, which
effectively shuts it off.
¾ A black “On” button indicates the master is on. A gray “On” button indicates the master is
off.
o Set Rate – Raven Set
¾ This window shows the set application rate for the product being applied.
¾ Touching the rate window brings up the rate control screen.
o Actual Rate – Raven Act
¾ This window shows the actual application rate as reported by the Raven System.
Table of Contents
17
Display Software Setup
(As-Applied Run Screen Windows)
Add As-Applied Run-Screen Windows as needed (Toolbox>Layout)
o There are seven available product layers. For each one, you can display the
amount of product applied, the average rate for the product applied, and the area
for the product applied.
o Product Amount Applied
¾ This is the total amount of product applied for the current task. This is calculated based on
the actual application rate and the section widths of the active sections while in-work. This
means that if a section is turned off, no product amount applied is accumulated for that
section.
o Product Area Applied
¾ This is the area on which the product is applied for the current task. This is calculated
based on the section widths of the active sections while in-work. This means that if a
section is turned off, no product area is accumulated for that section. This is different from
the task area, which calculates area based on implement width only when in-work and does
not take into account sections that may be turned off.
o Product Average Rate
¾ This is the average rate at which the product has been applied for the current task. This is
calculated from the Product Amount Applied and the Product Area Applied.
Table of Contents
18
Display Software Setup
(Run Screen Layout)
Layout
Selection List
Actual Rate
Master
Set Rate
Table of Contents
19
Display Software Setup
(Run Screen Layout)
Run Screen 1
Layout
Actual Rate
Master
Set Rate
Table of Contents
20
Display Software Setup
(Run Screen: Master On)
Actual Rate
Master
ON = Black
Set Rate
Run Screen 1