1 Introduction
This publication details replacement of the battery
(B12454) fitted to the baseboard of the RVG200
Paperless recorder. The procedure must be carried
out by a trained technician.
Tools required
Medium flat-bladed screwdriver
2 For more information
Further information is available from:
www.abb.com/recorders
or by scanning these codes:
Sales Service
3 Safety
IMPORTANT NOTE
Dispose of the old components as detailed in the
Operating Instructions (OI/RVG200-EN).
ScreenMaster RVG200
paperless recorder
2 IN/RandC/006-EN Rev. A | ScreenMaster RVG200 | Paperless recorder | Battery replacement
4 Replacing the battery
1. Isolate the recorder from the power supply.
Referring to Fig. 4.1:
2. Remove the tamper evident seal A if fitted.
3. Using a medium flat-bladed screwdriver, unscrew jacking
screw B.
4. Remove chassis C from case D.
Referring to Fig. 4.2:
5. Locate the mounted battery E on the underside of the
case.
Referring to Fig. 4.3:
6. Remove the battery from the battery-mount F and fit a
new battery.
Referring to Fig. 4.1:
7. Insert chassis C into case D.
8. Using a medium flat-bladed screwdriver to secure jacking
screw B to case D.
9. Fit new tamper evident seal A (if required).
10. Restore power to the recorder and proceed to Section 5,
page 3.
CAUTION – Property damage
The recorder is vulnerable to electrostatic damage.
Wear an anti-static strap or place the instrument on
an anti-static workbench.
Fig. 4.1 Removing the recorder from its case
A
B
C
D
Fig. 4.2 Locating the battery
Important note
Dispose of the old battery as detailed in the
Operating instructions (OIRVG200-EN).
Fig. 4.3 Replacing the battery
E
F
ScreenMaster RVG200 | Paperless recorder | Battery replacement | IN/RandC/006-EN Rev. A 3
5 Setting the time and date
To access the Configuration menus:
1. Touch on the first Operator menus page.
2. Enter an operator password (if configured).
3. Select the Edit Configuration mode by touching the
button.
The System Configuration page is displayed:
4. Press Common.
The Common Configuration menu is displayed:
5. Select Time and press (next to the Date and time
box).
A warning dialog is displayed:
6. Press .
The Date and time menu is displayed:
7. Set the required time and date using the instrument
touchscreen. Once finished, press and exit and
save the configuration as normal.
Important note
Once the battery has been removed, the battery failed
icon is displayed on the front panel of the unit. To
restore normal operation, the correct time and date
must set.
Important note
Changing the time will potentially cause loss of
data. Ensure that all data archiving is up to date
before proceeding.
IN/RandC/006-EN Rev. A 12.2018
We reserve the right to make technical changes or modify the contents of this document
without prior notice. With regard to purchase orders, the agreed particulars shall prevail.
ABB does not accept any responsibility whatsoever for potential errors or possible lack of
information in this document.
We reserve all rights in this document and in the subject matter and illustrations contained
therein. Any reproduction, disclosure to third parties or utilization of its contents – in
whole or in parts – is forbidden without prior written consent of ABB.
© ABB 2018
ABB Limited
Measurement & Analytics
Howard Road, St. Neots
Cambridgeshire, PE19 8EU
UK
Tel: +44 (0)0870 600 6122
Fax: +44 (0)1480 213 339
Email: instrumentat[email protected]
ABB Inc.
Measurement & Analytics
125 E. County Line Road
Warminster
PA 18974
USA
Tel: +1 215 674 6000
Fax: +1 215 674 7183
abb.com/measurement
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4

ABB ScreenMaster RVG200 Battery Replacement Procedure

Type
Battery Replacement Procedure

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI