eSolutions DPM 2.0 User manual

Type
User manual

eSolutions DPM 2.0 is a device that can be used to configure advanced functionalities of your eProWallbox, such as DPM (Dynamic Power Management), load unbalance, and energy meter configuration. With DPM, you can set a contractual power limit to ensure that your EV charging does not exceed your grid connection capacity. It also enables load unbalance settings to manage the distribution of current among phases and avoid overloading.

eSolutions DPM 2.0 is a device that can be used to configure advanced functionalities of your eProWallbox, such as DPM (Dynamic Power Management), load unbalance, and energy meter configuration. With DPM, you can set a contractual power limit to ensure that your EV charging does not exceed your grid connection capacity. It also enables load unbalance settings to manage the distribution of current among phases and avoid overloading.

EN
Advanced functionalities setup
Installation manual - Annex
2
Advanced functionalities setup
Installation manual - Annex
TABLE OF CONTENTS
SECTION PAGE
1 INTRODUCTION ...................................................................................................................................... 3
2 DPM 2.0 INSTALLATION .................................................................................................................... 3
3 PROCEDURE ............................................................................................................................................... 6
3.1 Energy meter conguration ...................................................................................................................... 8
3.2 DPM ................................................................................................................................................................ 10
(a) DPM Pmax .................................................................................................................................................... 10
(b) DPM ENABLING ........................................................................................................................................... 11
3.3 LOAD UNBALANCE ..............................................................................................................................12
(a) Load unbalance enabling ..........................................................................................................................12
(b) Load unbalance current .............................................................................................................................12
3.4 DPM USER CONFIGURATION ........................................................................................................13
3
Advanced functionalities setup
Installation manual - Annex
1. INTRODUCTION
The following features on eProWallbox can be congured via Bluetooth.
DPM:
DPM enabling
DPM Pmax
DPM 2.0:
Electrical Installation
Conguration
Transformer ratio KI
DPM Type selection
Load Unbalance
Load unbalance enabling
Load unbalance current
2. DPM 2.0 INSTALLATION
1. Place the Power Meter provided after the main utility meter and before the split
power.
During the installation always refer to the meter installation manual
included in the package.
Utility Meter PowerMeter
Loads
Eletrical panel
RS485 Port
4
Advanced functionalities setup
Installation manual - Annex
2. For the three-phase or single-phase electrical connection, refer to the dedicated
meter installation manual included in the Power Meter package.
3. Feed the Modbus communication cables through the eProWallbox box sheath (C).
Suggested cable: STP class 5E, 0.5 mm2 section.
4. Use the following order for connecting the communication cables from the
PowerMeter to the eProWallbox. Starting from left on the eProWallbox RS485
output port CN12.
5. If included connect the Current Transformers as indicated in the meter installation
manual, paying attention to drawn through the clamp the line according to the
direction indicated on the sensor. The neutral cable must not be drawn through the
clamp.
PowerMeter
Gavazzi EM330 Gavazzi EM111 Finder 7M
CN12 Port
GND -+
A SC B
CN12 Port
GND -+
13 12 11 10
GND A- B+ T
CN12 Port
GND -+
7 6 5 4
GND B+ A- T
Do not try to install the PowerMeter if you are not qualied as a
professional electrician. Such behavior can cause serious danger and
harm to you and to the people, things or animals around you.
5
Advanced functionalities setup
Installation manual - Annex
EM111
CTA5X K
L
LN
L
N
1
2
EM330L3L2L1N
N
L1
L2
L3
4
5
6
7
8
9
CTA5X
CTA5X
CTA5X
6
Advanced functionalities setup
Installation manual - Annex
3. PROCEDURE
The preliminary steps for the next operations are the following:
1. Download and Install the application nRF Connect on your smartphone.
Free2move eSolutions suggests using an Android operating system
2. Open nRF Connect and Set a lter (e.g. “ePro) in order to see only eProWallboxes
in the homepag
3. Select Scan on the top right corner to identify the eProwallbox to be connected via
Bluetooth through its Bluetooth name
4. Once connected to the desired eProwallbox, select Unknown Services to begin
with the conguration
7
Advanced functionalities setup
Installation manual - Annex
The UUID is associated to a specic functionality
By clicking on the down arrow the specics of
the functionalities will be displayed
By clicking on the up arrow a new command can
be sent through Bluetooth
5. The Unknown Services contains all the parameters that can be written and read
through Bluetooth
8
Advanced functionalities setup
Installation manual - Annex
3.1 ENERGY METER CONFIGURATION
1. Enter the menu by tapping&holding for 1.5 second the central display button for
three-phase meter (or the lower part of the display for single-phase), until the
page with the password is shown. Skip to the next page by pressing press both
left and right (or upper and lower) display button.
2. Now tap on the left (or upper for single-phase) display button to navigate menu.
3. To congure the Gavazzi Meter, enter the parameters by tapping&holding the
central (or lower for single-phase) display button and change them with the left
(or upper for single-phase) button:
a. System mode: 3Pn (For three-phase meter only)
b. Modbus address: 1
c. BaudRate: 38.4 kbps
d. Parity bit: Even
4. To congure Finder Meter select COMMUNICATION command (COMM on single-
phase meter), press and hold to enter the menu. Here set:
a. Device address: 001
b. Bits per second (baud): 38400 bit/s
c. Parity: Even
d. Stop bit: 1
5. For three-phase Finder Meter only, select INSTALLATION, press and hold to enter
the menu. Set:
a. Connection mode: 3L+N “Arithmetic
6. Set the model of Power Meter installed on nRF Connect app:
Parameter: DPM_TYPE
This eld allows to select the Power Meter model installed
UUID: f0f924f8-34ce-4f1d-9791-b1b19ff3ffe4
TYPE: Uint8, select UINT8 on the app
VALUE: 00 → FINDER 7M.38.8.400.0212
01 → FINDER 7M.24.8.230.0210
02 → GAVAZZI EM330DINAV53HS1X
03 → GAVAZZI EM111DINAV51XS1X
9
Advanced functionalities setup
Installation manual - Annex
7. If installed, set the Transformer Ratio KI on nRF Connect app:
Parameter: TRANSFORMER_RATIO_KI
This value allows to set the Current Transformer ratio according to the installed sensors
UUID: 0c8d04fc-247c-4119-ab10-77ad3779310c
TYPE: Uint32, select UINT32 on the app
VALUE: Set the Transformer Ratio KI according to the values printed on the sensor.
E.g. 100/5 → KI = 20 (Hex value → 14)
150/5 → KI = 30 (Hex value → 1E)
10
Advanced functionalities setup
Installation manual - Annex
3.2 DPM
a. DPM PMAX
Parameter: DPM_PMAX
This eld contains the contractual power expressed in Watt
UUID: b4bc4914-1381-4294-acb0-776947becb9d
TYPE: Uint32, select UINT32 on the app
VALUE: min value 0, max value 70000
1. Identify the
UUID of the DPM
Pmax parameter
2. Click on the
up arrow next
to the Unknow
characteristic
3. Select UINT32 4. In “New value
eld insert the
contractual power
value, expressed
in Watt, from 0 to
70000.
Then click SEND
5. The new value
will appear on
the main page,
expressed in bytes
11
Advanced functionalities setup
Installation manual - Annex
b. DPM enabling
Parameter: DPM_ENABLED
This feature enable the DPM functionality
UUID: 9b5732b1-b557-40f7-ab72-fb00a3696132
TYPE: Boolean, select BYTE on the app
VALUE: 01 enabling, 00 disabling
c. At the end of the process, to make the changes effective, restart the eProWallbox
1. Identify the
UUID of the
DPM Enabling
parameter
2. Click on the
up arrow next
to Unknow
characteristic
3. Select BYTE 4. In “New value
eld insert:
01 to ENABLE
00 to DISABLE
Then click SEND
5. The new value
will appear on the
main page
12
Advanced functionalities setup
Installation manual - Annex
3.3 LOAD UNBALANCE
a. Load unbalance enabling
Parameter: LOAD_UNBALANCE_ENABLED
This function enables the load unbalance settings
UUID: aa29e099-f9dc-40a4-8612-afbb78c612df
TYPE: boolean, select BYTE on the app
VALUE:
00 → FALSE, disabled
01 → TRUE, enabled
b. Load unbalance current
Parameter: LOAD_UNBALANCE_CURRENT
This value denes the max allowable phases current unbalance expressed in mA
UUID: f9217d22-b703-4a2a-a565-38662afc1a9c
TYPE: Uint32, select UINT32 on the app
VALUE:
0 → Min value
32000 → Max value, in mA
13
Advanced functionalities setup
Installation manual - Annex
3.4 DPM USER CONFIGURATION
Download eSolutions Charging, a dedicated App available for Android and iOS that
allows you to congure your wallbox and monitor the operating parameters
1. Log in on the App and associate the wallbox to your prole by framing the
personal QR code printed on your wallbox, on the back of the external cover.
2. Select the wallbox connected to the PowerMeter and go to settings. Then click on
Home Power.
3. Set your Contractual Power value in kW as indicated in your electricity bill by
moving the scroll button. This parameter allows the wallbox to understand the
power value not to exceed.
4. Click on DPM to enable the Home Power functionality.
Registered ofce
Free2move eSolutions S.p.A.
Piazzale Lodi, 3
20137 Milan – Italy
www.esolutions.free2move.com
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14

eSolutions DPM 2.0 User manual

Type
User manual

eSolutions DPM 2.0 is a device that can be used to configure advanced functionalities of your eProWallbox, such as DPM (Dynamic Power Management), load unbalance, and energy meter configuration. With DPM, you can set a contractual power limit to ensure that your EV charging does not exceed your grid connection capacity. It also enables load unbalance settings to manage the distribution of current among phases and avoid overloading.

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI