5.2 Start the Pump ........................................................................................................................................50
5.3 Operation................................................................................................................................................. 51
5.4 Shut down the pump ...............................................................................................................................53
5.5 Final Alignment........................................................................................................................................ 54
6 Maintenance..................................................................................................................................................... 55
6.1 Preventative Maintenance.......................................................................................................................55
6.2 Maintenance schedule ............................................................................................................................55
6.3 Bearing Maintenance ..............................................................................................................................56
6.3.1 Oil Lubricated Bearings................................................................................................................. 57
6.3.2 Grease lubricated bearings (6-18 inch sizes only) ........................................................................57
6.4 Shaft-seal maintenance........................................................................................................................... 59
6.4.1 Mechanical-seal maintenance.......................................................................................................59
6.4.2 Packed stuffing-box maintenance .................................................................................................59
6.5 Packed Stuffing Box ................................................................................................................................ 60
6.6 Connection of Sealing Liquid................................................................................................................... 61
6.7 Labyrinth Seals........................................................................................................................................ 62
6.8 Disassembly ............................................................................................................................................ 62
6.8.1 Pump Disassembly Precautions ................................................................................................... 62
6.8.2 Disassembly precautions .............................................................................................................. 62
6.8.3 Remove the coupling guard .......................................................................................................... 63
6.8.4 Tools required................................................................................................................................ 64
6.8.5 Disassemble the guard / drive (v-belt configuration)..................................................................... 64
6.8.6 Disassemble the back-pullout / elbow (cast back-pullout design only) ......................................... 68
6.8.7 Disassemble the back-pullout elbow with casing (cast back-pullout design only) ........................ 69
6.8.8 Disassemble the power frame from elbow (fabricated elbow design only) ................................... 69
6.8.9 Remove the liner (option).............................................................................................................. 72
6.8.10 Remove the standard impeller .................................................................................................... 72
6.8.11 Remove the sealed impeller ........................................................................................................ 73
6.8.12 Remove mechanical seal with optional adapter (cast back-pullout design only) ........................ 73
6.8.13 Remove the Mechanical Seal (Fabricated Elbow Design only) .................................................. 74
6.8.14 Disassemble the packed box (cast back-pullout design only)..................................................... 74
6.8.15 Remove the Packing Chamber(Fabricated Elbow Design Only) ................................................ 75
6.8.16 Remove the drip pan................................................................................................................... 75
6.8.17 Disassemble the bearing housing ...............................................................................................76
6.8.18 Remove the bearing (1MXR-3MXR configuration)......................................................................78
6.8.19 Remove the bearing (4MXR-6MXR configuration)......................................................................79
6.8.20 Disassemble the cooling coil (optional) sight glass / breather and plugs.................................... 80
6.9 Pre-assembly inspections .......................................................................................................................81
6.9.1 Inspect the elbow / casing / liner (options) ....................................................................................81
6.9.2 Inspect impeller vane .................................................................................................................... 81
6.9.3 Inspect the shaft............................................................................................................................ 82
6.9.4 Inspect the shaft sleeve ................................................................................................................ 82
6.9.5 Inspect the mechanical seal / restrictor bushing ........................................................................... 82
6.9.6 Inspect the stuffing box (packed pumps only)............................................................................... 82
6.9.7 Inspect the bearing housing ..........................................................................................................83
6.9.8 Inspect the bearings...................................................................................................................... 83
6.9.9 Labyrinth seals and O-rings .......................................................................................................... 83
6.9.10 Critical axial flow dimensions and tolerances..............................................................................84
6.9.11 Maximum bolt torque values N-M | Ft-Lb ...................................................................................84
Table of Contents
2 AF (6"-36") MXR Bearings Installation, Operation, and Maintenance Manual