Miller JETLINE CW5 CIRCUMFERENTIAL, MH000000 Owner's manual

  • Hello! I am an AI chatbot trained to assist you with the Miller JETLINE CW5 CIRCUMFERENTIAL Owner's manual. I’ve already reviewed the document and can help you find the information you need or explain it in simple terms. Just ask your questions, and providing more details will help me assist you more effectively!
Jetline Engineering, 15 Goodyear Street, Irvine, CA 92618
Telephone: (949) 951-1515 • Fax: (949) 951-9237
Web Site:
www.jetline.com • E-mail: [email protected]
INSTALLATION MANUAL
for
Model CW5
Circumferential Welder
July 2010
OM-CW5-INSTALL-07-2010
CW5 Circumferential Welder Installation
The installation, operation and maintenance guidelines set out in this manual will enable you to
maintain the equipment in peak condition and achieve maximum ef ciency with your welding opera-
tion. Please read these instructions carefully to become aware of every advantage.
Only experienced personnel familiar with the operation and safe practice of
welding equipment should install and/or use this equipment.
Use general industry good practices to move, lift, and install this equipment.
Experienced, professional riggers should be employed for the installation process.
NOTICE
CAUTION
TOOLS REQUIRED
Forklift or overhead crane with 7000 lb (3175 kg) lifting capacity
Two lifting straps rated at 4000 lb (1800 kg) each
Hand tools - hammer, screw driver, hex keys, wrenches
Air or electric impact drill
Refer to foundation layout drawing - 80007-CW5-144-FD RevA
CW5 Circumferential Welder Installation
INSTALLATION INSTRUCTIONS FOR CW5 CIRCUMFERENTIAL WELDER
1. Remove track and posts from shipping crate.
2. Set posts up per location on assembly. Do not secure
posts to concrete until the plate track has been attached
to the post.
3. After mounting the plate track to the xed posts, be sure that both posts are vertical using a
level. Continue with installation of the track making sure that the track is level and the face
is vertical. Check these with a level. These adjustments are done on the mounting anges
attached to the posts.
4. Now that the track has been installed to the posts, anchor the posts with concrete anchors,
securing the xed posts to the concrete oor. (Refer to foundation layout drawing -
80007-CW5-144-FD RevA.)
Bolt plate track to posts.
CW5 Circumferential Welder Installation
5. Move the lathe into position per assembly print. Insure that the track and track face are
parallel with the lathe centerline. This can be checked with a plumb bob.
The base of the lathe is tted with jack screws used to make adjustments to keep the base
level and straight with the track. You can now anchor the lathe to the concrete oor using
concrete anchors. (Refer to foundation layout drawing - 80007-CW5-144-FD RevA.)
6. Pick the carriage up by the lifting ring and install onto the plate track by sliding the bearings
over the plate track.
Once the carriage is installed, put end of travel stops back onto the plate track to keep the
carriage from being pushed off the track.
7. Now that the welding head is on the plate track, and the xture has been secured to the oor,
the power, air, gas, and water can be hooked up to the system.
8. Note: Make certain all fasteners are tight before using the system and that the posts and track
have been secured to the concrete oor. Hydraulics are self-contained and require power
only.
The welding system is now ready to be used.
Lifting Ring
CW5 Circumferential Welder Installation
enilte
8020
/