CW5 Circumferential Welder Installation
5. Move the lathe into position per assembly print. Insure that the track and track face are
parallel with the lathe centerline. This can be checked with a plumb bob.
The base of the lathe is fi tted with jack screws used to make adjustments to keep the base
level and straight with the track. You can now anchor the lathe to the concrete fl oor using
concrete anchors. (Refer to foundation layout drawing - 80007-CW5-144-FD RevA.)
6. Pick the carriage up by the lifting ring and install onto the plate track by sliding the bearings
over the plate track.
Once the carriage is installed, put end of travel stops back onto the plate track to keep the
carriage from being pushed off the track.
7. Now that the welding head is on the plate track, and the fi xture has been secured to the fl oor,
the power, air, gas, and water can be hooked up to the system.
8. Note: Make certain all fasteners are tight before using the system and that the posts and track
have been secured to the concrete fl oor. Hydraulics are self-contained and require power
only.
The welding system is now ready to be used.