8. Close drain valve and further tighten packing yoke screws, if necessary, to stop leakage.
9. Open valves and check again for leakage once valves and packing have reached full operating temperature.
Repacking the seat:
1. Remove stem bushing set screw; loosen with a 5/32” hex wrench to clear bushing threads (Figure 2).
2. Remove stem, stem bushing, packing yoke, all old packing, and packing washer. Inspect packing chambers for
pitting or steam cut. Polish as necessary with fine emery cloth. Replace valve if the chamber cannot be repaired
by polishing with a fine emery cloth.
3. Insert a 3/4" socket with an extension into the valve body, onto the valve seat and remove valve seat by rotating
counter-clockwise. Note: old style valves contain a separate valve seat and seat holder. Remove seat holder with
a 1/2" socket extension.
4. Lift out seat and seat gasket. Dispose of the gasket.
5. Clean and lubricate threads of seat with Molykote "G" high temperature lubricant, or equal.
6. Install new seat gasket and new seat. Tighten seat using 40 ft.-lb.(54 newton-meters) torque.
7. Lubricate threads of stem, stem bushing, and cap screws with Molykote "G" high temperature lubricant, or equal.
Install packing washer, yoke, stem, and stem bushing.
8. Repack stem as described above. Retighten stem bushing locking set screw. Be sure to check for leakage and
re-tighten cap screws (if necessary) shortly after boiler is returned to service.
FIELD INSTALLATION OF LIVE LOADING KIT (RK-34) FOR SG777 SERIES WATER GAGE VALVES:
The RK-34 Live-Loading kit is available to improve the performance and service live of Clark-Reliance Steel Water Gage
Valves that are already installed in the field. Live-loading offers a more leak-free valve, resists damage from vibration,
pressure variances, time and service, and other wear factors.
Installation steps are as follows:
1. Remove stem bushing locking set screw; loosen to clear bushing threads (Item G). Remove and discard the old
cap screws and flat washers from the packing gland (Item E).
2. Remove the stem bushing (Item B) and the stem (Item A). Then remove the packing gland (Item E) and the stem
packing cartridge (Item F).
3. Inspect packing chamber for pitting or steam cut. Polish as necessary with fine emery cloth. Replace valve if the
chamber cannot be repaired with fine emery cloth.
4. Install the new packing cartridge (Item F) in the packing chamber. Then re-install the packing gland, stem and
stem bushing. Tighten the stem bushing and install the lock screw.
5. Lubricate both sides of the spring washers (Item H) and the cap screws (item C) with Molykote "G" high
temperature lubricant, or equal. Install the washers and cap screws as shown in Figure 3. Note the orientation of
the spring washers.
6. Tighten the cap screws evenly to guide the packing gland squarely into the packing chamber. Apply 10 ft-lbs of
torque to each cap screw.
7. Cycle the valve several times to assure that the stem will operate smoothly. Reassemble the operating chains.
Fi
ure 3