INSTRUCTIONS for
INSTALLATION OF
NEW METERS IN METER KITS
When replacing a voltmeter or ammeter with one of
the new dustproof type meters, it is necessary to drill
three .140-in. diameter holes (No. 28 drill bit) before
the meter can be installed. Proceed as follows:
1. Disconnect main input power to the control.
2. Remove front control panel and meter to be
replaced.
3. Using template supplied below as Fig. 1, mark
and drill (with a No. 28 drill bit) the new mounting
holes.
4. After mounting the meter, refer to the appropriate
control instruction booklet for correct electrical
connections:
UEC-7 F-12-543
UEC-8 F-12-747
UCC-8 F-12-515
UCC-9 F-12-593
AGC-1 F-12-553
PCC-8 F-12-528
5. Reassemble the front panel to the control
cabinet.
6. The following voltmeters and ammeters are
available:
New Replaces
Voltmeter Part Number Part Number
0-80 VAC 2062415 996597
0-80-VDC 2062416 2062053
Ammeter
0-1000 AAC 2062418 996599
0-1500 AAC 2062419 2062049
0-500 ADC 2062421 639598
0-800 ADC 2062422 2062051
0-1000 ADC 2062423 639586
0-1500 ADC 2062424 639592
F-12-829 6/97 Printed in U.S.A.
Fig. 1 - Mounting Hole Pattern Template
  • Page 1 1

ESAB Installation of new Meters in Meter Kits Installation guide

Type
Installation guide

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI