10/20 Product Code: 2069T
Made in China to TQB Brands Pty Ltd specifications.
Visit us at www.tqbbrands.com.au Page | 4
ASSEMBLY, OPERATION, PREVENTITIVE MAINTENANCE
1. FEATURES
This TradeQuip hydraulic utility crane provides the lifting power to lift a 900kg load when fully retracted and 450kg when fully
extended. The boom pivots 360˚ at the base for easy loading and unloading. The boom extends from 930mm to 1295mm
and the base swivels to help you get the best angle when hoisting items into your utility bed. Saves time and effort loading
and unloading cargo from a ute, truck or dock. Get extra lift where you need it most with this utility crane that easily lifts
loads to 900kg. The utility crane also folds down when not in use.
2. ASSEMBLY
Unpacking: after removing the packing material, make sure the product is in perfect condition and that there are no visible
damaged parts.
1. Place the Bearing (#29) into the Bearing Sleeve (#30), then assemble into the Base (#32).
2. Assemble the Turntable (#24) onto the Bearing (#29) so that the Turntable (#28) and Base (#32) join together. Rotate
the Turntable (#28) onto the Base (#32) and ensure the assembly is stable.
3. Assemble the Grease Fitting (#31), Binding Bolt (#34), and Bakelite Nut (#33) onto the Base (#32).
4. Assemble the Bearing (#41) into the hole of the Large Pulley (#4), then using the Bolt M16x110 (#42) connect the Post
Weldment (#5) and Boom (#9). At the same time insert the Bushing (#3) and assembled Large Pulley (#4) ensuring the
assembled Large Pulley is centred, then tighten with a Flat Washer (#24), Lock Washer (#23) and Nut M16 (#22).
5. Assemble the Ram (#25) onto Boom (#9) using Bolt M16x80 (#21), Flat Washer (#24), Lock Washer (#23) and Nut M16
(#22). Assemble the bottom of the Ram (#25) onto the Post Weldment (#5), using Bolt M16x90 (#26), Flat Washer
(#24), Lock Washer (#23) and Nut (#22).
6. Assemble the Winch (#1) onto the Post Weldment (#5) by tightening 3 x Bolt M10x20 (#37), Lock Washer (#38), Flat
Washer (#39).
7. Put the Handle Cover (#36) onto the long end of Handle (#35), then insert the handle into the hollow sleeve on the Post
Weldment (#5), lock with the R-Pin (#40).
8. Assemble the Bearing (#17) into the Small Pulley (#16), then insert the Bolt M12x85 (#12) through the Boom Extension
(#11), Bearing (#17), and tighten using Flat Washer (#15), Lock Washer (#14) and Nut M12 (#13).
9. Fix the Base (#32), then put the Post Subassembly onto the Base Subassembly, connect using 6x Bolts M12x40 (#27),
Lock Washer (#14), Flat Washer (#15), and Nut M12 (#13).
10. Insert the Boom Extension Subassembly into the Boom Subassembly and lock using Bolt M14x100 (#10), Lock Washer
(#7), Flat Washer (#8) and Nut M14 (#6).
11. Insert one end of the Winch Wire (#2) through the Small Pulley (#16), Boom Extension (#11), Boom (#9) and large Pulley
(#4), then coil on the rope roll of the Winch (#1). Lock the wire into place on the side plate of the Winch by inserting it
through the four holes on the side plate.