Pella 99605207 Installation guide

Type
Installation guide
102 Main Street, Pella, IA 50219
www.pellagaragedoors.com
WL Supplement
Pella® Garage Doors
WIND LOAD INS TAL L ATION INS TR UC TIONS
Wind Load Models
Page 1 of 2
©AGD 04.2014 FORM #878 PRINTED IN USA
1
Typical Bottom Bracket
7/16” Bolt Retainers
(1) Installed Per Roller
STRUT INSTALLED ABOVE
BOTTOM FIXTURE
2”-20 ga. Struts Attached with
(2) 1/4-20 x 3/4”
Hex Head Screws
at End & Center Stiles
1
2
3
2
Typical End Hinge
3
Typical Center Hinge
3”-20 ga. Struts Attached with
(2) 1/4-20 x 3/4”
Hex Head Screws
at End & Center Stiles
2”-20 ga. Struts Attached with
(2) 1/4-20 x 3/4”
Hex Head Screws
at End & Center Stiles
Hex Head Screws
Strut
Strut
These Instructions are in addition to the Basic
Instructions included with your door.
The Jamb Brackets, Struts and Bolt Retainers, illustrated
below, must be installed exactly as shown to conform
to Wind Load regulations.
Failure to install the Jamb Brackets, Struts and Bolt
Retainers exactly as shown, will result in your door not
passing local inspection.
Strut Installation
Note: Perform Strut Installation prior to installing
sections into the opening.
Step 1:
Place Bottom Section on padded sawhorses.
Step 2:
Determine the correct Strut and location from the Section and
Strut Location chart below.
Note: To determine whether your strut is 2” or 3“ measure the
height of the Strut (Figure A).
Example: Bottom Section requires (1) 2” Strut at the bottom of
the section (Figure 1) and (1) 3“ Strut at the top of the section
(Figure 2&3)
Step 3:
Install each Strut using (2) 1/4-20 x 3/4” Hex Head Screws
into each Center and End Stile (Figure B & C). A total of (6)
1/4-20 x 3/4” Hex Head Screws per Strut.
Step 4:
Repeat for each section as required.
C
B
Hex Head Screws
End Stile
Center Stile
A
Strut
2” or 3”
Sec on
Top Sec
on
Int. Sec
on 2" Strut & 3" Strut - Top
Int. Sec
on
Bo
om Sec on 2" Strut & 3" Strut - Top
Section and Strut Location Chart
STRUT INSTALLED ON
ROLLER CARRIER
STRUT INSTALLED
ABOVE END HINGE
CORRECT STRUT LOCATION
AFTER INSTALLATION
Rollers
with 5” Stems
7/16” Bolt Retainers
(1) Installed Per Roller
3”-20 ga. Struts Attached with
(2) 1/4-20 x 3/4”
Hex Head Screws
at End & Center Stiles
2”-20 ga. Struts Attached with
(2) 1/4-20 x 3/4”
Hex Head Screws
at End & Center Stiles
These Installation Instructions are in addition to
the Basic Instructions included with your door.
The Jamb Brackets, Struts and Bolt Retainers, illustrated
below, must be installed exactly as shown to conform
to Wind Load regulations.
Failure to install the Jamb Brackets, Struts and Bolt
Retainers exactly as shown, will result in your door
not passing local inspection.
Strut Installations
Note: Perform Strut Installation prior to installing
sections into the opening.
Step 1 :
Place Bottom Section on padded sawhorses.
Step 2:
Determine the correct Strut and location from the Section
and Strut Location chart below.
Note: To determine whether your strut is 2” or 3” measure
the height of the Stut (Figure A).
Example: Bottom Section requires (1) 2”Strut at the
bottom of the section (Figure 1) and (1) 3” Strut at the
top of the section (Figure 2 & 3).
Step 3:
Install each Strut using (2) 1/4-20 x 3/4” Hex Head Screws
into each Center and End Stile (Figure B & C). A total
of (6) 1/4-20 x 3/4” Hex Head Screws per Strut.
Step 4:
Repeat for each section as required.
2" Strut & 3" Strut - Top
2" Strut & 3" Strut - Top
WL Supplement
Pella® Garage Doors
WIND LOAD INS TAL L ATION INS TR UC T IONS
Wind Load Models
Page 2 of 2
©AGD 04.2014 FORM #878 PRINTED IN USA
Bottom Bracket
Jamb Bracket
Vertical Track
Roller Carrier
Top Fixture
Bolt Retainer Installation
Step 1:
Insert Roller into Roller Carrier (Figure A).
Step 2:
Hammer the 7/16“ Bolt Retainer onto the Roller Shaft, using a
9/16” socket or 9/16” Closed End Wrench (shown) and a
hammer (Figure A). Once the Bolt Retainer has been installed it
will be virtually impossible to remove without damaging the
retainer.
Note: Bolt Retainers will need to be installed on Rollers in both
Bottom Fixtures (Figure B), all Roller Carriers (Figure C) and
both Top Fixtures (Figure D) as well.
Step 3:
Repeat for each Roller as required
Additional Jamb Bracket Attachment (Figure E)
Continued from the Basic Instructions, Page 3, Step 11.
Step 1:
Starting with the slot at 10“ from the bottom of the vertical
of the track as shown in Figure F.
Step 2:
Attach the Jamb Bracket with (1) 1/4” x 5/8” Track Splice Bolt
and (1) 1/4”-20 Hex Nut. Hand tighten. Repeat this step
attaching the three other Jamb Brackets into the slots at 21”, 42”
& 63“ from the bottom of the track.
Note: Failure to install the Jamb Brackets in the correct slots
will result in your door not passing local inspection.
Note: This will allow for slight adjustments during the
installation.
Note: 1/4”-20 Hex Nuts always go on the outside of the track.
Continue with Step 12 of the Basic Instructions.
B
C
D
10”
21”
42”
63”
E
F
A
7/16” Bolt Retainer
Hex Nut to outside
of track
Right Side Assembly
Shown
to Middle of Slot
Right
Right Side Assembly
Track Splice Bolt
102 Main Street, Pella, IA 50219
www.pellagaragedoors.com
  • Page 1 1
  • Page 2 2

Pella 99605207 Installation guide

Type
Installation guide

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI