HANDI-MATE FLOORING KIT INSTALLATION GUIDE
HANDI-MATEFLOORING KIT
FLOOR BEAM 1740
FLOOR JOINER 2000
FLOOR BEAM 2090
YOUR HANDI-MATE
SHED MODEL
WHAT YOU ARE
GOING TO NEED
HM1
1x BOX 1 1x BOX 2
HM2
1x BOX 3
HM3
1x BOX 4
HM4
2x BOX 3
HM5
1x BOX 2
1x BOX B
HM6
2x BOX 1
2x BOX A
HM7
2x BOX 2
2x BOX B
HM8
2x BOX 3
2x BOX A
HM9
2x BOX 4
2x BOX B
HM10
3x BOX 3
3x BOX A
HM11
1x BOX 1
1x BOX A
HML
Use the guide below to ensure you select the correct flooring components for your shed.
COMPONENTS
COMPONENT SELECTION
Handi-Mate Flooring kits are compatable with floor sheets or timber decking. Stratco oer a range of timber flooring options,
enquire in-store or at stratco.com.au for more information.
FLOORING OPTIONS
BROCGNI
« SCAN THIS QR CODE TO FIND A STRATCO NEAR YOU
1300 155 155
stratco.com.au
All brands and logos/images accompanied by ® or ™ are trade marks of Stratco (Australia) Pty Limited. ® Copyright July 2023
<450mm
!
!
Ensure a maximum distance between
Beams of 450mm.
Evenly space out Beams.
SLIDING INTO JOINER
FLOOR BEAM FLOOR JOINER
BROCHF
Install the Beams into the shed, ensuring the Beams are evenly spaced apart. Spacings between Beams should not exceed 450mm.
Flooring can be installed once the Floor Kit is installed. Lay down the flooring and fasten to the Floor Beams/ Joiners with
appropriate screws.
20mm decking pine, use 10G x 45mm Metal Decking Screws.
10-15mm floor sheets, use 10G x 35mm Metal Decking Screws.
HM6, HM7, HM8, HM9, HM10, HM11 and HML Sheds require 1 Floor Beam and 1 Floor Beam Joiner to achieve the required length.
INSTALLATION
  • Page 1 1
  • Page 2 2

Stratco Handi-Mate Flooring Kit Installation guide

Type
Installation guide

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI