  • Hello! I am an AI chatbot trained to assist you with the enphase Envoy Terminal Block Wiring Quick start guide. I’ve already reviewed the document and can help you find the information you need or explain it in simple terms. Just ask your questions, and providing more details will help me assist you more effectively!
Getting Started Guide: Envoy-S and IQ Envoy Terminal Block Wiring All rights reserved. © Enphase 2019
1
Getting Started Guide: Terminal Block Wiring for the Envoy-S, IQ Envoy, and IQ Combiner 3 / 3C
This guide is for the solar energy professional who will install the Enphase Envoy-S Metered™, the Enphase IQ Envoy™, the Enphase IQ Combiner 3or the
Enphase IQ Combiner 3C™ and current transformers (CTs). Refer to the appropriate Installation and Operation Manual for complete installation instructions
and safety warnings.
Envoy-S Metered (ENV-S-AM1-120 M)
All terminal wiring will be completed on the
job site.
The Production CT must be fed by Service
Line 1.
IQ Envoy (ENV-IQ-AM1-240) and
IQ Combiner 3 (X-IQ-AM1-240-3) and
IQ Combiner 3C (X-IQ-AM1-240-3C)
Power terminal and Production CT
terminals are pre-wired in the IQ Combiner
3 and the IQ Combiner 3C.
Consumption CT terminals will be wired on
the job site.
Not Used
Not Used
/