ATHI/ATVI QUICK START INSTRUCTIONS
THIS INSTRUCTION IS NOT A COMPLETE SOURCE
OF INFORMATION ON THE TRANSFER EQUIP-
MENT. INSTALLATION SHOULD NOT BE STARTED
UNTIL THE ENTIRE INSTRUCTION BOOK HAS
BEEN REVIEWED AND UNDERSTOOD. FAILURE TO
FOLLOW INSTRUCTIONS CAN RESULT IN DEATH,
SEVERE PERSONAL INJURY, OR PROPERTY
DAMAGE.
Step 1: Mount the transfer switch on a flat rigid surface
(Figure 1). Shim if necessary. For seismic mounting
requirements, check the instruction book.
!
WARNING
Figure 1 Mounting Details
Shim If Necessary
View A
See Detail A
QS4500TE0001
Page 2
Effective 6/01
Step 2: Install power cables. Cables shall be sized and
installed per National Electrical Code, refer to NFPA70.
The cable must be sized within the specified cable size
range on the side of the cable connectors.
Connect cables and torque to correct value indicated on
the label near the lugs in the following order: [1] Load
Cables* (T1, T2, T3), [2] Normal or Utility Supply (N1,
N2, N3), [3] Emergency and Generator Supply (E1, E2,
E3). For 4 pole transfer switches, connect load cables
(T4), normal or utility supply (N4), and emergency or
generator supply (E4). Refer to Figure 2 for the location
of all parts discussed in this document.
*
Load cables on switches using the vertical design MUST be
connected and torqued BEFORE installing the SUPPLY
cables (Figures 3 and 4).
Figure 2 300A, 3 Pole, Automatic Transfer Switch Interior
Normal Power Source
Molded Case Switch
Power Panel
Transformer Panel
Load Lugs (Top Entry)
Motor Disconnect (S3)
Voltage Selection
Connectors
Engine Start Contacts
Emergency Power Source
Molded Case Switch
Transfer Mechanism
Indicator Wheel
Manual Operating
Handle
Neutral Connections
QS4500TE0001
Page 3
Effective 6/01
Figure 3 Vertical Power Panel
Figure 4 Horizontal Power Panel
Step 3: Turn generator OFF at the Generator Control
Panel. This will prevent unexpected activation of the
generator.
Step 4: Connect Engine Generator Control to
Terminals 51, and 52 (Red) (Figure 5). This contact is
CLOSED whenever the engine generator is needed,
and should be connected to a generator controller.
NEVER connect directly to a starter solenoid or ignition
system.
Figure 5 Engine Start Contact Location
Tighten Cables Into Terminals
See Detail B
Detail B
Typical
Engine Start Contacts
(Red Terminals)
QS4500TE0001
Page 4
Effective 6/01
Step 5: Apply Utility (Normal) Power. If the switch is
properly applied for the system voltage ordered, the dis-
play should work and the
Normal Source (Source 1)
Available
LED should light (Figure 6). Using a voltmeter,
check for proper system voltage on the normal and load
terminals. Check all phases on a three-phase switch.
Voltage measurements should be taken phase to phase
and phase to neutral.
Figure 6 IQ Transfer Logic (Utility Supplying Load)
The following lights must be ON:
Source 1 Available
Source 1 Preferred
Source 1 Connected
Load Energized
Perform LED lamp test by depressing
and holding. All LED’s should turn on.
If not, contact factory for replacement.
QS4500TE0001
Page 5
Effective 6.01
Step 6: To view setpoints, press the <Display Select>
pushbutton until the Set Points LED lights. Use the
Table 1 Setpoint Possibilities
Setpoint Setpoint Units Description Range Factory Default
TDES Minutes:Seconds Time Delay Engine Start 0 to 120 seconds 0
TDNE Minutes:Seconds Time Delay Normal to Emergency 0 to 1800 seconds 0
TDEN Minutes:Seconds Time Delay Emergency to Normal 0 to 1800 seconds 0
TDEC Minutes:Seconds Time Delay Engine Cooloff 0 to 1800 seconds 0
NOMF Volts Nominal Frequency 50 or 60 Hz As ordered
NOMV Volts Nominal Voltage 120 to 600 volts As ordered
1UVD Volts Source 1 Undervoltage Dropout 97% to 50% of NOMV 80% of NOMV in volts
2UVD Volts Source 2 Undervoltage Dropout 97% to 50% of NOMV 80% of NOMV in volts
1UVP Volts Source 1 Undervoltage Pickup 99% to (1UVD + 2%) 90% of NOMV in volts
2UVP Volts Source 2 Undervoltage Pickup 99% to (2UVD + 2%) 90% of NOMV in volts
1OVD Volts Source 1 Overvoltage Dropout 105% to 120% 115% of NOMV in volts
2OVD Volts Source 2 Overvoltage Dropout 105% to 120% 115% of NOMV in volts
1OVP Volts Source 1 Overvoltage Pickup (1OVD - 2%) to 103% 110% of NOMV in volts
2OVP Volts Source 2 Overvoltage Pickup (2OVD - 2%) to 103% 110% of NOMV in volts
1UFD Hertz Source 1 Underfrequency Dropout 90% to 97% of NOMF
2UFD Hertz Source 2 Underfrequency Dropout 90% to 97% of NOMF
1UFP Hertz Source 1 Underfrequency Pickup (1UFD + 1Hz) to 99%
2UFP Hertz Source 2 Underfrequency Pickup (2UFD + 1Hz) to 99%
1OFD Hertz Source 1 Overfrequency Dropout 103% to 110% of NOMF
2OFD Hertz Source 2 Overfrequency Dropout 103% to 110% of NOMF
1OFP Hertz Source 1 Overfrequency Pickup (1OFD - 1Hz) to 101%
2OFP Hertz Source 2 Overfrequency Pickup (2OFD - 1Hz) to 101%
TDN Minutes:Seconds Time Delay Neutral 0 to 120 seconds 0
TDNLD Load Decay Neutral 0=Disable, 1=Enable 0
LDCY Volts Load Decay Voltage 10% to 30% of NOMV 10%
PRFSRC Preferred Source 0=None, 1-Src1, 2=Src2 1
EXER Clock Exerciser 0=Disable, 1=Enable 0
EXLD Exercise Load Transfer 0=Disable, 1=Enable 0
PEDAY Exercise Day 1 to 7 (1=Sunday)
PEH Clock Exercise Hour 12am to 11pm
PEMIN Clock Exercise Minute 00 to 59
MANTR Retransfer Mode 0=Automatic, 1=Manual 0
CTDNE Commit/No Commit 0=Not, 1=Commit
TMODE Engine Test Mode (Pushbutton) 0=No Load, 1=Load, 0
2=Disable
TER Hours:Minutes Engine Test/PE Run Time 1 minute to 10 hours 1
TPRE Minutes:Seconds Pre Transfer Signal Time 0 to 120 seconds 0
GENNO Number of Generators 0=Dual Utility, 1
1=One (Source 2)
2=Dual Generator
PHASE Phases 1 or 3 As Ordered
TSEQ Minutes:Seconds Time Delay Load Sequencing 0 to 120 seconds 0
PT PT Ratio 2 (2:1) to 500 (500:1) 2
TDEF Seconds Time Delay Engine Fail 0 to 6 seconds 0
<Step> pushbutton to step through the set points
(Figure 6 and Table 1).
QS4500TE0001
Page 6
Effective 6/01
Step 7: To change or add a setpoint, place the <Run -
Program> switch on the rear of the IQ Transfer Logic
unit in the
Program
position (Figure 7). The red LED
next to
Program
on the front display will flash (Figure 6).
Figure 7 IQ Transfer Logic (Rear View)
Press the <Display Select> pushbutton until the Set
Points LED lights. Use the <Step> pushbutton to step
through the setpoints.
Use the <Increase> and <Decrease> pushbuttons to
change the setpoint.
When finished changing setpoints, return the <Run-
Program> switch to the
Run
position and wait. The dis-
play should display the word
Program
and the red LED
next to
Program
will go out. When the display goes
blank, the setpoints have been changed to their new
values.
QS4500TE0001
Page 7
Effective 6/01
Step 8: Manually start the engine generator at the gen-
erator controller (Figure 8). With the generator running,
check that the
Emergency Source (Source 2) Available
LED is lit. Press the <Display Select> pushbutton to
display the voltage and frequency on Source 2. Then
using the <Step> pushbutton, step through the phase
voltages, frequency and message display. If the source
message indicates that the source is
Good,
shut down
the generator and place the genset controller in the
Auto
operating position. If the message indicates a
problem with the source, the setpoints should be
reviewed, and the generator checked for proper voltage
and frequency output.
Step 9: Initiate a
Load Test
from the front panel of the
IQ Transfer (Figure 9). This may be done by making the
TMODE setpoint
1
and pressing the <Engine Test>
pushbutton. The generator should start, the ATS should
transfer and run on the generator for the set test inter-
val, then proceed to a TDEN countdown and return to
NORMAL. While the tansfer switch is connected to
emergency, use a voltmeter to check for correct system
voltage on the load terminals of the transfer switch.
Check all phases on a three-phase system. Voltage
measurements should be taken phase to phase and
phase to neutral. A
load test
will cause a momentary
power outage during transfer.
Figure 8 IQ Transfer Logic (Utility Supplying Load and
Generator Running)
Figure 9 IQ Transfer Logic (During Test)
The following lights must be ON:
Source 1 Available
Source 1 Preferred
Source 1 Connected
Source 2 Available
Load Energized
The following lights must be ON:
Source 1 Available
Source 1 Preferred
Source 2 Available
Source 2 Connected
Load Energized
QS4500TE0001
Page 8
Cutler-Hammer
Pittsburgh, Pennsylvania U.S.A.
Effective 6/01 (ISI)
Style QS4500TE0001 H01
Printed in U.S.A.
Step 10: ATHI/ATVI Power Failure Test - Initiate a Load
Test by simulating an actual power failure.
(1) This should be done by opening the upstream
breaker or fused disconnect switch.
(2) If the ATS is Service Equipment Rated with no
upstream disconnect, use the Normal Control Circuit
Disconnect to simulate a power failure (Figure 10).
This can be found in one of two places. The first
would be located directly beside the normal breaker.
The second would be located on the transformer
panel/customer connection panel. The normal con-
trol circuit disconnect is the disconnect marked
Normal.
The disconnect switch should be in the
ON
position for normal operation. Turning the switch to
the OFF position will simulate a normal power out-
age.
Figure 10 Control Disconnect
(3) The generator should start and the ATS should
transfer to Emergency.
(4) After transfer, close the upstream breaker, or
close the Normal Control Circuit Disconnect. The
TDEN timer should begin counting, and, when com-
plete, the ATS should transfer to Normal. The En-
gine Cooldown Timer should time out and shut the
emergency power unit down.
NOTICE
While performing testing, if an undesired or undoc-
umented result occurs, first contact the local
Genset dealer. If the result is not corrected, contact
the Cutler-Hammer Product Integrity Center at
1-800-354-2070.
OFF Position
ON Position
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8

Eaton Cutler-Hammer QS4500TE0001 Quick Start Instructions

Type
Quick Start Instructions

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI