  • Hello! I am an AI chatbot trained to assist you with the Dextra Dil-0496-0001 Tanek Installation guide. I’ve already reviewed the document and can help you find the information you need or explain it in simple terms. Just ask your questions, and providing more details will help me assist you more effectively!
Tanek Installation
DIL-0496-0001 Revision - D 14/02/2023
220-240V / 50-60Hz
IP65
IK10
1.
Unpack the luminaire and undo the 10 x M5 6 Lobe
Pin Drive screws securing the frame. Remove the
frame and proceed to hang it on the tethers.
2.
Remove the screw holding the gear tray in place. (1)
Push the tray to one side. (2) Lift and tilt the gear tray
to remove.
3.
Knockout the semi-shear from the housing if bringing
the cable in through the side. Cornice Housing - Drill
20mm cable hole in desired location.
Drill the rear of the housing if a central cable entry is
required instead.
4.
Drill suitable fixings to suit required installation.
Please note, it is the contractor’s responsibility to
ensure the holes are suitably sealed. Failure to do so
will invalidate the luminaire's IP rating.
5.
Feed flex through preferred cable entry (contractor to
supply suitable grommet). Make relevant electrical
connection (all fittings will have 6 pole terminals due
to generic housing to tray connector loom).
6.
Connect the tray to the housing using the internal
loom.
2
1
Side
Rear
WARNING: Luminaire must be earthed. Risk of electric shock from LED boards if operated with cover
removed. Installation / operation outside of luminaires intended scope invalidates warranty. Suitable only for
domestic / light industrial / industrial applications within the scope of EN55015. Tested to compliance with
BSEN 60598: specification for general requirements and tests. Must be installed by a suitably qualified person
in accordance with all relevant legislation. Ambient operating temperature of 0°C to 25°C. If maximum
operating temperature is exceeded luminaire will automatically dim / switch off. Terminal blocks are rated to
16A unless stated otherwise. The light source is non replaceable. LUMINAIRES WITH EMERGENCY PACK:
When supply is isolated battery output terminals may be live if battery is connected. Isolate mains and battery
before servicing. Emergency luminaires require unswitched live connection taken from same phase as
switched supply. When unswitched supply is connected status indicator illuminates green, when unswitched
supply is disconnected indicator extinguishes and luminaire operates in emergency mode. 24 hour charge
period required before undertaking full discharge test. Emergency test sheets provided should be used to
record all emergency tests. Batteries should be replaced when 3 hour duration is not met. Excessive switching
of permanent live may result in premature battery failure. Battery electrolyte can be harmful to eyes / open
wounds, do not puncture, if electrolyte touches skin / eyes flush with water. Do not incinerate batteries.
Terminal Labelling:
Power
L1 Switched Live
E Earth
N Neutral
Emergency
L2 Unswitched Live
DA/AT3 DALI Autotest
DA/AT3 DALI Autotest
Dimming
-/D1/DA Analogue/DSI/DALI
+/D2/DA Analogue/DSI/DALI
L3 Switch Dim /
Corridor Function
Tanek Installation
DIL-0496-0001 Revision - D 14/02/2023
7.
(1) Slide one end of the gear tray into the housing. (2)
Then lower the gear tray into place. Secure the tray
with the screw that was removed earlier in step 2.
8.
Offer the frame up to the housing.
9.
Rest the frame on top of the housing. Insert and
fasten the 10 x M5 6 Lobe Pin Drive screws.
10.
Installation is now complete.
11.
12.
2
1
10 x
/