American Power Conversion 240-320kW User manual

Category
Power supply units
Type
User manual
APC Silcon
240-320kW 480V UPS
Installation Guide
Copyright ©2001 APC Denmark ApS
This manual is subject to
change without notice and does not represent
a commitment on the part of the vendor.
2 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
Thank You!
Thank you for chosing an APC Silcon UPS. Please read this Installation Guide thoroughly prior to
installing the system. It provides important information on safe and efficient installation.
The installation and use of this product must comply with national, federal, state, municipal and
local codes.
Safety Symbols used in this manual
WARNING!
Indicates a hazard which, if not avoided, could result in injury or death.
CAUTION!
Indicates a hazard which, if not avoided, could result in damage to
the product or other property.
NOTICE!
Read and pay attention to this important information.
WARNING!
This UPS unit contains hazardous AC and DC voltages. Only qualified electricians should install the
UPS, AC line and external batteries, and must be familiar with batteries and battery installation.
Before installing, maintaining or servicing the UPS, shut off the UPS and disconnect all sources of AC
and DC power.
As the UPS has no built-in disconnection devices to switch off external AC and DC input power, ensure
that disconnection devices are provided as separate parts in connection with the installation!
The installer must provide each external disconnecting device for this UPS system with labels with the
following text:
“Isolate the Uninterruptible Power Supply (UPS) as instructed in this guide before working on circuit”.
AC and/or DC voltage will always involve a potential risk of AC voltage at UPS output generated from
either batteries or utility. To avoid equipment damage or personal injury, always assume that there
may be voltage at UPS output.
This system is equipped with an auto-start function. If activated the system may start without warning.
Refer to “Programming” section for information on de-activation.
TEST BEFORE YOU TOUCH!
To reduce the risk of fire or electric shocks, install the UPS and external batteries in a temperature and
humidity controlled indoor area, free of conductive contaminants.
UPS batteries are high-current sources. Shorting battery terminals or DC terminals, DC busbars can
cause severe arcing, equipment damage and injury. A short circuit can cause a battery to explode.
Always wear protective clothing and eye protection and use insulated tools when working on batteries.
CAUTION!
This unit contains components sensitive to electrostatic discharge (ESD). If you do not follow the ESD
procedures, you may cause severe damage to electronic components.
PLEASE RECYCLE
The shipping materials for the APC Silcon UPS are recyclable. Please save for later use or dispose of
them appropriately.
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 3
Contents:
1.0 Introduction 5
1.1 Tools and Equipment 5
2.0 Unpacking/Identification of Equipment 6
3.0 Installation 9
3.1 Requirements on Site 9
3.2 Dimensions and Weight 9
3.2.1 Dimensions and Weight of UPS 9
3.3 Footprints 10
3.3.1 UPS Cabinet Footprints 10
3.3.2 Conduit Entrance Plate in bottom of the system 11
3.3.3 Top Cable Entry 12
4.0 External Connection 13
4.1 Connecting the UPS 13
4.1.1 Connecting AC and DC Power Cables (Dual Utility Connection) 14
4.1.2 Seperation of AC from DC1 and DC2 16
4.1.3 Top or Bottom Cable Entry 17
4.1.4 Dual and Single Utility Supply 18
4.1.5 Switching from Dual to Single Utility Input 20
4.1.6 Connection Terminals 22
4.1.7 Torque Specifications 22
4.1.8 Grounding 22
4.2 System Integration Interface 24
4.2.1 Connecting the System Integration Interface Board (SII-board) 25
4.3 Parallel Board 29
4.4 Relay Board 31
4.4.1 Relay Board Functions 31
4.4.2 Cable Sizes 33
4.5 Communication Interface / Smart Slot 34
4.5.1 Connections 34
4.6 SmartSlot for APC Silcon 240-320kW UPS 34
4.6.1 SmartSlot Accessories 35
4.6.2 Multiple SmartSlot Installation - introduction 35
4.6.3 APC Silcon Battery Cabinets 37
4.7 Battery Breaker Box 39
4.7.1 Interconnection 40
4.7.2 Mounting and Connection of Battery Breaker Box 40
4.7.3 UPS with External Battery via Battery Breaker Box 41
4.8 UPS Installations in Computer Rooms 41
4.8.1 EPO Principle 42
4.8.2 Emergency Power Off (EPO) for UPS 44
5.0 Programming 46
5.1 Parameters 46
5.1.1 Programming Keys 47
4 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
5.1.2 Programming Example - Switch to Bypass Operation 47
5.2 System Configuration 49
5.2.1 Programming Example - Change Boost Charge Voltage to 446V 50
5.2.2 Programming Example - Change to Output Isolation
Transformer Available 51
5.3 Programming Parameters for Advanced Parallel Operation. 52
5.3.1 Description of Settings. 52
5.3.2 Programming Example 52
5.4 Battery Monitor 53
6.0 Options/Accessories 54
6.1 Diagrams for Service Bypass Panel for Single Operation,
Single and Dual Utility 54
6.2 Seismic Anchoring 62
6.2.1 Mounting Seismic Anchoring 63
6.3 NEMA 12 Cover (IP31) 64
6.3.1 Mounting NEMA 12 Cover 64
6.4 Remote Display 65
6.4.1 Extension of Remote Display Communication Distance 65
6.4.2 Remote Display Installation 67
6.4.3 Remote Display Use 68
6.5 Isolation Transformer Module 69
6.5.1 Requirements on Site 69
6.5.2 Cabinets and Dimensions 70
6.5.3 Footprints 70
6.5.4 Connecting Isolation Transformer 70
6.5.5 Recommended Cable Lugs and Crimping Tools 70
6.5.6 Isolation Transformer - Diagram Delta WYE configuration (Dyn11) 71
6.5.7 Isolation Transformer Grounding 71
6.5.8 Principale Diagrams for Isolation Transformer 72
6.6 Intersystem Synchronization Unit 74
7.0 System Specifications 75
7.1 Technical Data 75
8.0 Appendix 76
8.1 Table 1. Installation Planning Data 76
8.2 Table 2 – Table 310-16 77
9.0 Warranty 79
9.1 APC Silcon Series® Limited Factory Warranty 79
10.0 How to Contact APC 80
Introduction
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 5
1.0 Introduction
Power regulation varies from country to country, and the information given in this installation
guide can therefore only be of a general nature. Electricians should always refer to national and
local electrical codes prior to installing the UPS system.
1.1 Tools and Equipment
This section lists all tools and equipment required to install all UPS configurations. See also
section 4 for further details on connection.
Tools:
10mm socket
13mm socket-deep
17mm socket
3/4” or 19mm socket-deep
3/4” or 19mm combo wrench
Small flathead/regular screwdriver
#3 philips screwdriver
Compression lug crimping tool
Knock-out set (for conduit)
Equipment:
Compression lugs for cable terminations
Cable to Service Bypass Panel from system feeder
Cable to UPS input from service bypass panel
Cable to Service Bypass Panel from UPS output
Cable from Service Bypass Panel to customer distribution
Cable to UPS input from external batteries/external Battery Breaker Box
(systems = with external battery)
Solid core, control wire to UPS from Service Bypass Panel
Solid core, control wire to UPS from external batteries/external Battery Breaker Box
Conduit necessary for above listed cabling
WARNING!
Heavy equipment. To prevent personal injury or equipment damage, take extreme care when
handling and transporting UPS cabinet and equipment.
WARNING!
Ensure that front doors are in place and that internal front cover is fastened by screws before
attempting to lift or transport the system.
6 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
Unpacking/Identification of Equipment
2.0 Unpacking/Identification of Equipment
Copy of type label (without battery):
NOTICE!
Unless otherwise specified by the shipping company, use a fork lift to unload equipment from
pallet.
1. Unpack system.
2. Verify compliance between type label on reverse side of front door and system ordered.
Check input and output voltage.
3. Copy the type label data to label copy below for easy identification of the system.
4. Use a fork lift to transport the system to installation site.
Unpacking/Identification of Equipment
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 7
Main UPS system
The UPS is a battery back-up system. Unconditioned power is fed to UPS input. The UPS
supplies conditioned power.
Service Bypass Panel
AC utility power for critical load is led through the service bypass panel while UPS is shut
down for maintenance
Battery Breaker Box
The APC Battery Breaker Box is required if the UPS is installed with an external battery. The
Battery Breaker Box provides overcurrent and short-circuit protection.
Battery Cabinet
For storage and protection of battery bank.
8 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
Unpacking/Identification of Equipment
Isolation Transformer
Isolation Transformers are used for galvanic isolation of utility power and conditioned power.
Seismic Anchoring
Seismic anchoring stabilizes the UPS in seismic areas.
NEMA 12 C
over
NEMA 12 covers are used in locations with potential risks of liquid discharge or leakage above
UPS system.
Remote Display
Use remote display to monitor UPS
NOTICE!
Contact your local APC representative or APC Support if you have any questions
Installation
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 9
3.0 Installation
3.1 Requirements on Site
All system parts are accessible from front or top of UPS. Cable entries are accessible from top
or bottom. The system may be installed close to walls as long as free space is allowed for system
doors to open.
For ventilation and service purposes allow for free space of a minimum of 3 foot above and in
front of UPS. Never install systems in direct sunlight.
3.2 Dimensions and Weight
3.2.1 Dimensions and Weight of UPS
WARNING!
For safety reasons do not stand on UPS. Keep UPS cabinet surface free of any objects
UPS
Height
inch/mm
Width
inch/mm
Depth
inch/mm
Weight
lbs./kgs
240kW 480V 70.86/1800 74.80/1900 31.50/800 4432/2014,5
320kW 480V 70.86/1800 74.80/1900 31.50/800 4432/2014,5
Cabinet
74.80/1900 in./mm wide
70.86/1800 in./mm
10 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
Installation
3.3 Footprints
3.3.1 UPS Cabinet Footprints
NOTICE!
Dimensions indicated in inches / milimeters and lbs. / kgs
74.80/1900
73.85/1876
71.05/1805
70.86/1800
62.20/1580
59.44/1510
54.20/1377
51.45/1307
42.40/1077
32.56/827
29.80/757
3.74/95
0.95/24
0
0
1.02/26
1.81/46
6.14/156
7.87/200
14.37/365
15.94/405
25.98/660
30.47/774
31.50/800
REAR
COM
DC
UTILITY 1
OUT-
PUT
UTILITY2
FRONT
Installation
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 11
3.3.2 Conduit Entrance Plate in bottom of the system
Cable entries need to be punched in the UPS cabinet. Follow diagram for correct orientation of
power and control cables to be led into the UPS.
0
10.14/257.5
19.78/502.5
30.39/771.9
FRONT
COM
COM
UTILITY 1
UTILITY 2 OUTPUT DC
LEFT
RIGHT
REAR
12 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
Installation
3.3.3 Top Cable Entry
Cable entries need to be punched in the UPS cabinet. Follow diagram for correct orientation of
power and control cables to be led into the UPS.
17.72/450
11.61/295
7.68/195
0
0
3.31/84
16.28/413.5
26.12/663.5
REAR
FRONT
RIGHT
LEFT
UTILITY 1-2/ OUTPUT/ DC
COM
External Connection
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 13
4.0 External Connection
4.1 Connecting the UPS
Prior to connecting the UPS, refer to section 6: Options and Accessories to ensure that UPS
options are correctly interphased.
To access cable terminals, open front door, remove screws and lift off the 4 front covers
(remember earth wire on rear side). Power cable entry at bottom: Remove front covers 2 and 3.
Power cable entry at top: Remove front covers 1 and 2. Remove cover 4.
WARNING!
Read warnings on page 2 of this manual before continuing.
NOTICE!
Always keep AC, DC and communication cables separate.
1
2
3
4
Connecting AC
and DC
Connecting Ground
Connecting
communication
UPS system without cover and doors
cables
power cables
UPS system with cover– doors open
14 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
External Connection
4.1.1 Connecting AC and DC Power Cables (Dual Utility Connection)
Top bar – Utility 2 (L1, L2, L3)
Bottom bar – Output (N/E, L1, L2, L3)
Bottom bar – Utility 1 (N, L1, L2, L3)
Top bar – Ext. DC (X003±, X004±)
Connection in the
bottom of the
cabinet
External Connection
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 15
WARNING!
Bottom cabinet connection must be grounded.
E
N
L1
L2
L3
N
L1
L2
L3
Utility 2 – X002
Output – X005
Ext. DC
Utility 1 – X001
Utility 1
X001
Ext. DC
Utility 2
X002
Output
X005
Dual Utility Connection
Seen from front
Seen from side
16 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
External Connection
4.1.2 Seperation of AC from DC1 and DC2
Use the 2 pieces of polycarbonate (supplied with the UPS) to separate AC from DC1 and DC2.
Standard length of polycarbonate adjusted for top cable entry. Adjust length of polycarbonate
to fit bottom entry where applicable.
WARNING!
Supply the UPS from grounded 3-wire/4-wire WYE service.
NOTICE!
Ensure correct phase rotation of input voltage.
NOTICE!
Keep UPS input and output conductors in separate conduits.
NOTICE!
Keep AC and DC conductors in separate conduits.
NOTICE!
Keep batteries 1 and 2 (DC conductors) in separate conduits.
WARNING!
Keep UPS power conductors and UPS control wiring in separate conduits.
Polycarbonate
Polycarbonate
External Connection
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 17
4.1.3 Top or Bottom Cable Entry
For top cable entry, move copper angle bar to bottom.
Unscrew bolt, take out the split, move the angle bar down,
insert split, and tighten the bolt
Angle bar
18 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
External Connection
4.1.4 Dual and Single Utility Supply
The UPS is fitted with dual utility input as standard. If dual utility is not available or not
needed, a small modification has to be made. See section 4.1.5 switching from dual to single
utility input.
WARNING!
UPS units contain hazardous AC and DC voltages. Only qualified electricians should install UPS,
AC line and external batteries, and must be familiar with batteries and battery installation.
Before installing, maintaining or servicing the UPS, shut off the UPS and disconnect all sources
of AC and DC power.
As the UPS has no built-in disconnection devices to switch off external AC and DC input power,
ensure that disconnection devices are provided as separate parts in connection with the
installation!
The installer must provide each external disconnecting device for this UPS system with labels
with wording as follows:
Isolate the Uninterruptible Power Supply (UPS) as instructed in this guide
before working on circuit
AC and/or DC voltage will always involve a potential risk of AC voltage at UPS output generated
from either batteries or utility. To avoid equipment damage or personal injury, always assume
that there may be voltage at UPS output.
This system is equipped with an auto-start function. If activated the system may start without
warning. Refer to Programming Parameters for information on de-activation.
TEST BEFORE YOU TOUCH!
To reduce the risk of fire or electric shocks, install the UPS and external batteries in a
temperature and humidity controlled indoor area, free of conductive contaminants.
UPS batteries are high-current sources. Shorting battery terminals or DC terminals or DC
busbars can cause severe arcing, equipment damage and injury. A short circuit can cause a
battery to explode. Always wear protective clothing and eye protection and use insulated tools
when working with working near batteries.
CAUTION!
This unit contains components sensitive to electrostatic discharge (ESD). If you do not follow the
ESD procedures, you may cause severe dammage to electronic components.
External Connection
990-4049
Installation Guide APC Silcon 240-320kW 480V UPS 19
Working Principle of Dual Utility (2 utility supplies)
Working Principle of Single Utility (1 utility supply)
NOTICE!
Max. phase shift between utility 1 and 2: less than
±
3.
Refer to section 7.0 System Specifications for frequency tolerance of utility 1 and 2, and voltage.
Utility 1 supports the load in normal operation. Utility 2 supports the load through the static and
service bypass switch.
NOTICE!
Refer to section 7.0 System Specifications for frequency and voltage tolerance of utility 1.
Utility 1 or 2 supports the load in normal operation or through the static service bypass switch.
Q10
Q1
Q2
Q3
Utility 2
Output
Utility 1
Utility 1
Utility 2
APC Silcon UPS
Q1
Q2
Q3
Output
APC Silcon UPS
Utility 1/2
Utility 1/2
20 Installation Guide APC Silcon 240-320kW 480V UPS
990-4049
External Connection
4.1.5 Switching from Dual to Single Utility Input
Follow steps 1 and 2 to switch from dual to single input.
1) Remove fiber bar (55322) by unscrewing bolts and by mounting copper bars as below
2) Switch the connector in Con3 to Con1.
In the static switch the
following modifications
have to be made for
single utility input
Fiber bar
Copper bars
  • Page 1 1
  • Page 2 2
  • Page 3 3
  • Page 4 4
  • Page 5 5
  • Page 6 6
  • Page 7 7
  • Page 8 8
  • Page 9 9
  • Page 10 10
  • Page 11 11
  • Page 12 12
  • Page 13 13
  • Page 14 14
  • Page 15 15
  • Page 16 16
  • Page 17 17
  • Page 18 18
  • Page 19 19
  • Page 20 20
  • Page 21 21
  • Page 22 22
  • Page 23 23
  • Page 24 24
  • Page 25 25
  • Page 26 26
  • Page 27 27
  • Page 28 28
  • Page 29 29
  • Page 30 30
  • Page 31 31
  • Page 32 32
  • Page 33 33
  • Page 34 34
  • Page 35 35
  • Page 36 36
  • Page 37 37
  • Page 38 38
  • Page 39 39
  • Page 40 40
  • Page 41 41
  • Page 42 42
  • Page 43 43
  • Page 44 44
  • Page 45 45
  • Page 46 46
  • Page 47 47
  • Page 48 48
  • Page 49 49
  • Page 50 50
  • Page 51 51
  • Page 52 52
  • Page 53 53
  • Page 54 54
  • Page 55 55
  • Page 56 56
  • Page 57 57
  • Page 58 58
  • Page 59 59
  • Page 60 60
  • Page 61 61
  • Page 62 62
  • Page 63 63
  • Page 64 64
  • Page 65 65
  • Page 66 66
  • Page 67 67
  • Page 68 68
  • Page 69 69
  • Page 70 70
  • Page 71 71
  • Page 72 72
  • Page 73 73
  • Page 74 74
  • Page 75 75
  • Page 76 76
  • Page 77 77
  • Page 78 78
  • Page 79 79
  • Page 80 80

American Power Conversion 240-320kW User manual

Category
Power supply units
Type
User manual

Ask a question and I''ll find the answer in the document

Finding information in a document is now easier with AI