INSTALLATION GUIDE
Disconnect the power when servicing or performing maintenance to the Aladdin
Storage Lift. Electricity can kill!
GETTING STARTED:
1. is installation guide is for the Aladdin Storage Lift which is rated to handle up to a
500lb load. Do not exceed a 500lb load.
2. Only install this lift system where there is ample space between the roof rafters and
attic oor joists. Do not lift loads into the attic that are taller than the attic. is will cause
damage to the loads, the storage lift, the roof, and the ceiling.
3. Study the ‘Warnings and Safety Precautions’ section in the owner’s manual.
4. Read the ‘Installation Guide’, studying the drawings carefully, and learn each part and
step before installing the Aladdin Storage Lift.
5. e Aladdin Storage Lift frames, chassis, and supports should be installed by a
licensed framer or trim carpenter. All line and low voltage electrical work should be
performed by a licensed electrician. Consult a structural engineer to conrm installation
and load capacity of the ASL500 can be safely supported by existing structure.
6. Open the boxes and examine the parts received. Included should be the following:
Motor drive assembly, drive shaft, end plates, cart cables, cart assembly, support
straps, limit switches, hardware, wiring, ceiling support frame, cart springs, and a
Keyswitch Controller.
INSTALLATION TIPS:
1. When installing the Motor Drive Assembly and the Bearing Plate Assembly, the
measurement of 74 ¾ inches center to center between the frames is crucial for Drive
Shaft alignment. See STEP 8.
2. When reinstalling pulley wheels and spacers after feeding cart cables, DO NOT over
tighten ½ inch bolt. See STEP 10.
3. On Motor Drive Assembly side, make sure the cables are feeding over the top of the Cable
Safety Switch Bar. See STEP 10.
4. Alignment of the cart cables on the helical grooving of the Drive Shaft is essential for
smooth operation of the Storage Lift. See STEP 18.
5. Make sure the cables are rolling o the top of the spools. See STEP 10 & 15.
6. Make sure the cable is inserted in the Motor Shuto Switch Bar. See STEP 14.
MATERIALS NEEDED:
1. One sheet of 3/8 plywood cut to 68 ½” x 44”.
2. One sheet 1/4 nished plywood cut to 83 ½” x 48” (not to exceed 20 lbs).
5