2" Turf INSTALLATION INSTRUCTIONS:
INSTALLATION INSTRUCTIONS:INSTALLATION INSTRUCTIONS:
INSTALLATION INSTRUCTIONS:
Dig footing at proper location 24"1. wide x 50" deep.
Place base post into footing and 2. support in a plumb condition with
the outside edge of the pipe tangent
to the outside of the foul line.
Rotate the post so that the panels
are to the inside of the field.
Repeat for other foul line.3. After concrete has cured 48 hrs.4. place top sections on the bases and
lock down with set screws.
1
Scale: 1:25
Date: 03-19-07
SportsPlay Equipment, Inc.
(314) 389-4140
By: Candy
PART NO. & DESCRIPTION
5432
5642 Natural Bridge
St. Louis, MO 63120
551-528 20' Foul Pole W/Wing
Foul Pole
Grade
Finished (3-1/2" O.D.
Concrete
3/4" Re-Bar x 46" places per footing
(Not included, to be provided by installer).
These are typical footing dimensions for
average soil conditions
48"
24"